Kilambakkam Station, Skywalk Opening Delayed To January 2026
RAILWAYS & METRO RAIL

Kilambakkam Station, Skywalk Opening Delayed To January 2026

The long-awaited Kilambakkam railway station and pedestrian skywalk connecting it to the Kilambakkam Kalaignar Centenary Bus Terminus (KCBT) will now open only by January 2026, after multiple construction delays by both the Chennai Metropolitan Development Authority (CMDA) and Southern Railway. The postponement has left thousands of commuters struggling with poor connectivity during the ongoing festive season.
Located nearly 25 kilometres from Chennai, KCBT serves as a major hub for mofussil and SETC buses heading to districts across Tamil Nadu. In the absence of train connectivity, commuters are spending between Rs 300 and Rs 500 on autorickshaws and cabs to reach the terminus. With no foot overbridge (FOB) or pedestrian pathway in place, hundreds continue to risk their lives crossing the busy GST Road on foot to access the bus stand.
The halt station project, which began in September 2023 with a 12-month deadline, has seen minimal progress despite assurances that “all bottlenecks have been cleared”. The 450-metre-long skywalk across GST Road, meant to provide safe access from the railway station to the terminus, also remains incomplete, with little visible work in front of KCBT.
The state government has already transferred Rs 200 million to the Railways for station development. However, both agencies have blamed each other for the delay. Southern Railway officials stated that while one platform with shelters has been completed, the 400-metre island platform is still under construction, with earth-filling and foundation works currently under way.
A spokesperson from the Chennai railway division said,
“CMDA’s delay in completing the foot overbridge has stalled the remaining station works. Once the FOB is finished, we will take up the pending platform construction.”
Meanwhile, CMDA officials said that pillars for the FOB have been installed at the MTC bus stand, and work on the skywalk over GST Road will proceed in two phases — one section after Ayudha Pooja, and the other after Deepavali, with the full structure expected to be completed by January 2026.
KCBT currently handles nearly 200,000 commuters on weekends and festival days, but lacks direct public transport links apart from city buses. This has forced passengers travelling to the southern, delta, and northern districts to depend on costly private transport.
S. Rajarathinam, a commuter from St. Thomas Mount, said,
“Fearing traffic congestion, I reached the bus stand two hours early for my SETC bus. I spent Rs 400 just to get there. The government should not have shifted the terminus without ensuring proper public transport connectivity.”
The delay in completing the Kilambakkam station and skywalk has once again highlighted coordination lapses between CMDA and Southern Railway, frustrating commuters who were promised a seamless transport corridor to one of Chennai’s busiest bus terminals. 

The long-awaited Kilambakkam railway station and pedestrian skywalk connecting it to the Kilambakkam Kalaignar Centenary Bus Terminus (KCBT) will now open only by January 2026, after multiple construction delays by both the Chennai Metropolitan Development Authority (CMDA) and Southern Railway. The postponement has left thousands of commuters struggling with poor connectivity during the ongoing festive season.Located nearly 25 kilometres from Chennai, KCBT serves as a major hub for mofussil and SETC buses heading to districts across Tamil Nadu. In the absence of train connectivity, commuters are spending between Rs 300 and Rs 500 on autorickshaws and cabs to reach the terminus. With no foot overbridge (FOB) or pedestrian pathway in place, hundreds continue to risk their lives crossing the busy GST Road on foot to access the bus stand.The halt station project, which began in September 2023 with a 12-month deadline, has seen minimal progress despite assurances that “all bottlenecks have been cleared”. The 450-metre-long skywalk across GST Road, meant to provide safe access from the railway station to the terminus, also remains incomplete, with little visible work in front of KCBT.The state government has already transferred Rs 200 million to the Railways for station development. However, both agencies have blamed each other for the delay. Southern Railway officials stated that while one platform with shelters has been completed, the 400-metre island platform is still under construction, with earth-filling and foundation works currently under way.A spokesperson from the Chennai railway division said,“CMDA’s delay in completing the foot overbridge has stalled the remaining station works. Once the FOB is finished, we will take up the pending platform construction.”Meanwhile, CMDA officials said that pillars for the FOB have been installed at the MTC bus stand, and work on the skywalk over GST Road will proceed in two phases — one section after Ayudha Pooja, and the other after Deepavali, with the full structure expected to be completed by January 2026.KCBT currently handles nearly 200,000 commuters on weekends and festival days, but lacks direct public transport links apart from city buses. This has forced passengers travelling to the southern, delta, and northern districts to depend on costly private transport.S. Rajarathinam, a commuter from St. Thomas Mount, said,“Fearing traffic congestion, I reached the bus stand two hours early for my SETC bus. I spent Rs 400 just to get there. The government should not have shifted the terminus without ensuring proper public transport connectivity.”The delay in completing the Kilambakkam station and skywalk has once again highlighted coordination lapses between CMDA and Southern Railway, frustrating commuters who were promised a seamless transport corridor to one of Chennai’s busiest bus terminals. 

Related Stories

Gold Stories

Next Story
Infrastructure Urban

BMW Ventures Secures Rs 249.83 Million (mn) Steel Orders

BMW Ventures Limited said it has secured two purchase orders totalling Rs 249.83 million (mn) from Lata Projects Limited for the supply of TMT steel FE-550D grade for three units of 800 megawatt (MW) capacity at the USCTPP Adani project. The orders were disclosed to the stock exchanges under Regulation 30 of the SEBI Listing Regulations and carry a contract value inclusive of all taxes.\n\nThe company stated that the orders will be executed within eight weeks from the date of the purchase orders and that the contract provides for 100 per cent advance payment with specified guarantees. The supp..

Next Story
Real Estate

Housing Sales Dip in Top Eight Cities in Q2, Pune and Bengaluru Hit Hard

Housing sales across the top eight cities fell six point one per cent year-on-year to 91,729 units in the April-June quarter from 97,674 a year earlier, PropTiger’s Real Insight Residential report showed. The moderation reflected seasonal pre-monsoon effects and heightened buyer caution amid the US-Iran conflict. New launches rose six per cent to 89,161 units. The impact was concentrated in technology-driven markets, with Pune and Bengaluru among the hardest hit. Pune recorded the steepest annual decline at 20.8 per cent, with sales falling to 12,642 units, while Ahmedabad declined 20.2 per ..

Next Story
Infrastructure Urban

India And ADB Sign US$230 Million Loan To Modernise Chennai Water

The Government of India and the Asian Development Bank (ADB) signed a US$230 million loan to modernise and expand water supply and sanitation infrastructure in Chennai. Saurabh Singh, Deputy Secretary, Department of Economic Affairs (DEA), signed on behalf of the Government of India and Mio Oka, Country Director of ADB’s India Resident Mission, signed for the lender. The engagement was guided by Baldeo Purushartha, Joint Secretary (ADB and Japan), DEA. The Chennai Climate-Resilient Water Security and Sewerage Project aims to improve access to safe and reliable water and sanitation citywide w..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code