Kilambakkam Station, Skywalk Opening Delayed To January 2026
RAILWAYS & METRO RAIL

Kilambakkam Station, Skywalk Opening Delayed To January 2026

The long-awaited Kilambakkam railway station and pedestrian skywalk connecting it to the Kilambakkam Kalaignar Centenary Bus Terminus (KCBT) will now open only by January 2026, after multiple construction delays by both the Chennai Metropolitan Development Authority (CMDA) and Southern Railway. The postponement has left thousands of commuters struggling with poor connectivity during the ongoing festive season.
Located nearly 25 kilometres from Chennai, KCBT serves as a major hub for mofussil and SETC buses heading to districts across Tamil Nadu. In the absence of train connectivity, commuters are spending between Rs 300 and Rs 500 on autorickshaws and cabs to reach the terminus. With no foot overbridge (FOB) or pedestrian pathway in place, hundreds continue to risk their lives crossing the busy GST Road on foot to access the bus stand.
The halt station project, which began in September 2023 with a 12-month deadline, has seen minimal progress despite assurances that “all bottlenecks have been cleared”. The 450-metre-long skywalk across GST Road, meant to provide safe access from the railway station to the terminus, also remains incomplete, with little visible work in front of KCBT.
The state government has already transferred Rs 200 million to the Railways for station development. However, both agencies have blamed each other for the delay. Southern Railway officials stated that while one platform with shelters has been completed, the 400-metre island platform is still under construction, with earth-filling and foundation works currently under way.
A spokesperson from the Chennai railway division said,
“CMDA’s delay in completing the foot overbridge has stalled the remaining station works. Once the FOB is finished, we will take up the pending platform construction.”
Meanwhile, CMDA officials said that pillars for the FOB have been installed at the MTC bus stand, and work on the skywalk over GST Road will proceed in two phases — one section after Ayudha Pooja, and the other after Deepavali, with the full structure expected to be completed by January 2026.
KCBT currently handles nearly 200,000 commuters on weekends and festival days, but lacks direct public transport links apart from city buses. This has forced passengers travelling to the southern, delta, and northern districts to depend on costly private transport.
S. Rajarathinam, a commuter from St. Thomas Mount, said,
“Fearing traffic congestion, I reached the bus stand two hours early for my SETC bus. I spent Rs 400 just to get there. The government should not have shifted the terminus without ensuring proper public transport connectivity.”
The delay in completing the Kilambakkam station and skywalk has once again highlighted coordination lapses between CMDA and Southern Railway, frustrating commuters who were promised a seamless transport corridor to one of Chennai’s busiest bus terminals. 

The long-awaited Kilambakkam railway station and pedestrian skywalk connecting it to the Kilambakkam Kalaignar Centenary Bus Terminus (KCBT) will now open only by January 2026, after multiple construction delays by both the Chennai Metropolitan Development Authority (CMDA) and Southern Railway. The postponement has left thousands of commuters struggling with poor connectivity during the ongoing festive season.Located nearly 25 kilometres from Chennai, KCBT serves as a major hub for mofussil and SETC buses heading to districts across Tamil Nadu. In the absence of train connectivity, commuters are spending between Rs 300 and Rs 500 on autorickshaws and cabs to reach the terminus. With no foot overbridge (FOB) or pedestrian pathway in place, hundreds continue to risk their lives crossing the busy GST Road on foot to access the bus stand.The halt station project, which began in September 2023 with a 12-month deadline, has seen minimal progress despite assurances that “all bottlenecks have been cleared”. The 450-metre-long skywalk across GST Road, meant to provide safe access from the railway station to the terminus, also remains incomplete, with little visible work in front of KCBT.The state government has already transferred Rs 200 million to the Railways for station development. However, both agencies have blamed each other for the delay. Southern Railway officials stated that while one platform with shelters has been completed, the 400-metre island platform is still under construction, with earth-filling and foundation works currently under way.A spokesperson from the Chennai railway division said,“CMDA’s delay in completing the foot overbridge has stalled the remaining station works. Once the FOB is finished, we will take up the pending platform construction.”Meanwhile, CMDA officials said that pillars for the FOB have been installed at the MTC bus stand, and work on the skywalk over GST Road will proceed in two phases — one section after Ayudha Pooja, and the other after Deepavali, with the full structure expected to be completed by January 2026.KCBT currently handles nearly 200,000 commuters on weekends and festival days, but lacks direct public transport links apart from city buses. This has forced passengers travelling to the southern, delta, and northern districts to depend on costly private transport.S. Rajarathinam, a commuter from St. Thomas Mount, said,“Fearing traffic congestion, I reached the bus stand two hours early for my SETC bus. I spent Rs 400 just to get there. The government should not have shifted the terminus without ensuring proper public transport connectivity.”The delay in completing the Kilambakkam station and skywalk has once again highlighted coordination lapses between CMDA and Southern Railway, frustrating commuters who were promised a seamless transport corridor to one of Chennai’s busiest bus terminals. 

Next Story
Infrastructure Urban

13 Firms Apply Under PLI Scheme with Rs 19.14 bn Investment

The fourth round of the Production Linked Incentive (PLI) Scheme for White Goods, covering air conditioners and LED lights, has attracted 13 applications with a committed investment of Rs 19.14 billion. The Department for Promotion of Industry and Internal Trade (DPIIT) had kept the window open from 15 September to 10 November 2025. Over half of the new applicants are Micro, Small and Medium Enterprises (MSMEs), signalling rising confidence among smaller manufacturers in joining the domestic AC and LED components value chain. Of the 13 applicants, one is an existing beneficiary that has pledg..

Next Story
Infrastructure Urban

TEC, SRMIST Partner to Boost Indigenous Telecom R&D and Standards

The Telecommunication Engineering Centre (TEC), the technical arm of the Department of Telecommunications (DoT), has signed an MoU with the SRM Institute of Science and Technology (SRMIST) to collaborate on research, joint studies, and technical contributions in advanced telecom technologies and global standardisation. The partnership focuses on creating India-specific standards, test frameworks, and contributions to future network technologies including 6G, Artificial Intelligence (AI), Non-Terrestrial Networks (NTN), and Quantum Communication. It also seeks to strengthen India’s role in I..

Next Story
Infrastructure Urban

C-DOT, NAM InfoCom Partner to Develop Mission-Critical MCX System

The Centre for Development of Telematics (C-DOT) has signed an agreement with NAM InfoCom Private to jointly develop an indigenous Mission Critical Communication System (MCX) solution. The collaboration is a major step towards strengthening India’s public safety and emergency communication infrastructure. Under the C-DOT MCX Alliance, the organisation has partnered with 10 entities—primarily startups—to build a comprehensive MCX ecosystem. The new MCX platform is aligned with 3GPP standards and supports Mission Critical Push-to-Talk, Mission Critical Data, and Mission Critical Video ser..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement