Indian Railways Sets 120-Day Deadline to Redevelop Ahmedabad Platforms
RAILWAYS & METRO RAIL

Indian Railways Sets 120-Day Deadline to Redevelop Ahmedabad Platforms

Indian Railways has set a 120-day deadline to redevelop platforms 4, 5, 6 and 7 at Ahmedabad Railway Station as part of an upgrade of passenger infrastructure. The project includes a modern concourse and improved facilities at the station, which is administered by the Western Railway (WR) zone.

To accelerate the work, Ahmedabad Division Divisional Railway Manager (DRM) Ved Prakash held a review meeting with officials from the Rail Land Development Authority, railway departments and the construction agency. Discussions covered construction progress, technical challenges, manpower and machinery availability, material supplies and coordination between the agencies involved.

Officials also reviewed the traffic and power blocks required for the construction. The plan includes 457 piles, 108 pile caps and 213 pedestals for platforms 4 and 5, and platforms 6 and 7. Around 6,400 t of structural steel will be fabricated and erected for the new concourse and related facilities.

The DRM directed officials to prioritise pile foundation work, pile caps and pedestals, Ballastless Track (BLT) work, and structural steel fabrication and erection. He also called for detailed planning at every stage and instructed the agencies to ensure adequate manpower, machinery and construction materials so the project can meet the 120-day schedule.

The redevelopment will be carried out while trains continue to operate through the station. Ahmedabad handles significant passenger and train movement, requiring the construction agencies to maintain operational continuity and passenger safety throughout the work. Railway officials said the project is intended to provide modern, safe and convenient facilities, including a world-class concourse, for passengers using the station.

Indian Railways has set a 120-day deadline to redevelop platforms 4, 5, 6 and 7 at Ahmedabad Railway Station as part of an upgrade of passenger infrastructure. The project includes a modern concourse and improved facilities at the station, which is administered by the Western Railway (WR) zone. To accelerate the work, Ahmedabad Division Divisional Railway Manager (DRM) Ved Prakash held a review meeting with officials from the Rail Land Development Authority, railway departments and the construction agency. Discussions covered construction progress, technical challenges, manpower and machinery availability, material supplies and coordination between the agencies involved. Officials also reviewed the traffic and power blocks required for the construction. The plan includes 457 piles, 108 pile caps and 213 pedestals for platforms 4 and 5, and platforms 6 and 7. Around 6,400 t of structural steel will be fabricated and erected for the new concourse and related facilities. The DRM directed officials to prioritise pile foundation work, pile caps and pedestals, Ballastless Track (BLT) work, and structural steel fabrication and erection. He also called for detailed planning at every stage and instructed the agencies to ensure adequate manpower, machinery and construction materials so the project can meet the 120-day schedule. The redevelopment will be carried out while trains continue to operate through the station. Ahmedabad handles significant passenger and train movement, requiring the construction agencies to maintain operational continuity and passenger safety throughout the work. Railway officials said the project is intended to provide modern, safe and convenient facilities, including a world-class concourse, for passengers using the station.

Related Stories

Gold Stories

Next Story
Technology

ABB Unveils Intelligent Motor to Accelerate Industrial AI Adoption

ABB recently launched Intelleqt, which it describes as the world’s first low-voltage motor with factory-integrated intelligence, at the SPS trade fair in Germany. Designed to deliver real-time operational insights from its first rotation, the motor enables industrial operators to integrate equipment-level data into existing digital platforms while retaining full ownership of their data.The launch addresses growing challenges in scaling artificial intelligence (AI) across industrial operations, particularly data quality and availability. According to Deloitte, while 84 per cent of manufacture..

Next Story
Real Estate

Hiranandani’s Centaurus Becomes India’s First SmartScore Platinum Tower

House of Hiranandani’s Centaurus, a Grade A commercial tower at Hiranandani Estate, Thane, recently became India’s first building to achieve SmartScore Platinum certification, the highest rating under the globally recognised smart building certification framework. The development is also the country’s first building to hold both SmartScore and WiredScore certifications at the Platinum level.SmartScore certification evaluates a building’s smart capabilities, digital infrastructure, intelligent building systems and technology-led solutions that enhance occupier experience, operational ef..

Next Story
Infrastructure Transport

PM Modi May Lay Foundation Stone for Mamnoor Airport in December

Prime Minister Narendra Modi is expected to lay the foundation stone for Mamnoor Airport in Warangal during a proposed visit to Telangana in December, according to a tentative schedule. A public meeting is also being planned, with the event likely to form a central part of the Bharatiya Janata Party’s campaign ahead of Legislative Council and civic elections. The BJP is preparing to present the proposed airport, highway construction, railway modernisation, the Kazipet coach factory and improved urban connectivity as evidence of the Union government’s infrastructure focus in Telangana. The ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code