MC Orders Completion Of Sadhu Vaswani Railway Overpass By Dec 2026
RAILWAYS & METRO RAIL

MC Orders Completion Of Sadhu Vaswani Railway Overpass By Dec 2026

Pune Municipal Corporation (PMC) municipal commissioner Naval Kishore Ram directed civic officials to complete the Sadhu Vaswani railway overpass by December 2026 after a site inspection. He instructed the project department to expedite work while ensuring close coordination with railway authorities and the traffic police. Ram set a requirement for monthly site inspections to review progress and to ensure adherence to technical standards and safety protocols during the remaining construction.

The project requires launching a 54-metre open web girder across a busy railway section that carries more than 240 trains each day, creating significant technical and operational challenges. Work under the project began in June 2024 but actual construction started nearly a year later owing to delays in obtaining clearances and resolving engineering issues. The PMC reported that approximately 75 per cent of the overall work has been completed and remaining tasks will be accelerated.

Delays stemmed from the need to relocate an existing overhead water pipeline with a diameter of one metre, complete underground laying, secure permissions from the railway ministry and revise parts of the project plan. These issues have been addressed, the project department said, and a new contractor has been appointed to remove the remaining overhead truss at the span, work that is expected to finish within a week. Once the truss is removed, the launch of the girder is slated for the end of September.

Commuters and local residents have reported persistent congestion on Bund Garden Road and at Wadia College Chowk, and civic officials acknowledged the project is a crucial link for the area. The PMC said it will coordinate traffic diversions with the police to reduce disruption while simultaneously commencing work on the remaining three spans after the main railway span is launched. The municipal commissioner directed officials to maintain pace and to ensure that final construction meets safety and durability standards before opening the overpass to traffic.

Pune Municipal Corporation (PMC) municipal commissioner Naval Kishore Ram directed civic officials to complete the Sadhu Vaswani railway overpass by December 2026 after a site inspection. He instructed the project department to expedite work while ensuring close coordination with railway authorities and the traffic police. Ram set a requirement for monthly site inspections to review progress and to ensure adherence to technical standards and safety protocols during the remaining construction. The project requires launching a 54-metre open web girder across a busy railway section that carries more than 240 trains each day, creating significant technical and operational challenges. Work under the project began in June 2024 but actual construction started nearly a year later owing to delays in obtaining clearances and resolving engineering issues. The PMC reported that approximately 75 per cent of the overall work has been completed and remaining tasks will be accelerated. Delays stemmed from the need to relocate an existing overhead water pipeline with a diameter of one metre, complete underground laying, secure permissions from the railway ministry and revise parts of the project plan. These issues have been addressed, the project department said, and a new contractor has been appointed to remove the remaining overhead truss at the span, work that is expected to finish within a week. Once the truss is removed, the launch of the girder is slated for the end of September. Commuters and local residents have reported persistent congestion on Bund Garden Road and at Wadia College Chowk, and civic officials acknowledged the project is a crucial link for the area. The PMC said it will coordinate traffic diversions with the police to reduce disruption while simultaneously commencing work on the remaining three spans after the main railway span is launched. The municipal commissioner directed officials to maintain pace and to ensure that final construction meets safety and durability standards before opening the overpass to traffic.

Related Stories

Gold Stories

Next Story
Real Estate

Peninsula Land launches 19 luxury villas in Pune

Pune’s residential landscape is witnessing a shift as premium homebuyers increasingly seek larger spaces, privacy and independent living options beyond high-rise apartments. Addressing this demand, Peninsula Land Limited, part of the Ashok Piramal Group, has launched AshokVillas, an exclusive collection of 19 premium furnished villas in Gahunje, Pune.The development combines the independence of a standalone home with the convenience and security of a managed residential community. Designed around low-density horizontal living, AshokVillas offers residents private spaces while providing acces..

Next Story
Infrastructure Urban

MyBranch Expands South India Network with 16 Workspace Centres

MyBranch has expanded its South India presence with a 50,000 sq ft flexible workspace network comprising 16 centres across 14 cities in Andhra Pradesh, Karnataka, Tamil Nadu and Telangana.The expansion reflects growing demand for flexible office infrastructure as businesses establish regional teams, satellite offices and operations beyond traditional metropolitan markets. MyBranch’s network spans Bengaluru, Coimbatore, Guntur, Hanamkonda, Hubballi, Hyderabad, Madurai, Mangaluru, Rajahmundry, Salem, Tirupati, Vellore, Vijayawada and Visakhapatnam, with a large office space in Chennai also und..

Next Story
Building Material

Walplast Launches Moisture-Resistant Gypsum Plaster Solutions

Walplast Products Pvt. Ltd. has expanded its HomeSure GypEx portfolio with the launch of GypEx MoistShield and GypEx Gold, two gypsum plaster solutions designed to address moisture-prone applications and improve plastering efficiency.The new products have been developed in response to the growing demand for faster construction processes, improved material performance and consistent surface quality. The solutions aim to simplify interior plastering while addressing specific application requirements across construction environments.“Through HomeSure GypEx MoistShield and GypEx Gold, we are exp..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code