Kochi Metro Pink Line To Add 20 Million Riders Monthly
RAILWAYS & METRO RAIL

Kochi Metro Pink Line To Add 20 Million Riders Monthly

The upcoming 11.2-kilometre Pink Line of the Kochi Metro, stretching from JLN Stadium in Kaloor to Infopark in Kakkanad, is expected to transform urban travel patterns in the city. Scheduled to open next year, the new corridor is projected to attract an additional 20 million commuters per month, significantly reducing reliance on private vehicles, according to Kochi Metro Rail Ltd (KMRL) estimates.

At present, Kochi Metro’s Phase 1 corridor, spanning 28.125 kilometres from Aluva to Tripunithura, serves an average of 30 million commuters monthly, with a record ridership of 3.41 million in August 2025. “After the commissioning of the entire Pink Line, we expect monthly ridership to rise to around 50 million,” said a KMRL spokesperson.

KMRL aims to open the first five stations up to Padamugal by June 2026, with the entire Phase 2 corridor targeted for completion by December 2026. “It is too early to confirm ridership figures for the first stretch. The final decision on whether Infopark trains will terminate at JLN or continue to other destinations such as Tripunithura will depend on future traffic studies,” the official added.

A detailed passenger traffic analysis will soon determine whether to extend the Infopark services beyond the JLN Stadium interchange station on the Blue Line. Potential extensions include key interchange stations such as Maharaja’s, Kadavanthra, Vyttila, and Tripunithura.

Work on the Infopark corridor has accelerated, with KMRL targeting a June 30, 2026 deadline. However, two major engineering challenges remain — crossing NH 66 at the Palarivattom flyover and constructing an elevated track over the Aluva–Tripunithura Metro line near Kurishupally. The proposed Edappally–Aroor elevated highway, planned at a height of 32 metres above the flyover and metro viaduct, will require close coordination between the National Highways Authority of India (NHAI) and KMRL.

The Kurishupally crossover, where one metro track passes above another, is expected to become an architectural highlight. The Infopark-bound line will rise above the existing Phase 1 track, while the returning line will run parallel on the opposite side, avoiding the need for an additional overpass.

Civil work on Phase 2 has made substantial headway. The first U-girder was installed over the pillars on the Infopark Expressway on 24 October, marking the transition from piling to viaduct construction. So far, 65 pillars and over 1,000 piles for the viaduct and stations have been completed. At the casting yard, work has been completed on 100 U-girders, 72 A-girders, and 100 pier caps.

Tender progress:

Awarded: Construction of viaducts, stations, entry/exit gates

Under evaluation: Architecture and track work

Floated: Traction work (bids under review)

Pending: Telecom and signalling (to be invited within six weeks)

Once operational, the Pink Line will not only strengthen connectivity to Kochi’s IT and business hub of Kakkanad but also mark a major step toward sustainable, high-capacity urban transport in Kerala’s commercial capital.

"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

The upcoming 11.2-kilometre Pink Line of the Kochi Metro, stretching from JLN Stadium in Kaloor to Infopark in Kakkanad, is expected to transform urban travel patterns in the city. Scheduled to open next year, the new corridor is projected to attract an additional 20 million commuters per month, significantly reducing reliance on private vehicles, according to Kochi Metro Rail Ltd (KMRL) estimates. At present, Kochi Metro’s Phase 1 corridor, spanning 28.125 kilometres from Aluva to Tripunithura, serves an average of 30 million commuters monthly, with a record ridership of 3.41 million in August 2025. “After the commissioning of the entire Pink Line, we expect monthly ridership to rise to around 50 million,” said a KMRL spokesperson. KMRL aims to open the first five stations up to Padamugal by June 2026, with the entire Phase 2 corridor targeted for completion by December 2026. “It is too early to confirm ridership figures for the first stretch. The final decision on whether Infopark trains will terminate at JLN or continue to other destinations such as Tripunithura will depend on future traffic studies,” the official added. A detailed passenger traffic analysis will soon determine whether to extend the Infopark services beyond the JLN Stadium interchange station on the Blue Line. Potential extensions include key interchange stations such as Maharaja’s, Kadavanthra, Vyttila, and Tripunithura. Work on the Infopark corridor has accelerated, with KMRL targeting a June 30, 2026 deadline. However, two major engineering challenges remain — crossing NH 66 at the Palarivattom flyover and constructing an elevated track over the Aluva–Tripunithura Metro line near Kurishupally. The proposed Edappally–Aroor elevated highway, planned at a height of 32 metres above the flyover and metro viaduct, will require close coordination between the National Highways Authority of India (NHAI) and KMRL. The Kurishupally crossover, where one metro track passes above another, is expected to become an architectural highlight. The Infopark-bound line will rise above the existing Phase 1 track, while the returning line will run parallel on the opposite side, avoiding the need for an additional overpass. Civil work on Phase 2 has made substantial headway. The first U-girder was installed over the pillars on the Infopark Expressway on 24 October, marking the transition from piling to viaduct construction. So far, 65 pillars and over 1,000 piles for the viaduct and stations have been completed. At the casting yard, work has been completed on 100 U-girders, 72 A-girders, and 100 pier caps. Tender progress: Awarded: Construction of viaducts, stations, entry/exit gates Under evaluation: Architecture and track work Floated: Traction work (bids under review) Pending: Telecom and signalling (to be invited within six weeks) Once operational, the Pink Line will not only strengthen connectivity to Kochi’s IT and business hub of Kakkanad but also mark a major step toward sustainable, high-capacity urban transport in Kerala’s commercial capital.

Next Story
Infrastructure Urban

ABS Marine Sees CRISIL Credit Rating Upgrade

ABS Marine Services has secured an upgrade to its long term and short term credit ratings from CRISIL, reflecting improved profitability and revenue growth through long term contracts. CRISIL moved the long term rating from BBB+/Stable to A-/Stable and revised the short term rating from A2 to A2+. The action signals strengthened financial metrics and operational resilience. The company benefited from durable client relationships with firms such as ONGC and Schlumberger. The rating decision followed stronger cash flows and an enlarged bank loan facility, which increased from Rs 3,705 million (m..

Next Story
Infrastructure Transport

Project BRAHMANK Marks 16 Years Of Strategic Roads In Arunachal

Project BRAHMANK is marking 16 years of work to establish strategic road and bridge links across Arunachal Pradesh, maintaining and developing 811 kilometres of roads and nearly 86 bridges that range from small culverts to large steel and arch bridges. These transport links are described as critical for ensuring year-round movement of defence personnel, equipment and essential supplies while improving everyday travel for people in remote villages. The project balances national security requirements with regional development by focusing on reliable access in challenging terrain. Notable enginee..

Next Story
Infrastructure Transport

Longleng CSOs Give One Week Ultimatum Over Two-Lane Highway

Civil society organisations (CSOs) in Longleng district have demanded immediate restoration of the deteriorating Changtongya–Longleng two-lane road and sought a detailed status report on the stalled construction within one week. The demand followed a consultative meeting convened under the Phom Peoples' Council (PPC) to discuss welfare and development concerns. PPC president YB Angam Phom said prolonged non-maintenance had caused hardship to commuters and affected transportation, local commerce and the district's development. The meeting urged authorities to undertake immediate restoration a..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement