Mumbai-Ahmedabad bullet train project running behind schedule
RAILWAYS & METRO RAIL

Mumbai-Ahmedabad bullet train project running behind schedule

The Mumbai-Ahmedabad high-speed rail project, which is India's first bullet train, is running behind schedule, with only 33.68% of physical progress achieved against a target of 35.97% as of May 2023.

The project was initially estimated to cost Rs 108,000 crore, but the total cost has risen to almost Rs 2 Lakh crore due to delays and fluctuations in yen value. The high-speed rail line will connect Mumbai and Ahmedabad through 12 stations at a cost of Rs 1.1 lakh crore, with a deadline of December 2023. Trains on the line will operate at a speed of 320 kmph on an elevated viaduct, except in Mumbai where it will be built underground.

The Vapi-Sabarmati section is expected to be commissioned in August 2027, although the project may face agitation from executives of Coal India, which is unrelated to the project.

The Mumbai-Ahmedabad high-speed rail project, which is India's first bullet train, is running behind schedule, with only 33.68% of physical progress achieved against a target of 35.97% as of May 2023.The project was initially estimated to cost Rs 108,000 crore, but the total cost has risen to almost Rs 2 Lakh crore due to delays and fluctuations in yen value. The high-speed rail line will connect Mumbai and Ahmedabad through 12 stations at a cost of Rs 1.1 lakh crore, with a deadline of December 2023. Trains on the line will operate at a speed of 320 kmph on an elevated viaduct, except in Mumbai where it will be built underground.The Vapi-Sabarmati section is expected to be commissioned in August 2027, although the project may face agitation from executives of Coal India, which is unrelated to the project.

Next Story
Building Material

Viva ACP Secures EPD Certification for Sustainable Cladding

Viva, Asia’s largest manufacturer of aluminium composite panels (ACP), has announced the successful release of its Environmental Product Declaration (EPD) under the International EPD® System. This milestone affirms Viva’s commitment to sustainability, transparent environmental reporting, and eco-conscious manufacturing. The certification covers Fire-Retardant (FR) Class A2, FR Class B1, and Non-FR ACPs, assessing the environmental performance of 1m² of Viva ACP (4mm thick) throughout its lifecycle—from raw material extraction to end-of-life recycling. The EPD reveals that up to 95..

Next Story
Real Estate

StarBigBloc Gets Shareholders’ Nod for IPO to Fund Expansion

StarBigBloc Building Material, a wholly owned subsidiary of BigBloc Construction Ltd (BSE: 540061), has received shareholder approval to raise funds through an Initial Public Offering (IPO). The move is aimed at unlocking shareholder value, securing growth capital, and potentially enhancing the overall valuation of BigBloc Construction. The IPO proposal was approved during the company’s Extraordinary General Meeting (EGM) held on 13th June 2025. The process remains subject to regulatory approvals, market conditions, and other applicable clearances. “This is a significant mileston..

Next Story
Resources

RentenPe and Mygate Partner to Transform Rent Payments in India

Through a strategic partnership, RentenPe and Mygate aim to streamline rent payments and promote financial inclusion by enabling rent-based credit scores for Indian renters. RentenPe, India’s first Rent Credit Score™ platform and a pioneer in rental fintech innovation, has entered a significant alliance with Mygate, the leading community management app in the country. This partnership will transform rent transactions for millions of Indian households by embedding RentenPe’s payment and rent credit scoring technology directly within the Mygate app. With this integration, all ren..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?