India, Japan Review Progress Of Rs 1.08 Trillion Bullet Train
RAILWAYS & METRO RAIL

India, Japan Review Progress Of Rs 1.08 Trillion Bullet Train

Union Minister for Railways Ashwini Vaishnaw and Japan’s Minister of Land, Infrastructure, Transport and Tourism Hiromasa Nakano on Friday jointly reviewed the progress of the Mumbai–Ahmedabad High-Speed Rail (MAHSR) Project, India’s first bullet train corridor, being developed at an estimated cost of Rs 1.08 trillion.
Minister Nakano was welcomed with a traditional Garba reception at Surat International Airport, where MP Mukesh Dalal, Mayor Daxesh Mavani, senior railway officials, and representatives from the National High-Speed Rail Corporation Limited (NHSRCL) were present.
At Surat, the ministers inspected the track construction base, where they witnessed the laying of the J-slab ballast-less track system on the elevated viaduct. Vaishnaw highlighted the recent installation of the project’s first track turnout near Surat High-Speed Rail (HSR) Station, marking an important construction milestone.
Later, the delegation travelled by Vande Bharat Express to Mumbai to inspect the Bandra Kurla Complex (BKC) underground bullet train station. Excavation work there has reached a depth of over 30 metres, equivalent to a 10-storey building, with 84 per cent of excavation already completed. The three-level station — comprising a platform, concourse, and service floor — will feature skylights, metro and road connectivity, and modern passenger facilities.

Project Milestones
The 508-kilometre MAHSR corridor has achieved substantial progress:
  • 323 km of viaduct and 399 km of pier construction completed
  • 17 river bridges, 5 PSC bridges, and 9 steel bridges finished
  • 211 km of track bed laid and over 400,000 noise barriers installed
  • 7 mountain tunnels under construction in Palghar and a 21-km NATM tunnel between BKC and Shilphata, with 5 km already completed
  • Construction of rolling stock depots at Surat and Ahmedabad advancing rapidly
  • Station superstructures in Gujarat nearing completion, while work on three elevated stations in Maharashtra has begun
Minister Nakano and the Japanese delegation commended the engineering quality and speed of execution, also praising India’s Vande Bharat Express as a symbol of home-grown technological progress. Both ministers reaffirmed Japan’s continued partnership and support in bringing high-speed rail technology to India.
The Mumbai–Ahmedabad bullet train, which will cut travel time between the two cities to just two hours, represents a cornerstone of India’s modern transport infrastructure. The joint review underscores the strengthening India–Japan collaboration in delivering sustainable, world-class railway systems. 

Union Minister for Railways Ashwini Vaishnaw and Japan’s Minister of Land, Infrastructure, Transport and Tourism Hiromasa Nakano on Friday jointly reviewed the progress of the Mumbai–Ahmedabad High-Speed Rail (MAHSR) Project, India’s first bullet train corridor, being developed at an estimated cost of Rs 1.08 trillion.Minister Nakano was welcomed with a traditional Garba reception at Surat International Airport, where MP Mukesh Dalal, Mayor Daxesh Mavani, senior railway officials, and representatives from the National High-Speed Rail Corporation Limited (NHSRCL) were present.At Surat, the ministers inspected the track construction base, where they witnessed the laying of the J-slab ballast-less track system on the elevated viaduct. Vaishnaw highlighted the recent installation of the project’s first track turnout near Surat High-Speed Rail (HSR) Station, marking an important construction milestone.Later, the delegation travelled by Vande Bharat Express to Mumbai to inspect the Bandra Kurla Complex (BKC) underground bullet train station. Excavation work there has reached a depth of over 30 metres, equivalent to a 10-storey building, with 84 per cent of excavation already completed. The three-level station — comprising a platform, concourse, and service floor — will feature skylights, metro and road connectivity, and modern passenger facilities.Project MilestonesThe 508-kilometre MAHSR corridor has achieved substantial progress:323 km of viaduct and 399 km of pier construction completed17 river bridges, 5 PSC bridges, and 9 steel bridges finished211 km of track bed laid and over 400,000 noise barriers installed7 mountain tunnels under construction in Palghar and a 21-km NATM tunnel between BKC and Shilphata, with 5 km already completedConstruction of rolling stock depots at Surat and Ahmedabad advancing rapidlyStation superstructures in Gujarat nearing completion, while work on three elevated stations in Maharashtra has begunMinister Nakano and the Japanese delegation commended the engineering quality and speed of execution, also praising India’s Vande Bharat Express as a symbol of home-grown technological progress. Both ministers reaffirmed Japan’s continued partnership and support in bringing high-speed rail technology to India.The Mumbai–Ahmedabad bullet train, which will cut travel time between the two cities to just two hours, represents a cornerstone of India’s modern transport infrastructure. The joint review underscores the strengthening India–Japan collaboration in delivering sustainable, world-class railway systems. 

Next Story
Infrastructure Urban

InsideFPV Delivers ₹10 Crore Kamikaze Drone Order Under MoD’s EPR Route

InsideFPV, a Surat-based drone technology manufacturer, has successfully executed a ₹10 crore defence contract to supply indigenous kamikaze drones under the Ministry of Defence’s Emergency Procurement Route (EPR). The company completed the delivery of hundreds of FPV kamikaze drone platforms within a rapid two-month timeframe, highlighting its ability to meet urgent military procurement timelines.The supply orders were fulfilled under the emergency procurement mechanism, which is aimed at fast-tracking acquisitions for immediate operational needs. InsideFPV’s quick execution reflects it..

Next Story
Infrastructure Energy

Vedanta Resources Secures Fitch Upgrade to ‘BB-’, Best Rating Since 2015

Vedanta Resources Limited (VRL), a global player in metals, oil & gas, critical minerals, power and technology, has received a credit rating upgrade from Fitch Ratings, marking its strongest bond rating in over a decade.Fitch has raised Vedanta Resources’ Long-Term Foreign-Currency Issuer Default Rating (IDR) to ‘BB-’ from ‘B+’, while maintaining a Stable Outlook. The agency also upgraded VRL’s senior unsecured rating, along with the ratings of US dollar-denominated bonds issued by Vedanta Resources Finance II Plc and guaranteed by VRL, to ‘BB-’.The upgrade represents Vedan..

Next Story
Real Estate

NAREDCO NextGen NCR Chapter Launched

The NAREDCO NextGen NCR Chapter was recently launched at Excelerate 2026 in Mumbai, marking a key step towards integrating emerging real estate leaders from the National Capital Region with the national platform. The initiative aims to promote sustainable and responsible urban development through collaboration and knowledge exchange.The event brought together young developers, entrepreneurs, and professionals from across NCR, including Noida, Gurugram, Ghaziabad, Faridabad, Bhiwadi, and Meerut. Discussions focused on urban development, finance, sustainability, innovation, and policy, emphasisi..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement