Metro corporation restores roads as Phase I nears completion
RAILWAYS & METRO RAIL

Metro corporation restores roads as Phase I nears completion

The Metro construction in the city has significantly improved local infrastructure. Almost all road sections temporarily used for Phase I of the Metro 3 station work have now been restored. Roads surrounding Marol, Santacruz, and BKC were the most impacted among the 10 stations in this phase. While road barricades have been removed, minor surface work in a few areas is ongoing and expected to conclude soon.

“Old facilities, including street furniture and pavements, are being reinstated,” said MMRCL Managing Director Ashwini Bhide. “Roads along the Aarey-BKC stretch have already been restored, and similar efforts are underway for the remaining route from Dharavi to Cuffe Parade.”

One of the main challenges remains at BKC, where road restoration has been slower due to ongoing civil work. Bhide noted that improvements are being made and stated, “As the civil work progresses, we are clearing the roads in this area.” The MMRCL plans to replace the steel deck currently at BKC with a concrete surface, a process expected to take two to three weeks. Despite this, traffic flow in the area has seen improvements.

The construction of the 33.5 km underground Metro 3 corridor, which used a combination of the cut-and-cover method and other technologies at 19 stations, impacted about 11 km of roadways, affecting a total of 97,000 square meters of road surface. This construction method involves excavating stretches of roads, which are then reinstated after work is completed. While the MMRCL aimed to minimise disruptions to the city’s road network, some areas were blocked to create shafts for launching tunnel boring machines.

Roadwork in Girgaum has reached a critical stage along the Phase II stretch, as construction began later than planned. A steel deck has been installed in the area, and road restrictions remain. In Worli, particularly along Acharya Atre Marg, road handover has been delayed due to multiple underground utilities. The MMRCL expects civil work for Phase II to be completed by December, after which road restoration will follow in a phased manner.

Reassuring residents, Bhide stated, “All trees removed during construction are being replanted at their original locations near each station. Additionally, facilities provided outside the stations will be maintained by Metro 3.”

(ET)

The Metro construction in the city has significantly improved local infrastructure. Almost all road sections temporarily used for Phase I of the Metro 3 station work have now been restored. Roads surrounding Marol, Santacruz, and BKC were the most impacted among the 10 stations in this phase. While road barricades have been removed, minor surface work in a few areas is ongoing and expected to conclude soon. “Old facilities, including street furniture and pavements, are being reinstated,” said MMRCL Managing Director Ashwini Bhide. “Roads along the Aarey-BKC stretch have already been restored, and similar efforts are underway for the remaining route from Dharavi to Cuffe Parade.” One of the main challenges remains at BKC, where road restoration has been slower due to ongoing civil work. Bhide noted that improvements are being made and stated, “As the civil work progresses, we are clearing the roads in this area.” The MMRCL plans to replace the steel deck currently at BKC with a concrete surface, a process expected to take two to three weeks. Despite this, traffic flow in the area has seen improvements. The construction of the 33.5 km underground Metro 3 corridor, which used a combination of the cut-and-cover method and other technologies at 19 stations, impacted about 11 km of roadways, affecting a total of 97,000 square meters of road surface. This construction method involves excavating stretches of roads, which are then reinstated after work is completed. While the MMRCL aimed to minimise disruptions to the city’s road network, some areas were blocked to create shafts for launching tunnel boring machines. Roadwork in Girgaum has reached a critical stage along the Phase II stretch, as construction began later than planned. A steel deck has been installed in the area, and road restrictions remain. In Worli, particularly along Acharya Atre Marg, road handover has been delayed due to multiple underground utilities. The MMRCL expects civil work for Phase II to be completed by December, after which road restoration will follow in a phased manner. Reassuring residents, Bhide stated, “All trees removed during construction are being replanted at their original locations near each station. Additionally, facilities provided outside the stations will be maintained by Metro 3.” (ET)

Next Story
Infrastructure Urban

Aadhaar Authentications Cross 27 Billion in FY25

Aadhaar authentication transactions surged past 27.07 billion in FY 2024–25, including 2.47 billion in March alone, reflecting its growing adoption across sectors such as banking, finance, telecom, and public service delivery. Since its inception, the cumulative number of Aadhaar authentication transactions has exceeded 148 billion.The Unique Identification Authority of India’s (UIDAI) AI/ML-based face authentication technology is also witnessing a sharp rise in usage. In March 2025 alone, over 150 million face authentication transactions were recorded. This biometric modality is now used ..

Next Story
Infrastructure Urban

IEPFA Holds Preparatory Meet for 'Niveshak Shivir' Initiative

The Investor Education and Protection Fund Authority (IEPFA), under the Ministry of Corporate Affairs, Government of India, hosted a preparatory meeting on April 28, 2025, with Nodal Officers from stakeholder companies via video conference. The session, chaired by IEPFA CEO Smt. Anita Shah Akella, focused on finalising operational plans for the upcoming ""Niveshak Shivir"" initiative—a joint effort between IEPFA and the Securities and Exchange Board of India (SEBI).""Niveshak Shivir"" aims to improve investor services and streamline the claims process by reaching out to cities with a high nu..

Next Story
Infrastructure Urban

India, France Sign Deal for 26 Rafale-Marine Jets for Navy

India and France have signed an Inter-Governmental Agreement (IGA) for the acquisition of 26 Rafale-Marine aircraft for the Indian Navy, comprising 22 single-seater and four twin-seater jets. The deal also includes training systems, simulators, associated equipment, weapons, and performance-based logistics, along with additional equipment for the Indian Air Force’s existing Rafale fleet.The IGA was signed by India’s Defence Minister Rajnath Singh and French Minister of Armed Forces Sébastien Lecornu. The agreement, along with supply protocols for aircraft and weapons, was exchanged in the..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?