Dharmapuri-Morappur Railway Line Delayed by Land Acquisition
RAILWAYS & METRO RAIL

Dharmapuri-Morappur Railway Line Delayed by Land Acquisition

Railway passengers in Dharmapuri renewed calls for a speedy completion of the Dharmapuri-Morappur railway line as land acquisition remains incomplete. The route was originally constructed in 1906 by the British administration and linked Dharmapuri with Morappur and northern districts including Vellore and Chennai. The tracks were dismantled in 1941 to supply iron for the Second World War and have remained out of service since.

The revival project was sanctioned in 2019 at Rs 3,589.5 million (Rs 3.5895 bn) and a foundation stone was laid by the then Union Minister of Railways, Piyush Goyal. Despite the sanction, officials report that land acquisition has progressed slowly over seven years and that only part of the required area has been secured. Passengers and local stakeholders continue to press Southern Railway for expedited action.

According to the Dharmapuri administration, the alignment runs through three taluks and 18 villages and requires 93 acres in total. To date about 47 acres have been secured, including 33 acres that are government land. Local business representatives have noted that the lack of direct trains to Chennai has discouraged investment and that the revived link would facilitate access to Chennai ports for freight and to air links.

Southern Railway officials attributed the delay to legal challenges from landholders, stated that the High Court has issued directions in the matter, and confirmed that notices have been served to advance acquisition. They indicated that construction could begin once acquisition is complete and that they expect the project to be finished within two years, subject to unforeseen circumstances. The scheme envisages two new railway stations, four major bridges, 36 minor bridges and several underpasses and is expected to increase the number of trains serving the district.

Railway passengers in Dharmapuri renewed calls for a speedy completion of the Dharmapuri-Morappur railway line as land acquisition remains incomplete. The route was originally constructed in 1906 by the British administration and linked Dharmapuri with Morappur and northern districts including Vellore and Chennai. The tracks were dismantled in 1941 to supply iron for the Second World War and have remained out of service since. The revival project was sanctioned in 2019 at Rs 3,589.5 million (Rs 3.5895 bn) and a foundation stone was laid by the then Union Minister of Railways, Piyush Goyal. Despite the sanction, officials report that land acquisition has progressed slowly over seven years and that only part of the required area has been secured. Passengers and local stakeholders continue to press Southern Railway for expedited action. According to the Dharmapuri administration, the alignment runs through three taluks and 18 villages and requires 93 acres in total. To date about 47 acres have been secured, including 33 acres that are government land. Local business representatives have noted that the lack of direct trains to Chennai has discouraged investment and that the revived link would facilitate access to Chennai ports for freight and to air links. Southern Railway officials attributed the delay to legal challenges from landholders, stated that the High Court has issued directions in the matter, and confirmed that notices have been served to advance acquisition. They indicated that construction could begin once acquisition is complete and that they expect the project to be finished within two years, subject to unforeseen circumstances. The scheme envisages two new railway stations, four major bridges, 36 minor bridges and several underpasses and is expected to increase the number of trains serving the district.

Related Stories

Gold Stories

Next Story
Real Estate

LML Realty Sells Out Jhirka Valley Industrial Park in Haryana

LML Realty, the real estate arm of LML Group, recently announced the complete sell-out of its Jhirka Valley Industrial Park in Haryana, with over 1.17 million sq ft of industrial space acquired by more than 50 companies. With utilities and internal infrastructure in place, the company has commenced plot handovers, enabling buyers to begin construction and establish their operations.The industrial park has attracted companies across diverse sectors, including chemicals, metals and alloys, textiles, electrical equipment, energy, logistics, construction, polymers and engineering. Key buyers inclu..

Next Story
Real Estate

WSB Real Estate Partners Exits Six Housing Investments

WSB Real Estate Partners recently announced the successful exit of six residential investments across Bengaluru, Mumbai Metropolitan Region (MMR) and National Capital Region (NCR), delivering an average internal rate of return (IRR) of 19–21 per cent and an overall investment return of 1.4 times.The real estate-focused investment firm invested approximately Rs 7 billion across six mid-affordable housing projects over the past four years. All six investments were fully repaid between April and November 2026, several months ahead of their original investment tenures.WSB collaborated with sever..

Next Story
Infrastructure Transport

Aluminium Industry Seeks Policy Support for Rs 4 Trillion Investment

The Aluminium Association of India (AAI) has recently urged the government to introduce supportive policy measures to safeguard the sector’s proposed Rs 4 trillion investment pipeline. The association highlighted the need for a predictable policy framework to strengthen domestic manufacturing, expand production capacity and reduce import dependence.AAI submitted its recommendations for the Union Budget 2027-28 to the Ministries of Finance, Commerce and Industry, and Mines, along with the Department for Promotion of Industry and Internal Trade (DPIIT).India’s aluminium demand is projected t..

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code