Puducherry station's Rs 930 mn redevelopment gains momentum
RAILWAYS & METRO RAIL

Puducherry station's Rs 930 mn redevelopment gains momentum

The ambitious Rs 930 million redevelopment of Puducherry Station is gaining significant momentum, poised to elevate the travel experience for tourists and passengers alike. Initiated in September 2022, the renovation project is making steady progress. A significant milestone was marked on August 6, 2023, as Prime Minister Narendra Modi laid the foundation stone for the station's transformation under the Amrit Bharat Station Scheme.

The project has already achieved several crucial milestones, including completing the new operation building column up to the lintel level, TTE Rest Room Pile Cap and grade Beam Shuttering, grade beam PCC work, Driver Rest Room pile cap, and parcel office column up to the lintel level.

The redevelopment efforts have included the validation of the master plan, comprehensive surveys, project management services initiation, and grant of the right of way for various structures, such as the New Operation Building, Parcel Office, TTE Rest Room, Driver Rest Room, Officer Rest House, Substation, and UG Sump. The project management site office is operational, and the site premises have been effectively barricaded.

The extensive project is entrusted to M/s Engineering Projects (India), Chennai, through an Engineering, Procurement, and Construction (EPC) contract. The timeline for project completion is set at 24 months. The responsibility of Project Management services (PMS) is assigned to M/s TUV India, Chennai.

Anticipating improved passenger convenience, the redevelopment plan envisions two terminals—one on the Beach Side and the other on the Villupuram Side. These terminals will house world-class amenities, including waiting lounges, ticketing areas, commercial zones, and roof plazas. The proposed structures will feature FOBs, air concourses, lifts, and escalators, ensuring seamless passenger movement.

Beyond enhancing passenger comfort, the project aims to alleviate traffic issues and integrate the city through feeder buses and e-bus parking facilities. The new design will seamlessly blend with Puducherry's aesthetic, offering travellers a welcoming and contemporary environment that contributes to a positive perception of the city.

The ambitious Rs 930 million redevelopment of Puducherry Station is gaining significant momentum, poised to elevate the travel experience for tourists and passengers alike. Initiated in September 2022, the renovation project is making steady progress. A significant milestone was marked on August 6, 2023, as Prime Minister Narendra Modi laid the foundation stone for the station's transformation under the Amrit Bharat Station Scheme.The project has already achieved several crucial milestones, including completing the new operation building column up to the lintel level, TTE Rest Room Pile Cap and grade Beam Shuttering, grade beam PCC work, Driver Rest Room pile cap, and parcel office column up to the lintel level.The redevelopment efforts have included the validation of the master plan, comprehensive surveys, project management services initiation, and grant of the right of way for various structures, such as the New Operation Building, Parcel Office, TTE Rest Room, Driver Rest Room, Officer Rest House, Substation, and UG Sump. The project management site office is operational, and the site premises have been effectively barricaded.The extensive project is entrusted to M/s Engineering Projects (India), Chennai, through an Engineering, Procurement, and Construction (EPC) contract. The timeline for project completion is set at 24 months. The responsibility of Project Management services (PMS) is assigned to M/s TUV India, Chennai.Anticipating improved passenger convenience, the redevelopment plan envisions two terminals—one on the Beach Side and the other on the Villupuram Side. These terminals will house world-class amenities, including waiting lounges, ticketing areas, commercial zones, and roof plazas. The proposed structures will feature FOBs, air concourses, lifts, and escalators, ensuring seamless passenger movement.Beyond enhancing passenger comfort, the project aims to alleviate traffic issues and integrate the city through feeder buses and e-bus parking facilities. The new design will seamlessly blend with Puducherry's aesthetic, offering travellers a welcoming and contemporary environment that contributes to a positive perception of the city.

Next Story
Infrastructure Urban

ClickPost Launches Atlas to Benchmark E-commerce Logistics

ClickPost, a leading logistics intelligence platform, has launched Atlas, a subscription-based benchmarking tool designed to transform how e-commerce brands strategise logistics. Powered by ClickPost’s proprietary network, which processes over 50 million shipments each month, Atlas enables brands to benchmark key operational metrics in real time against industry peers and standards.Unlike traditional dashboards, Atlas delivers comparative insights—from fulfilment speeds, RTO rates and average order values to city-level delivery times and sales data—allowing brands to identify operational..

Next Story
Real Estate

Kalyani Launches Two New LivingTree Towers in Bengaluru

Bengaluru-based Kalyani Developers has announced the launch of Towers 3 and 4 at its flagship residential project, Kalyani LivingTree, located in KIADB Aerospace Park. The expansion adds 525 premium 3BHK apartments, ranging from 1300 to 1600 sq ft, and over 7.5 lakh sq ft of built-up area. Prices start from Rs 1.2 crore.These towers, the most exclusive in Phase 1, offer uninterrupted pool and landscape views, and access to over 60 lifestyle amenities, two clubhouses totalling 1 lakh sq ft, and more than 80 per cent open space.LivingTree spans 25 acres and will comprise ten towers of 23–24 fl..

Next Story
Infrastructure Urban

Blue Water Logistics IPO opens May 27

Hyderabad-based Blue Water Logistics is launching its Rs 40.5 crore IPO on May 27, 2025, which will remain open for subscription until May 29. The price band has been set at Rs 132 to Rs 135 per share, with a lot size of 1,000 shares. This is a book-built issue entirely comprising a fresh issue of 30 lakh equity shares. The IPO will be listed on the NSE Emerge platform.Smart Horizon Capital Advisors is the sole book-running lead manager, while Maashitla Securities will act as the registrar. The anchor book will open on May 26, 2025. The IPO allocates 8,35,000 shares to anchor investors, 1,56,0..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?