+
Final Cross-Passage Completed in East-West Metro's Subsidence Zone
RAILWAYS & METRO RAIL

Final Cross-Passage Completed in East-West Metro's Subsidence Zone

The final cross-passage in the East-West Metro's Esplanade-to-Sealdah subsidence zone has been successfully completed, paving the way to link the two disjointed sections of the Green Line. With the construction of cross-passages on this section now finished, the work on the Esplanade-Sealdah stretch is expected to wrap up soon. Following this, the two currently operational sections "one between Sector V and Sealdah and the other between Howrah Maidan and Esplanade" will be connected, allowing services on the entire 16.6km corridor to commence.

"We made sure there was no ground settlement and damage to the buildings in the vicinity," an engineer involved in the project stated. Contractors ITD-ITD Cementation and the Kolkata Metro Rail Corporation (KMRC) had to proceed cautiously, taking a month to complete the last of the cross-passages, 5B, in the cave-in zone due to the need for heightened alertness and vigilance.

On April 18, water seepage was detected at two spots during micro-tunnelling to build a cross-passage below Hind on Ganesh Chandra Avenue, prompting an immediate halt to construction. Expensive chemical and cement grouting were carried out over three days, and micro-tunnelling resumed on April 22. As a precaution, a high-rise at 1A, Subodh Mullick Square was evacuated for a week starting April 22.

Cross-passages, small tunnels built at intervals of 250m on underground metro lines, allow passengers to cross from one main tunnel to another during emergencies, such as a fire. Although these smaller tunnels are crucial for safety in an underground metro corridor, KMRC had to abandon three of the eight originally planned cross-passages in the Esplanade-Sealdah section after the subsidence incident on October 14, 2022. The East-West Metro project between Esplanade and Sealdah has experienced three such incidents from 2019 to 2022.

Over the past month, alongside micro-tunnelling, the construction team also concretized small tunnel rings to create these smaller tunnels connecting the larger twin tunnels. The original site for cross-passage 5B under Nirmal Chunder Street proved to be as porous as three proposed sites beyond this area. After several months of grouting failed to stabilize the soil, the location was shifted to a more stable ground condition below the cinema. However, this new site also required extensive chemical and concrete grouting.

On April 16, hi-tech micro-tunnelling using the New Austrian Tunnel Method (NATM) commenced. "In less than four days, water seepage was detected at two spots and the work was stopped. A high-rise with a weak foundation was evacuated. From April 22, we worked slowly, lest there was subsidence. Thankfully, there was none," the engineer added.

The final cross-passage in the East-West Metro's Esplanade-to-Sealdah subsidence zone has been successfully completed, paving the way to link the two disjointed sections of the Green Line. With the construction of cross-passages on this section now finished, the work on the Esplanade-Sealdah stretch is expected to wrap up soon. Following this, the two currently operational sections one between Sector V and Sealdah and the other between Howrah Maidan and Esplanade will be connected, allowing services on the entire 16.6km corridor to commence. We made sure there was no ground settlement and damage to the buildings in the vicinity, an engineer involved in the project stated. Contractors ITD-ITD Cementation and the Kolkata Metro Rail Corporation (KMRC) had to proceed cautiously, taking a month to complete the last of the cross-passages, 5B, in the cave-in zone due to the need for heightened alertness and vigilance. On April 18, water seepage was detected at two spots during micro-tunnelling to build a cross-passage below Hind on Ganesh Chandra Avenue, prompting an immediate halt to construction. Expensive chemical and cement grouting were carried out over three days, and micro-tunnelling resumed on April 22. As a precaution, a high-rise at 1A, Subodh Mullick Square was evacuated for a week starting April 22. Cross-passages, small tunnels built at intervals of 250m on underground metro lines, allow passengers to cross from one main tunnel to another during emergencies, such as a fire. Although these smaller tunnels are crucial for safety in an underground metro corridor, KMRC had to abandon three of the eight originally planned cross-passages in the Esplanade-Sealdah section after the subsidence incident on October 14, 2022. The East-West Metro project between Esplanade and Sealdah has experienced three such incidents from 2019 to 2022. Over the past month, alongside micro-tunnelling, the construction team also concretized small tunnel rings to create these smaller tunnels connecting the larger twin tunnels. The original site for cross-passage 5B under Nirmal Chunder Street proved to be as porous as three proposed sites beyond this area. After several months of grouting failed to stabilize the soil, the location was shifted to a more stable ground condition below the cinema. However, this new site also required extensive chemical and concrete grouting. On April 16, hi-tech micro-tunnelling using the New Austrian Tunnel Method (NATM) commenced. In less than four days, water seepage was detected at two spots and the work was stopped. A high-rise with a weak foundation was evacuated. From April 22, we worked slowly, lest there was subsidence. Thankfully, there was none, the engineer added.

Next Story
Technology

ITI honoured by ISRO for role in NISAR satellite launch

ITI Limited, India’s first PSU established after independence and a leading telecom manufacturer, has been recognised by the Indian Space Research Organisation (ISRO) for its contribution to the successful launch of the NASA–ISRO Synthetic Aperture Radar (NISAR) satellite on 30 July 2025. The appreciation highlights ITI’s timely realisation of avionics systems while meeting all quality standards set by the Vikram Sarabhai Space Centre (VSSC).The landmark mission was carried out by ISRO’s GSLV-F16 rocket, which placed the 2,393 kg NISAR satellite into its intended orbit from the Satish ..

Next Story
Infrastructure Urban

Kings Infra posts 22 per cent rise in Q1 income

Kings Infra Ventures Limited today announced its results for Q1 FY25-26, reporting strong growth driven by expanded exports and the integration of additional leased farms into its high-efficiency supply chain. The performance reflects the company’s strategic focus on diversifying global markets, enhancing farm productivity, and consolidating its position in the high-growth healthy proteins sector.Financial PerformanceTotal income rose to Rs 3.42 billion, up 21.68 per cent from Rs 2.81 billion in Q1 FY24-25.EBITDA increased to Rs 701 million, a 36.91 per cent rise from Rs 512 million.EBITDA m..

Next Story
Infrastructure Transport

Afcom sets cargo milestone at Velana Airport

AFCOM Holdings Limited, an integrated air cargo solutions provider with domestic and international operations, has achieved a historic milestone at Velana International Airport (MLE) in the Maldives. In July 2025, the company uplifted the highest-ever volume of transshipment cargo in the airport’s history, underlining Afcom’s pivotal role in the region’s logistics ecosystem.The month marked a turning point for MLE, with transshipment volumes reaching record levels in a single month. Afcom emerged as the top contributor, significantly driving this achievement and reinforcing its growing i..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?