Final Cross-Passage Completed in East-West Metro's Subsidence Zone
RAILWAYS & METRO RAIL

Final Cross-Passage Completed in East-West Metro's Subsidence Zone

The final cross-passage in the East-West Metro's Esplanade-to-Sealdah subsidence zone has been successfully completed, paving the way to link the two disjointed sections of the Green Line. With the construction of cross-passages on this section now finished, the work on the Esplanade-Sealdah stretch is expected to wrap up soon. Following this, the two currently operational sections "one between Sector V and Sealdah and the other between Howrah Maidan and Esplanade" will be connected, allowing services on the entire 16.6km corridor to commence.

"We made sure there was no ground settlement and damage to the buildings in the vicinity," an engineer involved in the project stated. Contractors ITD-ITD Cementation and the Kolkata Metro Rail Corporation (KMRC) had to proceed cautiously, taking a month to complete the last of the cross-passages, 5B, in the cave-in zone due to the need for heightened alertness and vigilance.

On April 18, water seepage was detected at two spots during micro-tunnelling to build a cross-passage below Hind on Ganesh Chandra Avenue, prompting an immediate halt to construction. Expensive chemical and cement grouting were carried out over three days, and micro-tunnelling resumed on April 22. As a precaution, a high-rise at 1A, Subodh Mullick Square was evacuated for a week starting April 22.

Cross-passages, small tunnels built at intervals of 250m on underground metro lines, allow passengers to cross from one main tunnel to another during emergencies, such as a fire. Although these smaller tunnels are crucial for safety in an underground metro corridor, KMRC had to abandon three of the eight originally planned cross-passages in the Esplanade-Sealdah section after the subsidence incident on October 14, 2022. The East-West Metro project between Esplanade and Sealdah has experienced three such incidents from 2019 to 2022.

Over the past month, alongside micro-tunnelling, the construction team also concretized small tunnel rings to create these smaller tunnels connecting the larger twin tunnels. The original site for cross-passage 5B under Nirmal Chunder Street proved to be as porous as three proposed sites beyond this area. After several months of grouting failed to stabilize the soil, the location was shifted to a more stable ground condition below the cinema. However, this new site also required extensive chemical and concrete grouting.

On April 16, hi-tech micro-tunnelling using the New Austrian Tunnel Method (NATM) commenced. "In less than four days, water seepage was detected at two spots and the work was stopped. A high-rise with a weak foundation was evacuated. From April 22, we worked slowly, lest there was subsidence. Thankfully, there was none," the engineer added.

The final cross-passage in the East-West Metro's Esplanade-to-Sealdah subsidence zone has been successfully completed, paving the way to link the two disjointed sections of the Green Line. With the construction of cross-passages on this section now finished, the work on the Esplanade-Sealdah stretch is expected to wrap up soon. Following this, the two currently operational sections one between Sector V and Sealdah and the other between Howrah Maidan and Esplanade will be connected, allowing services on the entire 16.6km corridor to commence. We made sure there was no ground settlement and damage to the buildings in the vicinity, an engineer involved in the project stated. Contractors ITD-ITD Cementation and the Kolkata Metro Rail Corporation (KMRC) had to proceed cautiously, taking a month to complete the last of the cross-passages, 5B, in the cave-in zone due to the need for heightened alertness and vigilance. On April 18, water seepage was detected at two spots during micro-tunnelling to build a cross-passage below Hind on Ganesh Chandra Avenue, prompting an immediate halt to construction. Expensive chemical and cement grouting were carried out over three days, and micro-tunnelling resumed on April 22. As a precaution, a high-rise at 1A, Subodh Mullick Square was evacuated for a week starting April 22. Cross-passages, small tunnels built at intervals of 250m on underground metro lines, allow passengers to cross from one main tunnel to another during emergencies, such as a fire. Although these smaller tunnels are crucial for safety in an underground metro corridor, KMRC had to abandon three of the eight originally planned cross-passages in the Esplanade-Sealdah section after the subsidence incident on October 14, 2022. The East-West Metro project between Esplanade and Sealdah has experienced three such incidents from 2019 to 2022. Over the past month, alongside micro-tunnelling, the construction team also concretized small tunnel rings to create these smaller tunnels connecting the larger twin tunnels. The original site for cross-passage 5B under Nirmal Chunder Street proved to be as porous as three proposed sites beyond this area. After several months of grouting failed to stabilize the soil, the location was shifted to a more stable ground condition below the cinema. However, this new site also required extensive chemical and concrete grouting. On April 16, hi-tech micro-tunnelling using the New Austrian Tunnel Method (NATM) commenced. In less than four days, water seepage was detected at two spots and the work was stopped. A high-rise with a weak foundation was evacuated. From April 22, we worked slowly, lest there was subsidence. Thankfully, there was none, the engineer added.

Next Story
Resources

Skyview by Empyrean is Making Benchmarks in the Indian Ropeway Industry

FIL Industries Private Limited, the parent company of Empyrean Skyview Projects that pioneered ropeway mobility solutions in India with Jammu’s Skyview Gondola, is currently developing the Dehradun-Mussoorie ropeway and is on track to complete Phase I by September 2026. The ropeway is set to be India’s longest passenger aerial monocable covering 5.8 km between the foothills of Dehradun in Purkulgam and MDDA taxi stand in the hills of Mussoorie in just under 20 minutes. The firm pioneered green mobility solutions in India with the development of the flagship Skyview Gondola in Jam..

Next Story
Technology

Creativity is for Humans, Productivity is for Robots!

On most construction sites, the rhythm of progress is measured by the clang of steel, the hum of machinery and the sweat of thousands. But increasingly, new sounds are entering the mix: the quiet efficiency of algorithms, the hum of drones overhead, and the precision of robotic arms at work. Behind the concrete and cables, an invisible force is taking hold: data. It is turning blueprints into living simulations, managing fleets of machines, and helping engineers make decisions before a single brick is laid. This is not the construction of tomorrow; it is the architecture of today – built on ..

Next Story
Infrastructure Urban

Bhartiya Urban Unveils ‘Bhartiya Converge’ GCC Enablement Platform

Bhartiya Urban has launched Bhartiya Converge, its latest business venture designed to become India’s premier platform for enabling Global Capability Centres (GCCs). The initiative offers an integrated ecosystem aimed at helping global clients gain a competitive edge in today’s rapidly evolving business environment. Focused on enhancing turnaround time and operational efficiencies, the company seeks to deliver better business outcomes powered by top-tier talent. Bhartiya Converge presents a customised and integrated suite of microservices that addresses the nuanced and evolving operational..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?