MC Orders Completion Of Sadhu Vaswani Railway Overpass By Dec 2026
RAILWAYS & METRO RAIL

MC Orders Completion Of Sadhu Vaswani Railway Overpass By Dec 2026

Pune Municipal Corporation (PMC) municipal commissioner Naval Kishore Ram directed civic officials to complete the Sadhu Vaswani railway overpass by December 2026 after a site inspection. He instructed the project department to expedite work while ensuring close coordination with railway authorities and the traffic police. Ram set a requirement for monthly site inspections to review progress and to ensure adherence to technical standards and safety protocols during the remaining construction.

The project requires launching a 54-metre open web girder across a busy railway section that carries more than 240 trains each day, creating significant technical and operational challenges. Work under the project began in June 2024 but actual construction started nearly a year later owing to delays in obtaining clearances and resolving engineering issues. The PMC reported that approximately 75 per cent of the overall work has been completed and remaining tasks will be accelerated.

Delays stemmed from the need to relocate an existing overhead water pipeline with a diameter of one metre, complete underground laying, secure permissions from the railway ministry and revise parts of the project plan. These issues have been addressed, the project department said, and a new contractor has been appointed to remove the remaining overhead truss at the span, work that is expected to finish within a week. Once the truss is removed, the launch of the girder is slated for the end of September.

Commuters and local residents have reported persistent congestion on Bund Garden Road and at Wadia College Chowk, and civic officials acknowledged the project is a crucial link for the area. The PMC said it will coordinate traffic diversions with the police to reduce disruption while simultaneously commencing work on the remaining three spans after the main railway span is launched. The municipal commissioner directed officials to maintain pace and to ensure that final construction meets safety and durability standards before opening the overpass to traffic.

Pune Municipal Corporation (PMC) municipal commissioner Naval Kishore Ram directed civic officials to complete the Sadhu Vaswani railway overpass by December 2026 after a site inspection. He instructed the project department to expedite work while ensuring close coordination with railway authorities and the traffic police. Ram set a requirement for monthly site inspections to review progress and to ensure adherence to technical standards and safety protocols during the remaining construction. The project requires launching a 54-metre open web girder across a busy railway section that carries more than 240 trains each day, creating significant technical and operational challenges. Work under the project began in June 2024 but actual construction started nearly a year later owing to delays in obtaining clearances and resolving engineering issues. The PMC reported that approximately 75 per cent of the overall work has been completed and remaining tasks will be accelerated. Delays stemmed from the need to relocate an existing overhead water pipeline with a diameter of one metre, complete underground laying, secure permissions from the railway ministry and revise parts of the project plan. These issues have been addressed, the project department said, and a new contractor has been appointed to remove the remaining overhead truss at the span, work that is expected to finish within a week. Once the truss is removed, the launch of the girder is slated for the end of September. Commuters and local residents have reported persistent congestion on Bund Garden Road and at Wadia College Chowk, and civic officials acknowledged the project is a crucial link for the area. The PMC said it will coordinate traffic diversions with the police to reduce disruption while simultaneously commencing work on the remaining three spans after the main railway span is launched. The municipal commissioner directed officials to maintain pace and to ensure that final construction meets safety and durability standards before opening the overpass to traffic.

Related Stories

Gold Stories

Next Story
Resources

Schindler named among Forbes’ World’s Best Employers 2026

Schindler has been named among Forbes’ World’s Best Employers 2026, a global ranking recognising companies for their workplace environments.Compiled by Forbes in partnership with Statista, the ranking is based on independent employee feedback, including whether employees would recommend their organisation to friends and family.The company said the recognition reflected its focus on creating a workplace where employees can develop their expertise and build careers. ..

Next Story
Infrastructure Urban

India needs an export-execution mindset: Vishesh Jain

Interview with Vishesh Jain, Founder & CEO, EximpleWhat gaps in India’s global trade ecosystem led you to build Eximple, and what problem did you see businesses struggling with most?Eximple came out of a problem that all three founders had seen from different choke points in the trade ecosystem. India has millions of MSMEs and manufacturers, and many of them can make products that are genuinely competitive on quality. Yet only a small fraction is able to build meaningful international businesses. In our experience, the gap is usually not manufacturing capability; it is the ability to exe..

Next Story
Building Material

Nuvoco reports 13.5% revenue growth in Q2 FY27

Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code