CMRL Completes Final U-Girder Casting for Phase II Corridor 5
RAILWAYS & METRO RAIL

CMRL Completes Final U-Girder Casting for Phase II Corridor 5

Chennai Metro Rail (CMRL) has completed the casting of all precast elements, including the final U-girder, for Phase II Corridor 5 between Ullagaram and Sholinganallur. The completion marks a major construction milestone for the elevated corridor and concludes the precasting work required for the package.

A total of 3,126 precast elements have been cast for the corridor. These comprise 1,041 I-girders, 892 U-girders, 871 pier arm segments, 303 pier caps and 19 portal shells. The U-girders form the largest individual category of elements produced for the package.

CMRL said the package recorded the highest U-girder production among the Phase II project packages, with 892 units cast. The precast operation used 98,052 cubic metres of concrete, 18,550 tonnes of reinforcement steel and 3,010 tonnes of high-tensile strands, indicating the scale of materials deployed for the corridor’s structural components.

The work was carried out through collaboration between CMRL, general consultant AEON Consortium and contractor HCC-KEC Consortium. With casting completed, construction activity will now focus on installing the remaining U-girders and building the entry and exit structures. CMRL said these activities are progressing towards the timely completion of the Chennai Metro Phase II project.

The Ullagaram-Sholinganallur section is part of Corridor 5 under Phase II. Completion of the precast element casting provides the project team with the full set of manufactured structural components listed for this package, while installation and associated structural works continue at the corridor site. The latest milestone was outlined in a CMRL press note updated on 14 October 2026.

Chennai Metro Rail (CMRL) has completed the casting of all precast elements, including the final U-girder, for Phase II Corridor 5 between Ullagaram and Sholinganallur. The completion marks a major construction milestone for the elevated corridor and concludes the precasting work required for the package. A total of 3,126 precast elements have been cast for the corridor. These comprise 1,041 I-girders, 892 U-girders, 871 pier arm segments, 303 pier caps and 19 portal shells. The U-girders form the largest individual category of elements produced for the package. CMRL said the package recorded the highest U-girder production among the Phase II project packages, with 892 units cast. The precast operation used 98,052 cubic metres of concrete, 18,550 tonnes of reinforcement steel and 3,010 tonnes of high-tensile strands, indicating the scale of materials deployed for the corridor’s structural components. The work was carried out through collaboration between CMRL, general consultant AEON Consortium and contractor HCC-KEC Consortium. With casting completed, construction activity will now focus on installing the remaining U-girders and building the entry and exit structures. CMRL said these activities are progressing towards the timely completion of the Chennai Metro Phase II project. The Ullagaram-Sholinganallur section is part of Corridor 5 under Phase II. Completion of the precast element casting provides the project team with the full set of manufactured structural components listed for this package, while installation and associated structural works continue at the corridor site. The latest milestone was outlined in a CMRL press note updated on 14 October 2026.

Related Stories

Gold Stories

Next Story
Real Estate

IGBC Green Building Congress 2026 advances India’s net-zero agenda

The Indian Green Building Council (IGBC), part of the Confederation of Indian Industry (CII), opened the 24th edition of the Green Building Congress 2026 at the Jio World Convention Centre, Mumbai, with a focus on accelerating India's green and net-zero building movement. The three-day event, being held from 26 to 28 November, brought together policymakers, industry leaders and sustainability experts to discuss green buildings, climate-resilient infrastructure and sustainable communities.A key highlight of the inaugural session was the launch of five pilot rating systems: Green Retail, DigiBui..

Next Story
Real Estate

Maharashtra CM inaugurates fifth Model Sub-Registrar Office in Mumbai

Maharashtra Chief Minister Devendra Fadnavis has inaugurated a Model Sub-Registrar Office (SRO) in Lower Parel, Mumbai, taking the number of such centres launched in the state to five. The initiative aims to modernise property registration services through technology-enabled infrastructure and citizen-centric processes.Developed by the Government of Maharashtra in association with VFS Global and WE Excel Software, the Lower Parel centre follows the launch of Model SROs in Pune, Bandra Kurla Complex in Mumbai, Navi Mumbai and Nagpur.The centres provide facilities for registering property-relate..

Next Story
Infrastructure Transport

NHBF hails Indian Army aircraft operations on Amritsar–Jamnagar corridor

The National Highways Builders Federation (NHBF) has welcomed the successful landing and take-off of four Indian Army microlight aircraft on the Amritsar–Jamnagar Economic Corridor (NH-754K) in Gujarat. The exercise demonstrated the potential of highway infrastructure to support defence operations and emergency response. The expressway was developed by CDS Infra Projects, an NHBF member company.Developed under the Bharatmala Pariyojana, the six-lane greenfield corridor is described as India's second-longest expressway. The operation was conducted by the Indian Army's Team Mountain Eagles as ..

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code