Kilambakkam Station, Skywalk Opening Delayed To January 2026
RAILWAYS & METRO RAIL

Kilambakkam Station, Skywalk Opening Delayed To January 2026

The long-awaited Kilambakkam railway station and pedestrian skywalk connecting it to the Kilambakkam Kalaignar Centenary Bus Terminus (KCBT) will now open only by January 2026, after multiple construction delays by both the Chennai Metropolitan Development Authority (CMDA) and Southern Railway. The postponement has left thousands of commuters struggling with poor connectivity during the ongoing festive season.
Located nearly 25 kilometres from Chennai, KCBT serves as a major hub for mofussil and SETC buses heading to districts across Tamil Nadu. In the absence of train connectivity, commuters are spending between Rs 300 and Rs 500 on autorickshaws and cabs to reach the terminus. With no foot overbridge (FOB) or pedestrian pathway in place, hundreds continue to risk their lives crossing the busy GST Road on foot to access the bus stand.
The halt station project, which began in September 2023 with a 12-month deadline, has seen minimal progress despite assurances that “all bottlenecks have been cleared”. The 450-metre-long skywalk across GST Road, meant to provide safe access from the railway station to the terminus, also remains incomplete, with little visible work in front of KCBT.
The state government has already transferred Rs 200 million to the Railways for station development. However, both agencies have blamed each other for the delay. Southern Railway officials stated that while one platform with shelters has been completed, the 400-metre island platform is still under construction, with earth-filling and foundation works currently under way.
A spokesperson from the Chennai railway division said,
“CMDA’s delay in completing the foot overbridge has stalled the remaining station works. Once the FOB is finished, we will take up the pending platform construction.”
Meanwhile, CMDA officials said that pillars for the FOB have been installed at the MTC bus stand, and work on the skywalk over GST Road will proceed in two phases — one section after Ayudha Pooja, and the other after Deepavali, with the full structure expected to be completed by January 2026.
KCBT currently handles nearly 200,000 commuters on weekends and festival days, but lacks direct public transport links apart from city buses. This has forced passengers travelling to the southern, delta, and northern districts to depend on costly private transport.
S. Rajarathinam, a commuter from St. Thomas Mount, said,
“Fearing traffic congestion, I reached the bus stand two hours early for my SETC bus. I spent Rs 400 just to get there. The government should not have shifted the terminus without ensuring proper public transport connectivity.”
The delay in completing the Kilambakkam station and skywalk has once again highlighted coordination lapses between CMDA and Southern Railway, frustrating commuters who were promised a seamless transport corridor to one of Chennai’s busiest bus terminals. 

"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

The long-awaited Kilambakkam railway station and pedestrian skywalk connecting it to the Kilambakkam Kalaignar Centenary Bus Terminus (KCBT) will now open only by January 2026, after multiple construction delays by both the Chennai Metropolitan Development Authority (CMDA) and Southern Railway. The postponement has left thousands of commuters struggling with poor connectivity during the ongoing festive season.Located nearly 25 kilometres from Chennai, KCBT serves as a major hub for mofussil and SETC buses heading to districts across Tamil Nadu. In the absence of train connectivity, commuters are spending between Rs 300 and Rs 500 on autorickshaws and cabs to reach the terminus. With no foot overbridge (FOB) or pedestrian pathway in place, hundreds continue to risk their lives crossing the busy GST Road on foot to access the bus stand.The halt station project, which began in September 2023 with a 12-month deadline, has seen minimal progress despite assurances that “all bottlenecks have been cleared”. The 450-metre-long skywalk across GST Road, meant to provide safe access from the railway station to the terminus, also remains incomplete, with little visible work in front of KCBT.The state government has already transferred Rs 200 million to the Railways for station development. However, both agencies have blamed each other for the delay. Southern Railway officials stated that while one platform with shelters has been completed, the 400-metre island platform is still under construction, with earth-filling and foundation works currently under way.A spokesperson from the Chennai railway division said,“CMDA’s delay in completing the foot overbridge has stalled the remaining station works. Once the FOB is finished, we will take up the pending platform construction.”Meanwhile, CMDA officials said that pillars for the FOB have been installed at the MTC bus stand, and work on the skywalk over GST Road will proceed in two phases — one section after Ayudha Pooja, and the other after Deepavali, with the full structure expected to be completed by January 2026.KCBT currently handles nearly 200,000 commuters on weekends and festival days, but lacks direct public transport links apart from city buses. This has forced passengers travelling to the southern, delta, and northern districts to depend on costly private transport.S. Rajarathinam, a commuter from St. Thomas Mount, said,“Fearing traffic congestion, I reached the bus stand two hours early for my SETC bus. I spent Rs 400 just to get there. The government should not have shifted the terminus without ensuring proper public transport connectivity.”The delay in completing the Kilambakkam station and skywalk has once again highlighted coordination lapses between CMDA and Southern Railway, frustrating commuters who were promised a seamless transport corridor to one of Chennai’s busiest bus terminals. 

Next Story
Infrastructure Urban

ABS Marine Sees CRISIL Credit Rating Upgrade

ABS Marine Services has secured an upgrade to its long term and short term credit ratings from CRISIL, reflecting improved profitability and revenue growth through long term contracts. CRISIL moved the long term rating from BBB+/Stable to A-/Stable and revised the short term rating from A2 to A2+. The action signals strengthened financial metrics and operational resilience. The company benefited from durable client relationships with firms such as ONGC and Schlumberger. The rating decision followed stronger cash flows and an enlarged bank loan facility, which increased from Rs 3,705 million (m..

Next Story
Infrastructure Transport

Project BRAHMANK Marks 16 Years Of Strategic Roads In Arunachal

Project BRAHMANK is marking 16 years of work to establish strategic road and bridge links across Arunachal Pradesh, maintaining and developing 811 kilometres of roads and nearly 86 bridges that range from small culverts to large steel and arch bridges. These transport links are described as critical for ensuring year-round movement of defence personnel, equipment and essential supplies while improving everyday travel for people in remote villages. The project balances national security requirements with regional development by focusing on reliable access in challenging terrain. Notable enginee..

Next Story
Infrastructure Transport

Longleng CSOs Give One Week Ultimatum Over Two-Lane Highway

Civil society organisations (CSOs) in Longleng district have demanded immediate restoration of the deteriorating Changtongya–Longleng two-lane road and sought a detailed status report on the stalled construction within one week. The demand followed a consultative meeting convened under the Phom Peoples' Council (PPC) to discuss welfare and development concerns. PPC president YB Angam Phom said prolonged non-maintenance had caused hardship to commuters and affected transportation, local commerce and the district's development. The meeting urged authorities to undertake immediate restoration a..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement