Construction begins on three underground metro stations
RAILWAYS & METRO RAIL

Construction begins on three underground metro stations

In the Kanpur Metro Rail Project, a 4.10 km (approximately) long underground section from Rawatpur to Double Puliya, located under Corridor-2 between CSA University and Barra-8, is slated for construction. The process of excavating the ground to lower the panel of the first Diaphragm Wall (D-Wall) at the Rawatpur underground station commenced in the presence of senior officials of UPMRC and contracting agencies.

It was mentioned that the pre-construction stage works such as soil testing, barricading, and utility shifting were in progress on the aforementioned section since the tender was awarded in December the previous year. With the commencement of the excavation process for the D-Wall, it was indicated that the construction work for this section had now progressed to the next stage. The stations to be constructed under this section include Rawatpur, Kakadeo, and Double Puliya metro stations. It was emphasised that the Rawatpur underground metro station would serve as a crucial station connecting both corridors of the Kanpur Metro. Passengers would change trains at this station to travel between stations on the first and second corridors.

The D-Wall, described as the boundary of an underground metro station, was explained to be constructed with small rectangular panels, with 65 such panels of different sizes to be used for the D-Wall in Rawatpur Metro Station.

It was further explained that the underground stations of Kanpur Metro Corridor-2 would be built using the 'Top-Down Method', meaning that construction works for these stations would progress from top to bottom. Initially, the roof slab would be prepared, followed by the construction of concourse platform levels.

The adoption of this method was justified as a means to minimize the impact on traffic, as barricading on roads would be reduced after the construction of the first floor underground. It was assured that construction work below ground would continue while allowing the smooth movement of vehicles on the road. This method was stated to be similarly employed in the construction of both underground sections of Corridor-1.

In the Kanpur Metro Rail Project, a 4.10 km (approximately) long underground section from Rawatpur to Double Puliya, located under Corridor-2 between CSA University and Barra-8, is slated for construction. The process of excavating the ground to lower the panel of the first Diaphragm Wall (D-Wall) at the Rawatpur underground station commenced in the presence of senior officials of UPMRC and contracting agencies. It was mentioned that the pre-construction stage works such as soil testing, barricading, and utility shifting were in progress on the aforementioned section since the tender was awarded in December the previous year. With the commencement of the excavation process for the D-Wall, it was indicated that the construction work for this section had now progressed to the next stage. The stations to be constructed under this section include Rawatpur, Kakadeo, and Double Puliya metro stations. It was emphasised that the Rawatpur underground metro station would serve as a crucial station connecting both corridors of the Kanpur Metro. Passengers would change trains at this station to travel between stations on the first and second corridors. The D-Wall, described as the boundary of an underground metro station, was explained to be constructed with small rectangular panels, with 65 such panels of different sizes to be used for the D-Wall in Rawatpur Metro Station. It was further explained that the underground stations of Kanpur Metro Corridor-2 would be built using the 'Top-Down Method', meaning that construction works for these stations would progress from top to bottom. Initially, the roof slab would be prepared, followed by the construction of concourse platform levels. The adoption of this method was justified as a means to minimize the impact on traffic, as barricading on roads would be reduced after the construction of the first floor underground. It was assured that construction work below ground would continue while allowing the smooth movement of vehicles on the road. This method was stated to be similarly employed in the construction of both underground sections of Corridor-1.

Next Story
Technology

Six ways a smarter workflow leads to faster, more accurate bids

In today’s fast-paced civil construction environment, estimators need more than just solid numbers. They need smart, streamlined processes. This article explores six key ways connected workflows can transform the estimated approach, help in minimising risk, move faster, and improve accuracy. By integrating tools, data, and teams, one can produce stronger bids with less rework, fewer surprises, and more confidence. As an estimator, the job goes beyond producing numbers. They are responsible for delivering bids that are fast, accurate, and built to win. In today’s civil construction ind..

Next Story
Real Estate

Experion Launches Women-Only Co-Living Project in Greater Noida

Experion, part of Singapore-based AT Capital Group, has launched its first co-living space under its managed rental housing brand, VLIV, in Greater Noida. The all-women residence features 730 twin-sharing beds with a strong focus on safety, comfort, and well-being. VLIV has committed a $300 million investment to create a structured, service-led rental housing ecosystem in India. The brand aims to scale up to 20,000 beds in the next few years, with a long-term target of 100,000 beds nationwide. “India’s rental housing is fragmented. VLIV is our way of building long-term, dependabl..

Next Story
Infrastructure Urban

Officine Maccaferri Acquires CPT to Bolster Tunnelling Tech

Ambienta’s platform company, Officine Maccaferri S.p.A., has acquired CPT Group, a leading Italian developer of robotic prefabrication systems and digital control technologies for mechanised tunnelling. The move positions Maccaferri as a global player in integrated tunnelling solutions, blending traditional and advanced mechanised systems. Based in Nova Milanese, CPT serves major global contractors across Europe, Southeast Asia, and Australia. The company offers robotic prefabrication (Robofactory), productivity-monitoring software for Tunnel Boring Machines (TBMs), and eco-designed spa..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?