Afcons creates milestone by excavating 7.32 km of Tunnel T49 in J&K
RAILWAYS & METRO RAIL

Afcons creates milestone by excavating 7.32 km of Tunnel T49 in J&K

Afcons Infrastructure Limited creates significant milestones by excavating 7.32 km of 12.75 km-long tunnel under extreme conditions in Jammu & kashmir. Milestone was attained on the Udhampur Srinagar Baramulla Rail Link project (USBRL) on Feb 15, 2022, with the advancement of Tunnel T49 between Sumber and Arpinchala Stations on the Katra-Banihal Section.

T49 is a 12.75 km-long tunnel and to be the longest tunnel of the Indian Railways surpassing the Peer Panjal Tunnel of 11.2 km on the Banihal-Qazigund section. The south portal of Tunnel T49 is located in the picturesque Sumber Village at an altitude of 1,400 m, while the north portal of the tunnel is situated near Arpinchala Village at an altitude of 1,600 m.

Afcons, a critical player in the strategic project, made it to the breakthrough point from the north portal despite considerable geological challenges.

While executing the tunnel from the north portal, Afcons' engineers excavated 4.07 km from a single audit. It is the most critical and longest length implemented by any agency from a single audit. No other agency in the entire USBRL project has excavated such a long distance from a single phase. Amidst the challenge of working in extremely cold conditions (as low as -10 degrees centigrade) during the winter months, the team faced another significant hurdle. There was water ingress of 40-50 litres per second which made tunnelling extremely challenging.

Since they were operating on a downward gradient, on average, they had to dewater nearly 2 lakh kWh units per month.

The water ingress was due to multiple aquifers and nullahs crossing the tunnel alignment, the Project Manager said. Over 60% of the tunnel length was implemented in very poor rock class. But extremely high deformation was noticed in a 1.5 km stretch of the tunnel.

To overcome this, the team adapted different construction techniques such as enlargement of tunnel profile and introduced steel fibre reinforced concrete to speed up the progress. They commenced an excavation in 2015 and throughout excavated under particularly poor geology.

The original scope was later updated to accommodate an additional 3.6 km escape tunnel which brought about a change in alignment. But we were able to complete the entire project within schedule. This tunnel is a significant achievement for Indian Railways and Afcons. From heavy snowfall and heavy rains, which restricted vehicle movement every year, to local issues and extremely poor geology, they are happy to have passed them all and complete a significant assignment for the nation.

Afcons Infrastructure Limited is a construction and engineering firm headquartered in Mumbai and part of Shapoorji Pallonji (SP) Group, which has a legacy of more than 150 years.

Image Source

Also read: Railways connects longest tunnel T-49 on Katra-Banihal section

"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

Afcons Infrastructure Limited creates significant milestones by excavating 7.32 km of 12.75 km-long tunnel under extreme conditions in Jammu & kashmir. Milestone was attained on the Udhampur Srinagar Baramulla Rail Link project (USBRL) on Feb 15, 2022, with the advancement of Tunnel T49 between Sumber and Arpinchala Stations on the Katra-Banihal Section. T49 is a 12.75 km-long tunnel and to be the longest tunnel of the Indian Railways surpassing the Peer Panjal Tunnel of 11.2 km on the Banihal-Qazigund section. The south portal of Tunnel T49 is located in the picturesque Sumber Village at an altitude of 1,400 m, while the north portal of the tunnel is situated near Arpinchala Village at an altitude of 1,600 m. Afcons, a critical player in the strategic project, made it to the breakthrough point from the north portal despite considerable geological challenges. While executing the tunnel from the north portal, Afcons' engineers excavated 4.07 km from a single audit. It is the most critical and longest length implemented by any agency from a single audit. No other agency in the entire USBRL project has excavated such a long distance from a single phase. Amidst the challenge of working in extremely cold conditions (as low as -10 degrees centigrade) during the winter months, the team faced another significant hurdle. There was water ingress of 40-50 litres per second which made tunnelling extremely challenging. Since they were operating on a downward gradient, on average, they had to dewater nearly 2 lakh kWh units per month. The water ingress was due to multiple aquifers and nullahs crossing the tunnel alignment, the Project Manager said. Over 60% of the tunnel length was implemented in very poor rock class. But extremely high deformation was noticed in a 1.5 km stretch of the tunnel. To overcome this, the team adapted different construction techniques such as enlargement of tunnel profile and introduced steel fibre reinforced concrete to speed up the progress. They commenced an excavation in 2015 and throughout excavated under particularly poor geology. The original scope was later updated to accommodate an additional 3.6 km escape tunnel which brought about a change in alignment. But we were able to complete the entire project within schedule. This tunnel is a significant achievement for Indian Railways and Afcons. From heavy snowfall and heavy rains, which restricted vehicle movement every year, to local issues and extremely poor geology, they are happy to have passed them all and complete a significant assignment for the nation. Afcons Infrastructure Limited is a construction and engineering firm headquartered in Mumbai and part of Shapoorji Pallonji (SP) Group, which has a legacy of more than 150 years. Image Source Also read: Railways connects longest tunnel T-49 on Katra-Banihal section

Next Story
Infrastructure Urban

VECV Sales Rise 7.8 Per Cent In May 2026

VE Commercial Vehicles recorded sales of 7,978 units in May 2026, compared to 7,401 units in May 2025, registering growth of 7.8 per cent. This included 7,789 units from the Eicher brand and 189 units from the Volvo brand.Eicher branded trucks and buses reported sales of 7,789 units during the month, up 7.3 per cent from 7,258 units a year earlier. In the domestic commercial vehicle market, Eicher sales rose 9.1 per cent to 7,375 units from 6,758 units in May 2025.Exports declined 17.2 per cent to 414 units from 500 units in the corresponding month last year. Volvo Trucks and Volvo Buses recor..

Next Story
Infrastructure Urban

Table Space Strengthens DESYN Leadership Team

Table Space has announced strategic leadership appointments within DESYN, its integrated Design and Build business, as it looks to strengthen operations across key enterprise and GCC markets in India. DESYN was launched as a strategic extension of Table Space’s workspace solutions portfolio to meet rising demand for agile, high-quality and rapidly deployable enterprise workspaces.Shruti Ookabhoy has joined DESYN as Executive Director and will lead the Design vertical, focusing on design capability, operational excellence and team development across markets. She brings over 22 years of experi..

Next Story
Infrastructure Transport

Concord Associate Bags Rs 2.79 Bn Kavach Order

Concord Control Systems said its associate company, Progota India, has received a Rs 2.79 bn domestic order from Indian Railways for the supply, installation, testing and commissioning of on-board Kavach 4.0 loco equipment.The order is scheduled for execution within 12 months and strengthens Concord’s role in India’s railway safety and signalling ecosystem. Kavach is India’s indigenous automatic train protection system, designed to improve operational safety by helping prevent signal passing at danger and reducing collision risks.Gaurav Lath, Joint Managing Director, Concord Control Syst..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement