Construction begins on three underground metro stations
RAILWAYS & METRO RAIL

Construction begins on three underground metro stations

In the Kanpur Metro Rail Project, a 4.10 km (approximately) long underground section from Rawatpur to Double Puliya, located under Corridor-2 between CSA University and Barra-8, is slated for construction. The process of excavating the ground to lower the panel of the first Diaphragm Wall (D-Wall) at the Rawatpur underground station commenced in the presence of senior officials of UPMRC and contracting agencies.

It was mentioned that the pre-construction stage works such as soil testing, barricading, and utility shifting were in progress on the aforementioned section since the tender was awarded in December the previous year. With the commencement of the excavation process for the D-Wall, it was indicated that the construction work for this section had now progressed to the next stage. The stations to be constructed under this section include Rawatpur, Kakadeo, and Double Puliya metro stations. It was emphasised that the Rawatpur underground metro station would serve as a crucial station connecting both corridors of the Kanpur Metro. Passengers would change trains at this station to travel between stations on the first and second corridors.

The D-Wall, described as the boundary of an underground metro station, was explained to be constructed with small rectangular panels, with 65 such panels of different sizes to be used for the D-Wall in Rawatpur Metro Station.

It was further explained that the underground stations of Kanpur Metro Corridor-2 would be built using the 'Top-Down Method', meaning that construction works for these stations would progress from top to bottom. Initially, the roof slab would be prepared, followed by the construction of concourse platform levels.

The adoption of this method was justified as a means to minimize the impact on traffic, as barricading on roads would be reduced after the construction of the first floor underground. It was assured that construction work below ground would continue while allowing the smooth movement of vehicles on the road. This method was stated to be similarly employed in the construction of both underground sections of Corridor-1.

"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

In the Kanpur Metro Rail Project, a 4.10 km (approximately) long underground section from Rawatpur to Double Puliya, located under Corridor-2 between CSA University and Barra-8, is slated for construction. The process of excavating the ground to lower the panel of the first Diaphragm Wall (D-Wall) at the Rawatpur underground station commenced in the presence of senior officials of UPMRC and contracting agencies. It was mentioned that the pre-construction stage works such as soil testing, barricading, and utility shifting were in progress on the aforementioned section since the tender was awarded in December the previous year. With the commencement of the excavation process for the D-Wall, it was indicated that the construction work for this section had now progressed to the next stage. The stations to be constructed under this section include Rawatpur, Kakadeo, and Double Puliya metro stations. It was emphasised that the Rawatpur underground metro station would serve as a crucial station connecting both corridors of the Kanpur Metro. Passengers would change trains at this station to travel between stations on the first and second corridors. The D-Wall, described as the boundary of an underground metro station, was explained to be constructed with small rectangular panels, with 65 such panels of different sizes to be used for the D-Wall in Rawatpur Metro Station. It was further explained that the underground stations of Kanpur Metro Corridor-2 would be built using the 'Top-Down Method', meaning that construction works for these stations would progress from top to bottom. Initially, the roof slab would be prepared, followed by the construction of concourse platform levels. The adoption of this method was justified as a means to minimize the impact on traffic, as barricading on roads would be reduced after the construction of the first floor underground. It was assured that construction work below ground would continue while allowing the smooth movement of vehicles on the road. This method was stated to be similarly employed in the construction of both underground sections of Corridor-1.

Next Story
Infrastructure Urban

ABS Marine Sees CRISIL Credit Rating Upgrade

ABS Marine Services has secured an upgrade to its long term and short term credit ratings from CRISIL, reflecting improved profitability and revenue growth through long term contracts. CRISIL moved the long term rating from BBB+/Stable to A-/Stable and revised the short term rating from A2 to A2+. The action signals strengthened financial metrics and operational resilience. The company benefited from durable client relationships with firms such as ONGC and Schlumberger. The rating decision followed stronger cash flows and an enlarged bank loan facility, which increased from Rs 3,705 million (m..

Next Story
Infrastructure Transport

Project BRAHMANK Marks 16 Years Of Strategic Roads In Arunachal

Project BRAHMANK is marking 16 years of work to establish strategic road and bridge links across Arunachal Pradesh, maintaining and developing 811 kilometres of roads and nearly 86 bridges that range from small culverts to large steel and arch bridges. These transport links are described as critical for ensuring year-round movement of defence personnel, equipment and essential supplies while improving everyday travel for people in remote villages. The project balances national security requirements with regional development by focusing on reliable access in challenging terrain. Notable enginee..

Next Story
Infrastructure Transport

Longleng CSOs Give One Week Ultimatum Over Two-Lane Highway

Civil society organisations (CSOs) in Longleng district have demanded immediate restoration of the deteriorating Changtongya–Longleng two-lane road and sought a detailed status report on the stalled construction within one week. The demand followed a consultative meeting convened under the Phom Peoples' Council (PPC) to discuss welfare and development concerns. PPC president YB Angam Phom said prolonged non-maintenance had caused hardship to commuters and affected transportation, local commerce and the district's development. The meeting urged authorities to undertake immediate restoration a..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement