DMRC Starts Land Acquisition for New Delhi Metro Corridors
RAILWAYS & METRO RAIL

DMRC Starts Land Acquisition for New Delhi Metro Corridors

The Delhi Metro Rail Corporation (DMRC) has initiated the land acquisition process for two new corridors under Phase 4 of its expansion plan. The corridors, extending from Lajpat Nagar to Saket G Block and from Inderlok to Indraprastha, aim to enhance connectivity in Delhi. The Union Cabinet approved these projects in March 2024, targeting operational readiness by 2028.

DMRC is currently securing statutory clearances from the Delhi Development Authority (DDA), Central Public Works Department (CPWD), and the Public Works Department (PWD). This phase involves obtaining forest clearance and planning for civil works and specialised contracts for essential technical components.

The Inderlok to Indraprastha corridor will be 12.4 kilometres long with 10 stations, while the Lajpat Nagar to Saket G Block corridor will span 8.4 kilometres with eight stations. Both corridors will feature several interchange stations, enhancing the efficiency of the metro network. The addition of these corridors is part of a broader strategic plan to improve Delhi?s urban transit infrastructure, reducing travel times and increasing convenience for commuters.

The expansion will bring the total number of interchange stations in Delhi to 48, facilitating smoother transitions between metro lines. Key interchange stations like Lajpat Nagar and New Delhi will become triple interchange hubs, further optimising the metro system.

Alongside these corridors, three priority corridors?Majlis Park-Maujpur, Janakpuri West-RK Ashram Marg, and Aerocity-Tughlaqabad?are also under construction. These efforts underscore DMRC's commitment to expanding and enhancing Delhi's metro network.

The Delhi Metro Rail Corporation (DMRC) has initiated the land acquisition process for two new corridors under Phase 4 of its expansion plan. The corridors, extending from Lajpat Nagar to Saket G Block and from Inderlok to Indraprastha, aim to enhance connectivity in Delhi. The Union Cabinet approved these projects in March 2024, targeting operational readiness by 2028. DMRC is currently securing statutory clearances from the Delhi Development Authority (DDA), Central Public Works Department (CPWD), and the Public Works Department (PWD). This phase involves obtaining forest clearance and planning for civil works and specialised contracts for essential technical components. The Inderlok to Indraprastha corridor will be 12.4 kilometres long with 10 stations, while the Lajpat Nagar to Saket G Block corridor will span 8.4 kilometres with eight stations. Both corridors will feature several interchange stations, enhancing the efficiency of the metro network. The addition of these corridors is part of a broader strategic plan to improve Delhi?s urban transit infrastructure, reducing travel times and increasing convenience for commuters. The expansion will bring the total number of interchange stations in Delhi to 48, facilitating smoother transitions between metro lines. Key interchange stations like Lajpat Nagar and New Delhi will become triple interchange hubs, further optimising the metro system. Alongside these corridors, three priority corridors?Majlis Park-Maujpur, Janakpuri West-RK Ashram Marg, and Aerocity-Tughlaqabad?are also under construction. These efforts underscore DMRC's commitment to expanding and enhancing Delhi's metro network.

Next Story
Infrastructure Transport

India’s Maha Kumbh of Road Construction

The RAHSTA Forum 2025, held on June 25 at Courtyard by Marriott, Mumbai, delivered powerful insights and dialogue on the future of India’s roads and highways sector. Organised by the FIRST Construction Council, the Forum served as the curtain-raiser to the much-anticipated RAHSTA Expo 2025, set to take place on 3rd and 4th September at the Jio Convention Centre, Mumbai.Union Minister of Roads Transport & Highways Shri Nitin Gadkari, while appreciating the efforts of FIRST Construction Council and ASAPP Info Global Group, commended the awards which recognise excellence across various..

Next Story
Real Estate

Built to Last, Designed to Impress

The construction and interior design industries stand at the confluence of functionality and aesthetics, where innovation powers the creation of enduring structures and inspiring spaces. At the heart of this process are materials and solutions that enable architects, designers, and builders to realise their visions with precision and reliability.Featuring iconic brands such as Fevicol—synonymous with adhesive solutions—Dr. Fixit, a complete waterproofing system renowned for addressing every critical area of construction, and Roff, a specialist in tile-fixing solutions, Pidilite has earned ..

Next Story
Infrastructure Energy

New Push to Cut India’s Air Pollution through Power Sector Reforms

In a significant stride toward environmental sustainability, Cummins India introduced CPCB IV+ compliant gensets to India on July 5, 2023, marking a paradigm shift in the power generation industry. These generators are engineered to adhere to the progressive emission norms set by the Ministry of Environment, Forest, and Climate Change. Being the first sets in the field, they have garnered praise for their remarkable achievements in emissions reduction and cutting-edge technology. Powerica, with its four-decade-long partnership with Cummins India Limited, is dedicated to consistently deliver th..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?