First-of-a-kind for Mumbai: Metro viaduct over water
RAILWAYS & METRO RAIL

First-of-a-kind for Mumbai: Metro viaduct over water

The wait to witness a metro viaduct pass over a water body was over with the last span of the 550-m Kasheli Creek metro viaduct in the Mumbai Metropolitan Region (MMR) is erected. This is part of Phase 1 of the Mumbai Metro Line 5, connecting Thane to Kalyan via Bhiwandi. The Kasheli Creek bridge - first to be crossing the creek- comprises 13 spans, including nine on water, with each span being 42.23 m in length with 15 segments. What’s more, the spans were erected with the help of launching girders in around four months - precisely 123 days.

The bridge has been constructed by Mumbai-based Afcons. Asked how the construction was achieved in just 123 days, Sukesh Singh, Project Manager, Afcons Infrastructure, replies, “The day-to-day activities were monitored at a micro level and exclusive resources were allocated.”

Initial establishments like a temporary jetty to facilitate construction inside water were first erected after necessary permissions and approvals. Thereafter, major components such as piling, pile cap, pier, pier cap and segments as superstructure were executed.

“The piles were constructed using a reverse circular drilling (RCD) machine,” shares Singh. “A barge of 2,143 mt capacity and crawler crane of 150 mt along with vibro hammer, diesel generators and tugboat were used.” He adds that the shutter arrangement for the pile cap was built by supporting on a permanent liner of piles. The piers and pier caps were cast by making supporting arrangement on pile caps.

The major difference in constructing a metro line over water compared to land isdifferent logistics arrangements.In a marine-based project, all logistics must be done via a temporary jetty whereas on land, all the required material can reach exact span locations. It also requires additional floating devices with provisions to carry heavy equipment like aRCD machine and cranes required for marine construction...

To read the full feature, CLICK HERE

.

The wait to witness a metro viaduct pass over a water body was over with the last span of the 550-m Kasheli Creek metro viaduct in the Mumbai Metropolitan Region (MMR) is erected. This is part of Phase 1 of the Mumbai Metro Line 5, connecting Thane to Kalyan via Bhiwandi. The Kasheli Creek bridge - first to be crossing the creek- comprises 13 spans, including nine on water, with each span being 42.23 m in length with 15 segments. What’s more, the spans were erected with the help of launching girders in around four months - precisely 123 days. The bridge has been constructed by Mumbai-based Afcons. Asked how the construction was achieved in just 123 days, Sukesh Singh, Project Manager, Afcons Infrastructure, replies, “The day-to-day activities were monitored at a micro level and exclusive resources were allocated.” Initial establishments like a temporary jetty to facilitate construction inside water were first erected after necessary permissions and approvals. Thereafter, major components such as piling, pile cap, pier, pier cap and segments as superstructure were executed. “The piles were constructed using a reverse circular drilling (RCD) machine,” shares Singh. “A barge of 2,143 mt capacity and crawler crane of 150 mt along with vibro hammer, diesel generators and tugboat were used.” He adds that the shutter arrangement for the pile cap was built by supporting on a permanent liner of piles. The piers and pier caps were cast by making supporting arrangement on pile caps. The major difference in constructing a metro line over water compared to land isdifferent logistics arrangements.In a marine-based project, all logistics must be done via a temporary jetty whereas on land, all the required material can reach exact span locations. It also requires additional floating devices with provisions to carry heavy equipment like aRCD machine and cranes required for marine construction... To read the full feature, CLICK HERE.

Next Story
Infrastructure Transport

MMRDA advances 250 m on Orange Gate–Marine Drive tunnel

The Mumbai Metropolitan Region Development Authority (MMRDA) has completed 250 m of underground tunnelling for the Orange Gate–Marine Drive Urban Road Tunnel using India’s largest slurry shield tunnel boring machine (TBM) deployed for an urban road project.The project involves twin tunnels extending over 7 km beneath critical transport corridors, including Central Railway, Western Railway and Metro Line 3. The work requires high-precision engineering to navigate densely developed urban infrastructure.Once completed, the tunnel is expected to reduce travel time between Orange Gate and Marin..

Next Story
Infrastructure Urban

Hindustan Zinc Pays Rs 188.46 Billion in FY26

Hindustan Zinc contributed Rs 188.46 billion to the public exchequer in FY 2025-26, according to its 9th Tax Transparency Report. The contribution, equivalent to 46 per cent of the company’s revenue, included direct and indirect taxes, government royalties, dividends to the Government of India, withholding taxes and other statutory levies.The company’s five-year cumulative contribution to the exchequer stood at Rs 915.72 billion. In FY26, Hindustan Zinc reported revenue of Rs 408.44 billion, EBITDA of Rs 221.62 billion and profit after tax of Rs 138.32 billion. It also achieved its highest..

Next Story
Infrastructure Urban

World of Concrete India 2026 Opens in Mumbai

Informa Markets in India will host the 12th edition of World of Concrete India 2026 from 3–5 June 2026 at the Bombay Exhibition Centre, Mumbai. The specialised B2B exhibition will bring together manufacturers, suppliers, contractors, developers, architects, consultants, infrastructure companies, project leaders and government stakeholders.The event is expected to feature over 350 brands and more than 18,000 trade professionals. It will cover concrete and cement, dry mortar, precast technologies, formwork, construction chemicals, industrial and commercial flooring, scaffolding, safety solutio..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

-->