Construction begins on three underground metro stations
RAILWAYS & METRO RAIL

Construction begins on three underground metro stations

In the Kanpur Metro Rail Project, a 4.10 km (approximately) long underground section from Rawatpur to Double Puliya, located under Corridor-2 between CSA University and Barra-8, is slated for construction. The process of excavating the ground to lower the panel of the first Diaphragm Wall (D-Wall) at the Rawatpur underground station commenced in the presence of senior officials of UPMRC and contracting agencies.

It was mentioned that the pre-construction stage works such as soil testing, barricading, and utility shifting were in progress on the aforementioned section since the tender was awarded in December the previous year. With the commencement of the excavation process for the D-Wall, it was indicated that the construction work for this section had now progressed to the next stage. The stations to be constructed under this section include Rawatpur, Kakadeo, and Double Puliya metro stations. It was emphasised that the Rawatpur underground metro station would serve as a crucial station connecting both corridors of the Kanpur Metro. Passengers would change trains at this station to travel between stations on the first and second corridors.

The D-Wall, described as the boundary of an underground metro station, was explained to be constructed with small rectangular panels, with 65 such panels of different sizes to be used for the D-Wall in Rawatpur Metro Station.

It was further explained that the underground stations of Kanpur Metro Corridor-2 would be built using the 'Top-Down Method', meaning that construction works for these stations would progress from top to bottom. Initially, the roof slab would be prepared, followed by the construction of concourse platform levels.

The adoption of this method was justified as a means to minimize the impact on traffic, as barricading on roads would be reduced after the construction of the first floor underground. It was assured that construction work below ground would continue while allowing the smooth movement of vehicles on the road. This method was stated to be similarly employed in the construction of both underground sections of Corridor-1.

In the Kanpur Metro Rail Project, a 4.10 km (approximately) long underground section from Rawatpur to Double Puliya, located under Corridor-2 between CSA University and Barra-8, is slated for construction. The process of excavating the ground to lower the panel of the first Diaphragm Wall (D-Wall) at the Rawatpur underground station commenced in the presence of senior officials of UPMRC and contracting agencies. It was mentioned that the pre-construction stage works such as soil testing, barricading, and utility shifting were in progress on the aforementioned section since the tender was awarded in December the previous year. With the commencement of the excavation process for the D-Wall, it was indicated that the construction work for this section had now progressed to the next stage. The stations to be constructed under this section include Rawatpur, Kakadeo, and Double Puliya metro stations. It was emphasised that the Rawatpur underground metro station would serve as a crucial station connecting both corridors of the Kanpur Metro. Passengers would change trains at this station to travel between stations on the first and second corridors. The D-Wall, described as the boundary of an underground metro station, was explained to be constructed with small rectangular panels, with 65 such panels of different sizes to be used for the D-Wall in Rawatpur Metro Station. It was further explained that the underground stations of Kanpur Metro Corridor-2 would be built using the 'Top-Down Method', meaning that construction works for these stations would progress from top to bottom. Initially, the roof slab would be prepared, followed by the construction of concourse platform levels. The adoption of this method was justified as a means to minimize the impact on traffic, as barricading on roads would be reduced after the construction of the first floor underground. It was assured that construction work below ground would continue while allowing the smooth movement of vehicles on the road. This method was stated to be similarly employed in the construction of both underground sections of Corridor-1.

Related Stories

Gold Stories

Next Story
Real Estate

LML Realty Sells Out Jhirka Valley Industrial Park in Haryana

LML Realty, the real estate arm of LML Group, recently announced the complete sell-out of its Jhirka Valley Industrial Park in Haryana, with over 1.17 million sq ft of industrial space acquired by more than 50 companies. With utilities and internal infrastructure in place, the company has commenced plot handovers, enabling buyers to begin construction and establish their operations.The industrial park has attracted companies across diverse sectors, including chemicals, metals and alloys, textiles, electrical equipment, energy, logistics, construction, polymers and engineering. Key buyers inclu..

Next Story
Real Estate

WSB Real Estate Partners Exits Six Housing Investments

WSB Real Estate Partners recently announced the successful exit of six residential investments across Bengaluru, Mumbai Metropolitan Region (MMR) and National Capital Region (NCR), delivering an average internal rate of return (IRR) of 19–21 per cent and an overall investment return of 1.4 times.The real estate-focused investment firm invested approximately Rs 7 billion across six mid-affordable housing projects over the past four years. All six investments were fully repaid between April and November 2026, several months ahead of their original investment tenures.WSB collaborated with sever..

Next Story
Infrastructure Transport

Aluminium Industry Seeks Policy Support for Rs 4 Trillion Investment

The Aluminium Association of India (AAI) has recently urged the government to introduce supportive policy measures to safeguard the sector’s proposed Rs 4 trillion investment pipeline. The association highlighted the need for a predictable policy framework to strengthen domestic manufacturing, expand production capacity and reduce import dependence.AAI submitted its recommendations for the Union Budget 2027-28 to the Ministries of Finance, Commerce and Industry, and Mines, along with the Department for Promotion of Industry and Internal Trade (DPIIT).India’s aluminium demand is projected t..

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code