Mumbai-Ahmedabad bullet train project running behind schedule
RAILWAYS & METRO RAIL

Mumbai-Ahmedabad bullet train project running behind schedule

The Mumbai-Ahmedabad high-speed rail project, which is India's first bullet train, is running behind schedule, with only 33.68% of physical progress achieved against a target of 35.97% as of May 2023.

The project was initially estimated to cost Rs 108,000 crore, but the total cost has risen to almost Rs 2 Lakh crore due to delays and fluctuations in yen value. The high-speed rail line will connect Mumbai and Ahmedabad through 12 stations at a cost of Rs 1.1 lakh crore, with a deadline of December 2023. Trains on the line will operate at a speed of 320 kmph on an elevated viaduct, except in Mumbai where it will be built underground.

The Vapi-Sabarmati section is expected to be commissioned in August 2027, although the project may face agitation from executives of Coal India, which is unrelated to the project.

The Mumbai-Ahmedabad high-speed rail project, which is India's first bullet train, is running behind schedule, with only 33.68% of physical progress achieved against a target of 35.97% as of May 2023.The project was initially estimated to cost Rs 108,000 crore, but the total cost has risen to almost Rs 2 Lakh crore due to delays and fluctuations in yen value. The high-speed rail line will connect Mumbai and Ahmedabad through 12 stations at a cost of Rs 1.1 lakh crore, with a deadline of December 2023. Trains on the line will operate at a speed of 320 kmph on an elevated viaduct, except in Mumbai where it will be built underground.The Vapi-Sabarmati section is expected to be commissioned in August 2027, although the project may face agitation from executives of Coal India, which is unrelated to the project.

Next Story
Infrastructure Urban

InsideFPV Delivers ₹10 Crore Kamikaze Drone Order Under MoD’s EPR Route

InsideFPV, a Surat-based drone technology manufacturer, has successfully executed a ₹10 crore defence contract to supply indigenous kamikaze drones under the Ministry of Defence’s Emergency Procurement Route (EPR). The company completed the delivery of hundreds of FPV kamikaze drone platforms within a rapid two-month timeframe, highlighting its ability to meet urgent military procurement timelines.The supply orders were fulfilled under the emergency procurement mechanism, which is aimed at fast-tracking acquisitions for immediate operational needs. InsideFPV’s quick execution reflects it..

Next Story
Infrastructure Energy

Vedanta Resources Secures Fitch Upgrade to ‘BB-’, Best Rating Since 2015

Vedanta Resources Limited (VRL), a global player in metals, oil & gas, critical minerals, power and technology, has received a credit rating upgrade from Fitch Ratings, marking its strongest bond rating in over a decade.Fitch has raised Vedanta Resources’ Long-Term Foreign-Currency Issuer Default Rating (IDR) to ‘BB-’ from ‘B+’, while maintaining a Stable Outlook. The agency also upgraded VRL’s senior unsecured rating, along with the ratings of US dollar-denominated bonds issued by Vedanta Resources Finance II Plc and guaranteed by VRL, to ‘BB-’.The upgrade represents Vedan..

Next Story
Real Estate

NAREDCO NextGen NCR Chapter Launched

The NAREDCO NextGen NCR Chapter was recently launched at Excelerate 2026 in Mumbai, marking a key step towards integrating emerging real estate leaders from the National Capital Region with the national platform. The initiative aims to promote sustainable and responsible urban development through collaboration and knowledge exchange.The event brought together young developers, entrepreneurs, and professionals from across NCR, including Noida, Gurugram, Ghaziabad, Faridabad, Bhiwadi, and Meerut. Discussions focused on urban development, finance, sustainability, innovation, and policy, emphasisi..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement