Construction begins on three underground metro stations
RAILWAYS & METRO RAIL

Construction begins on three underground metro stations

In the Kanpur Metro Rail Project, a 4.10 km (approximately) long underground section from Rawatpur to Double Puliya, located under Corridor-2 between CSA University and Barra-8, is slated for construction. The process of excavating the ground to lower the panel of the first Diaphragm Wall (D-Wall) at the Rawatpur underground station commenced in the presence of senior officials of UPMRC and contracting agencies.

It was mentioned that the pre-construction stage works such as soil testing, barricading, and utility shifting were in progress on the aforementioned section since the tender was awarded in December the previous year. With the commencement of the excavation process for the D-Wall, it was indicated that the construction work for this section had now progressed to the next stage. The stations to be constructed under this section include Rawatpur, Kakadeo, and Double Puliya metro stations. It was emphasised that the Rawatpur underground metro station would serve as a crucial station connecting both corridors of the Kanpur Metro. Passengers would change trains at this station to travel between stations on the first and second corridors.

The D-Wall, described as the boundary of an underground metro station, was explained to be constructed with small rectangular panels, with 65 such panels of different sizes to be used for the D-Wall in Rawatpur Metro Station.

It was further explained that the underground stations of Kanpur Metro Corridor-2 would be built using the 'Top-Down Method', meaning that construction works for these stations would progress from top to bottom. Initially, the roof slab would be prepared, followed by the construction of concourse platform levels.

The adoption of this method was justified as a means to minimize the impact on traffic, as barricading on roads would be reduced after the construction of the first floor underground. It was assured that construction work below ground would continue while allowing the smooth movement of vehicles on the road. This method was stated to be similarly employed in the construction of both underground sections of Corridor-1.

In the Kanpur Metro Rail Project, a 4.10 km (approximately) long underground section from Rawatpur to Double Puliya, located under Corridor-2 between CSA University and Barra-8, is slated for construction. The process of excavating the ground to lower the panel of the first Diaphragm Wall (D-Wall) at the Rawatpur underground station commenced in the presence of senior officials of UPMRC and contracting agencies. It was mentioned that the pre-construction stage works such as soil testing, barricading, and utility shifting were in progress on the aforementioned section since the tender was awarded in December the previous year. With the commencement of the excavation process for the D-Wall, it was indicated that the construction work for this section had now progressed to the next stage. The stations to be constructed under this section include Rawatpur, Kakadeo, and Double Puliya metro stations. It was emphasised that the Rawatpur underground metro station would serve as a crucial station connecting both corridors of the Kanpur Metro. Passengers would change trains at this station to travel between stations on the first and second corridors. The D-Wall, described as the boundary of an underground metro station, was explained to be constructed with small rectangular panels, with 65 such panels of different sizes to be used for the D-Wall in Rawatpur Metro Station. It was further explained that the underground stations of Kanpur Metro Corridor-2 would be built using the 'Top-Down Method', meaning that construction works for these stations would progress from top to bottom. Initially, the roof slab would be prepared, followed by the construction of concourse platform levels. The adoption of this method was justified as a means to minimize the impact on traffic, as barricading on roads would be reduced after the construction of the first floor underground. It was assured that construction work below ground would continue while allowing the smooth movement of vehicles on the road. This method was stated to be similarly employed in the construction of both underground sections of Corridor-1.

Next Story
Building Material

Suraj Estate Wins Euromoney Award for India’s Best Residential Developer

"Suraj Estate Developers Limited has received the Euromoney Real Estate Award 2025 for ‘India’s Best Residential Developer’, positioning the company among globally benchmarked leaders in the sector. The recognition reflects its four-decade legacy in delivering high-quality residential and redevelopment-led projects across South Central Mumbai. The Euromoney Real Estate Awards, presented by the London-based Euromoney magazine, are widely regarded as one of the most credible global assessments of performance in real estate, banking and finance. Winners are selected through surveys of inte..

Next Story
Building Material

Lloyds Metals, Tata Steel Sign MoU to Explore Strategic Collaboration

"Lloyds Metals and Energy Limited has signed a non-binding Memorandum of Understanding with Tata Steel Limited to evaluate potential areas of strategic cooperation across mining, logistics, pelletisation and steelmaking. The MoU was signed by B Prabhakaran, Managing Director of Lloyds Metals, and Mr T V Narendran, CEO and Managing Director of Tata Steel. The partnership framework aims to leverage the natural operational synergies between both companies and assess opportunities in greenfield steel projects, iron ore mining, slurry pipeline infrastructure, pellet manufacturing in iron ore–ric..

Next Story
Building Material

IndiaAI, Gujarat Govt Host Regional Conclave Ahead of 2026 AI Summit

The IndiaAI Mission under the Ministry of Electronics and Information Technology, along with the Government of Gujarat and IIT Gandhinagar, convened a Regional Pre-Summit Event at Mahatma Mandir, Gandhinagar. The initiative is part of the build-up to the India–AI Impact Summit 2026, scheduled for 15–20 February 2026 at Bharat Mandapam, New Delhi. The conclave brought together senior policymakers, technology leaders, researchers and industry practitioners to examine how AI can accelerate economic, digital and social transformation across sectors. The programme focused on the overarching th..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Open In App