First-of-a-kind for Mumbai: Metro viaduct over water
RAILWAYS & METRO RAIL

First-of-a-kind for Mumbai: Metro viaduct over water

The wait to witness a metro viaduct pass over a water body was over with the last span of the 550-m Kasheli Creek metro viaduct in the Mumbai Metropolitan Region (MMR) is erected. This is part of Phase 1 of the Mumbai Metro Line 5, connecting Thane to Kalyan via Bhiwandi. The Kasheli Creek bridge - first to be crossing the creek- comprises 13 spans, including nine on water, with each span being 42.23 m in length with 15 segments. What’s more, the spans were erected with the help of launching girders in around four months - precisely 123 days.

The bridge has been constructed by Mumbai-based Afcons. Asked how the construction was achieved in just 123 days, Sukesh Singh, Project Manager, Afcons Infrastructure, replies, “The day-to-day activities were monitored at a micro level and exclusive resources were allocated.”

Initial establishments like a temporary jetty to facilitate construction inside water were first erected after necessary permissions and approvals. Thereafter, major components such as piling, pile cap, pier, pier cap and segments as superstructure were executed.

“The piles were constructed using a reverse circular drilling (RCD) machine,” shares Singh. “A barge of 2,143 mt capacity and crawler crane of 150 mt along with vibro hammer, diesel generators and tugboat were used.” He adds that the shutter arrangement for the pile cap was built by supporting on a permanent liner of piles. The piers and pier caps were cast by making supporting arrangement on pile caps.

The major difference in constructing a metro line over water compared to land isdifferent logistics arrangements.In a marine-based project, all logistics must be done via a temporary jetty whereas on land, all the required material can reach exact span locations. It also requires additional floating devices with provisions to carry heavy equipment like aRCD machine and cranes required for marine construction...

To read the full feature, CLICK HERE

.

The wait to witness a metro viaduct pass over a water body was over with the last span of the 550-m Kasheli Creek metro viaduct in the Mumbai Metropolitan Region (MMR) is erected. This is part of Phase 1 of the Mumbai Metro Line 5, connecting Thane to Kalyan via Bhiwandi. The Kasheli Creek bridge - first to be crossing the creek- comprises 13 spans, including nine on water, with each span being 42.23 m in length with 15 segments. What’s more, the spans were erected with the help of launching girders in around four months - precisely 123 days. The bridge has been constructed by Mumbai-based Afcons. Asked how the construction was achieved in just 123 days, Sukesh Singh, Project Manager, Afcons Infrastructure, replies, “The day-to-day activities were monitored at a micro level and exclusive resources were allocated.” Initial establishments like a temporary jetty to facilitate construction inside water were first erected after necessary permissions and approvals. Thereafter, major components such as piling, pile cap, pier, pier cap and segments as superstructure were executed. “The piles were constructed using a reverse circular drilling (RCD) machine,” shares Singh. “A barge of 2,143 mt capacity and crawler crane of 150 mt along with vibro hammer, diesel generators and tugboat were used.” He adds that the shutter arrangement for the pile cap was built by supporting on a permanent liner of piles. The piers and pier caps were cast by making supporting arrangement on pile caps. The major difference in constructing a metro line over water compared to land isdifferent logistics arrangements.In a marine-based project, all logistics must be done via a temporary jetty whereas on land, all the required material can reach exact span locations. It also requires additional floating devices with provisions to carry heavy equipment like aRCD machine and cranes required for marine construction... To read the full feature, CLICK HERE.

Next Story
Infrastructure Transport

Metro Line 2B Phase 1 to Boost Realty in Mumbai’s Eastern Suburbs

Mumbai’s real estate sector is set for a major boost as Phase 1 of Metro Line 2B, between Mandale and Diamond Garden, nears completion. The Mumbai Metropolitan Region Development Authority (MMRDA) has confirmed that mandatory rectifications are done, and inspections by the Commissioner of Metro Railway Safety (CMRS) have been carried out. The 5.39-km stretch with five stations forms part of the larger DN Nagar–Mandale corridor, designed to ease congestion and improve east–west connectivity. Passenger operations are expected by December 2025, with the full line slated for 2027. ..

Next Story
Resources

WattPower wins Best Inverter award at Global Solar Expo 2025

WattPower, a leading renewable energy solutions provider, has won the award for “Best Inverter in the Utility Segment” at the Global Solar Expo 2025. The recognition underscores the company’s commitment to delivering reliable, high-performance and future-ready solar solutions for large-scale projects. At the forefront of utility-scale solar, WattPower manufactures advanced string inverters that directly feed power into the Indian grid. With robust technology, high-quality components and comprehensive product lifecycle support, its solutions stand among the most sophisticated in the ..

Next Story
Real Estate

Awfis delivers 67,000 sq. ft. innovation hub for eBay in Bengaluru

Awfis Space Solutions, India’s largest flexible workspace provider and the first publicly listed workspace solutions platform, has partnered with eBay to establish a 67,000 sq. ft. innovation hub at Embassy Tech Village, Bengaluru. The mandate covers design, build and management of the new office, which will act as a strategic hub supporting diverse functions and accelerating eBay’s AI-first commerce strategy. The centre will focus on artificial intelligence, engineering, product development and applied research, strengthening eBay’s growth in India. Embassy Tech Village, North Beng..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?