Mumbai-Ahmedabad bullet train project running behind schedule
RAILWAYS & METRO RAIL

Mumbai-Ahmedabad bullet train project running behind schedule

The Mumbai-Ahmedabad high-speed rail project, which is India's first bullet train, is running behind schedule, with only 33.68% of physical progress achieved against a target of 35.97% as of May 2023.

The project was initially estimated to cost Rs 108,000 crore, but the total cost has risen to almost Rs 2 Lakh crore due to delays and fluctuations in yen value. The high-speed rail line will connect Mumbai and Ahmedabad through 12 stations at a cost of Rs 1.1 lakh crore, with a deadline of December 2023. Trains on the line will operate at a speed of 320 kmph on an elevated viaduct, except in Mumbai where it will be built underground.

The Vapi-Sabarmati section is expected to be commissioned in August 2027, although the project may face agitation from executives of Coal India, which is unrelated to the project.

The Mumbai-Ahmedabad high-speed rail project, which is India's first bullet train, is running behind schedule, with only 33.68% of physical progress achieved against a target of 35.97% as of May 2023.The project was initially estimated to cost Rs 108,000 crore, but the total cost has risen to almost Rs 2 Lakh crore due to delays and fluctuations in yen value. The high-speed rail line will connect Mumbai and Ahmedabad through 12 stations at a cost of Rs 1.1 lakh crore, with a deadline of December 2023. Trains on the line will operate at a speed of 320 kmph on an elevated viaduct, except in Mumbai where it will be built underground.The Vapi-Sabarmati section is expected to be commissioned in August 2027, although the project may face agitation from executives of Coal India, which is unrelated to the project.

Next Story
Products

TOTO India Launches Premium G & L Showers with Sleek Faucet Range

TOTO India has launched its G Shower and L Shower series, alongside an expanded range of GT, LH, and Pull-Out lavatory faucets. The collection blends advanced technology, refined aesthetics, and everyday comfort, staying true to TOTO’s philosophy of creating spaces that are both beautiful and functional. The G Shower series delivers the 3Rs of showering: Relaxing, Refreshing, and Revitalizing. Features include the Calming Shawl spray mode, Warm Spa technology, and multiple overhead and hand-shower options across eight finishes. The L Shower complements this with easy-to-use controls sui..

Next Story
Infrastructure Energy

Hero Future Energies Secures Funding for 120 MW Hybrid Project

Hero Future Energies (HFE), through its SPV Clean Renewable Energy Hybrid Three, has secured Rs 19.08 billion in funding from the State Bank of India (lead) and Canara Bank. The funds will be used to develop and construct HFE’s 120 MW renewable energy hybrid project at Kurnool, Andhra Pradesh. The project, contracted with SJVN, integrates wind, solar, and storage technologies to deliver reliable peak power. With a 21-year repayment period, the funding ensures timely execution and the commencement of commercial operations. The financial closure demonstrates continued lender confidence in..

Next Story
Infrastructure Energy

IOC GPS Renewables Raises Rs 8.36 billion Debt for Compressed Biogas Plants

IOC GPS Renewables Private Limited (IGRPL), a joint venture between IndianOil Corporation  and GPS Renewables, has raised Rs 8.36 billion (approx. US$ 95 million) in debt financing from Indian Bank to execute nine Compressed Biogas (CBG) projects across India.   The funding is the largest single-bank debt raise in the CBG sector and the first fully non-recourse financing in India for these projects. The plants—four in Haryana, three in Uttar Pradesh, one each in Chhattisgarh and Andhra Pradesh—will each produce 15 tonnes of CBG per day using paddy straw as feedstock. All nin..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?