MC Orders Completion Of Sadhu Vaswani Railway Overpass By Dec 2026
RAILWAYS & METRO RAIL

MC Orders Completion Of Sadhu Vaswani Railway Overpass By Dec 2026

Pune Municipal Corporation (PMC) municipal commissioner Naval Kishore Ram directed civic officials to complete the Sadhu Vaswani railway overpass by December 2026 after a site inspection. He instructed the project department to expedite work while ensuring close coordination with railway authorities and the traffic police. Ram set a requirement for monthly site inspections to review progress and to ensure adherence to technical standards and safety protocols during the remaining construction.

The project requires launching a 54-metre open web girder across a busy railway section that carries more than 240 trains each day, creating significant technical and operational challenges. Work under the project began in June 2024 but actual construction started nearly a year later owing to delays in obtaining clearances and resolving engineering issues. The PMC reported that approximately 75 per cent of the overall work has been completed and remaining tasks will be accelerated.

Delays stemmed from the need to relocate an existing overhead water pipeline with a diameter of one metre, complete underground laying, secure permissions from the railway ministry and revise parts of the project plan. These issues have been addressed, the project department said, and a new contractor has been appointed to remove the remaining overhead truss at the span, work that is expected to finish within a week. Once the truss is removed, the launch of the girder is slated for the end of September.

Commuters and local residents have reported persistent congestion on Bund Garden Road and at Wadia College Chowk, and civic officials acknowledged the project is a crucial link for the area. The PMC said it will coordinate traffic diversions with the police to reduce disruption while simultaneously commencing work on the remaining three spans after the main railway span is launched. The municipal commissioner directed officials to maintain pace and to ensure that final construction meets safety and durability standards before opening the overpass to traffic.

Pune Municipal Corporation (PMC) municipal commissioner Naval Kishore Ram directed civic officials to complete the Sadhu Vaswani railway overpass by December 2026 after a site inspection. He instructed the project department to expedite work while ensuring close coordination with railway authorities and the traffic police. Ram set a requirement for monthly site inspections to review progress and to ensure adherence to technical standards and safety protocols during the remaining construction. The project requires launching a 54-metre open web girder across a busy railway section that carries more than 240 trains each day, creating significant technical and operational challenges. Work under the project began in June 2024 but actual construction started nearly a year later owing to delays in obtaining clearances and resolving engineering issues. The PMC reported that approximately 75 per cent of the overall work has been completed and remaining tasks will be accelerated. Delays stemmed from the need to relocate an existing overhead water pipeline with a diameter of one metre, complete underground laying, secure permissions from the railway ministry and revise parts of the project plan. These issues have been addressed, the project department said, and a new contractor has been appointed to remove the remaining overhead truss at the span, work that is expected to finish within a week. Once the truss is removed, the launch of the girder is slated for the end of September. Commuters and local residents have reported persistent congestion on Bund Garden Road and at Wadia College Chowk, and civic officials acknowledged the project is a crucial link for the area. The PMC said it will coordinate traffic diversions with the police to reduce disruption while simultaneously commencing work on the remaining three spans after the main railway span is launched. The municipal commissioner directed officials to maintain pace and to ensure that final construction meets safety and durability standards before opening the overpass to traffic.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

Panel Urges Zone-Wise Freight Plans and Crew Strengthening

A Parliamentary Standing Committee has urged the Railway Ministry to prepare zone-wise plans to enhance freight traffic in regions with limited mineral movement and industrial activity, according to its ninth report tabled in Parliament on 10 August. The Committee commended efforts to augment network capacity through multitracking, operationalisation of Dedicated Freight Corridors (DFC) and modernisation of yards. It noted that the Ministry has said periodic data-driven assessments are carried out with inputs from Zonal Railways, Divisional Railways and Business Development Units to support po..

Next Story
Infrastructure Urban

Coal India Weighs Buying Wealth Minerals Unit For Chile Lithium

Coal India Limited is evaluating a proposal to acquire the Chilean lithium assets held by the Wealth Minerals unit in Canada as part of a strategic move into battery materials. The company is assessing the asset portfolio, regulatory landscape and integration challenges while retaining coal operations as its core business. The potential interest reflects a shift by a state-owned miner towards minerals critical to the low emission transition. Wealth Minerals, a Canada-based exploration company, holds licences and exploration agreements in Chile that involve hard rock and brine lithium prospects..

Next Story
Infrastructure Energy

Bajel Projects Wins Ultra?Mega Transmission Line Contract

Bajel Projects Limited has secured an Ultra?Mega engineering, procurement and construction order for a transmission line package TL05 from PowerGrid Corporation of India Limited on behalf of its special purpose vehicle. The award forms part of the Western Region–Eastern Region inter?regional network expansion scheme Part A procured under the tariff based competitive bidding route. The contract covers construction of a 765 kV double circuit transmission line. The scope includes bypassing of the Raigarh (Tamnar)–Dharamjaygarh (Sec?B) 765 kV double circuit line and reconfiguration to form the..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement