Mumbai-Ahmedabad bullet train project running behind schedule
RAILWAYS & METRO RAIL

Mumbai-Ahmedabad bullet train project running behind schedule

The Mumbai-Ahmedabad high-speed rail project, which is India's first bullet train, is running behind schedule, with only 33.68% of physical progress achieved against a target of 35.97% as of May 2023.

The project was initially estimated to cost Rs 108,000 crore, but the total cost has risen to almost Rs 2 Lakh crore due to delays and fluctuations in yen value. The high-speed rail line will connect Mumbai and Ahmedabad through 12 stations at a cost of Rs 1.1 lakh crore, with a deadline of December 2023. Trains on the line will operate at a speed of 320 kmph on an elevated viaduct, except in Mumbai where it will be built underground.

The Vapi-Sabarmati section is expected to be commissioned in August 2027, although the project may face agitation from executives of Coal India, which is unrelated to the project.

The Mumbai-Ahmedabad high-speed rail project, which is India's first bullet train, is running behind schedule, with only 33.68% of physical progress achieved against a target of 35.97% as of May 2023.The project was initially estimated to cost Rs 108,000 crore, but the total cost has risen to almost Rs 2 Lakh crore due to delays and fluctuations in yen value. The high-speed rail line will connect Mumbai and Ahmedabad through 12 stations at a cost of Rs 1.1 lakh crore, with a deadline of December 2023. Trains on the line will operate at a speed of 320 kmph on an elevated viaduct, except in Mumbai where it will be built underground.The Vapi-Sabarmati section is expected to be commissioned in August 2027, although the project may face agitation from executives of Coal India, which is unrelated to the project.

Related Stories

Gold Stories

Next Story
Resources

Schindler named among Forbes’ World’s Best Employers 2026

Schindler has been named among Forbes’ World’s Best Employers 2026, a global ranking recognising companies for their workplace environments.Compiled by Forbes in partnership with Statista, the ranking is based on independent employee feedback, including whether employees would recommend their organisation to friends and family.The company said the recognition reflected its focus on creating a workplace where employees can develop their expertise and build careers. ..

Next Story
Infrastructure Urban

India needs an export-execution mindset: Vishesh Jain

Interview with Vishesh Jain, Founder & CEO, EximpleWhat gaps in India’s global trade ecosystem led you to build Eximple, and what problem did you see businesses struggling with most?Eximple came out of a problem that all three founders had seen from different choke points in the trade ecosystem. India has millions of MSMEs and manufacturers, and many of them can make products that are genuinely competitive on quality. Yet only a small fraction is able to build meaningful international businesses. In our experience, the gap is usually not manufacturing capability; it is the ability to exe..

Next Story
Building Material

Nuvoco reports 13.5% revenue growth in Q2 FY27

Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code