Metro corporation restores roads as Phase I nears completion
RAILWAYS & METRO RAIL

Metro corporation restores roads as Phase I nears completion

The Metro construction in the city has significantly improved local infrastructure. Almost all road sections temporarily used for Phase I of the Metro 3 station work have now been restored. Roads surrounding Marol, Santacruz, and BKC were the most impacted among the 10 stations in this phase. While road barricades have been removed, minor surface work in a few areas is ongoing and expected to conclude soon.

“Old facilities, including street furniture and pavements, are being reinstated,” said MMRCL Managing Director Ashwini Bhide. “Roads along the Aarey-BKC stretch have already been restored, and similar efforts are underway for the remaining route from Dharavi to Cuffe Parade.”

One of the main challenges remains at BKC, where road restoration has been slower due to ongoing civil work. Bhide noted that improvements are being made and stated, “As the civil work progresses, we are clearing the roads in this area.” The MMRCL plans to replace the steel deck currently at BKC with a concrete surface, a process expected to take two to three weeks. Despite this, traffic flow in the area has seen improvements.

The construction of the 33.5 km underground Metro 3 corridor, which used a combination of the cut-and-cover method and other technologies at 19 stations, impacted about 11 km of roadways, affecting a total of 97,000 square meters of road surface. This construction method involves excavating stretches of roads, which are then reinstated after work is completed. While the MMRCL aimed to minimise disruptions to the city’s road network, some areas were blocked to create shafts for launching tunnel boring machines.

Roadwork in Girgaum has reached a critical stage along the Phase II stretch, as construction began later than planned. A steel deck has been installed in the area, and road restrictions remain. In Worli, particularly along Acharya Atre Marg, road handover has been delayed due to multiple underground utilities. The MMRCL expects civil work for Phase II to be completed by December, after which road restoration will follow in a phased manner.

Reassuring residents, Bhide stated, “All trees removed during construction are being replanted at their original locations near each station. Additionally, facilities provided outside the stations will be maintained by Metro 3.”

(ET)

The Metro construction in the city has significantly improved local infrastructure. Almost all road sections temporarily used for Phase I of the Metro 3 station work have now been restored. Roads surrounding Marol, Santacruz, and BKC were the most impacted among the 10 stations in this phase. While road barricades have been removed, minor surface work in a few areas is ongoing and expected to conclude soon. “Old facilities, including street furniture and pavements, are being reinstated,” said MMRCL Managing Director Ashwini Bhide. “Roads along the Aarey-BKC stretch have already been restored, and similar efforts are underway for the remaining route from Dharavi to Cuffe Parade.” One of the main challenges remains at BKC, where road restoration has been slower due to ongoing civil work. Bhide noted that improvements are being made and stated, “As the civil work progresses, we are clearing the roads in this area.” The MMRCL plans to replace the steel deck currently at BKC with a concrete surface, a process expected to take two to three weeks. Despite this, traffic flow in the area has seen improvements. The construction of the 33.5 km underground Metro 3 corridor, which used a combination of the cut-and-cover method and other technologies at 19 stations, impacted about 11 km of roadways, affecting a total of 97,000 square meters of road surface. This construction method involves excavating stretches of roads, which are then reinstated after work is completed. While the MMRCL aimed to minimise disruptions to the city’s road network, some areas were blocked to create shafts for launching tunnel boring machines. Roadwork in Girgaum has reached a critical stage along the Phase II stretch, as construction began later than planned. A steel deck has been installed in the area, and road restrictions remain. In Worli, particularly along Acharya Atre Marg, road handover has been delayed due to multiple underground utilities. The MMRCL expects civil work for Phase II to be completed by December, after which road restoration will follow in a phased manner. Reassuring residents, Bhide stated, “All trees removed during construction are being replanted at their original locations near each station. Additionally, facilities provided outside the stations will be maintained by Metro 3.” (ET)

Next Story
Infrastructure Energy

J&K CM Rules Out Power Privatisation, Focuses on Sector Reform

Jammu and Kashmir Chief Minister Omar Abdullah has dismissed speculation regarding privatisation of electricity in the Union Territory, emphasising that his priority is to strengthen and reform the power sector.“We are not discussing privatisation. By reducing losses, improving billing efficiency, and enhancing revenue, there will be no need for it. My vision is to strengthen and reform the power sector in J&K,” Abdullah stated.He addressed the gathering at the 58th Engineers’ Day at SKICC on Monday evening, an event honouring Bharat Ratna Sir M Visvesvaraya for his pioneering contri..

Next Story
Infrastructure Urban

Mumbai’s Sassoon Dock to Get Tech-Driven Modernisation with Finland

The Maharashtra government, in collaboration with Finland, will modernise Mumbai’s historic Sassoon Dock using advanced technology, state minister Nitesh Rane announced on Wednesday.Rane met a delegation of Finnish officials and representatives of Finnish companies at the dock to discuss strategic plans for upgrading the facility in south Mumbai, according to an official statement.Built in the 19th century, Sassoon Dock is one of Mumbai’s oldest and busiest fishing harbours. Operations currently exceed its original capacity, raising concerns over hygiene, odour, fish handling standards, an..

Next Story
Infrastructure Energy

Agarwal Industrial Wins Rs 3.3 Billion IOCL Bitumen Tender

Agarwal Industrial Corporation rose 3.84 per cent to Rs 945.65 after announcing it had secured a prestigious tender from Indian Oil Corporation (IOCL) worth Rs 3.3 billion.In a regulatory filing during market hours, the company confirmed it had won the tender to supply Bulk Bitumen (VG-30 and VG-40 grades) to IOCL’s Kakinada locations.The firm quantity under the award totals around 60,500 tonnes across 11 parcels, while the optional quantity is approximately 33,000 tonnes across six parcels. This brings the total awarded quantity to roughly 93,500 tonnes. At current market prices, the firm o..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?