Telangana: Rail work to YTPS done, coal transportation to start soon
RAILWAYS & METRO RAIL

Telangana: Rail work to YTPS done, coal transportation to start soon

The railway officials conducted a trial run on the new railway line constructed from Vishnupuram to Yadadri Thermal Power Plant (YTPS) in Damaracherla mandal of Nalgonda district.

The work of the 8 km railway line was completed recently, paving the way for coal transportation to the power plant.

According to officials, this particular line had been connected to Secunderabad-Guntur and Motumarri-Jaggayyapet routes for smooth transportation of coal to the plant.

Construction of an overpass and two sub-lines was underway near Damaracherla, the officials said, adding that about 50,000 metric tonnes of coal was needed on a regular basis and ten rakes would be moving in and out on this line.

According to sources, the signaling system at Vishnupuram railway station was supposed to be completed by October 1, but due to repair work on Balharshah-Kazipet-Vijayawada railway line, some trains were diverted to the Bibinagar-Nadikudi route, which caused a delay in changing the signaling system at Vishnupuram.

Since the railway line works have been completed, the officials are expecting the commissioning of the two units of the plant shortly.

As part of testing the readiness for full production of power, two boiler units were ‘fired’ in May. It would take about five to six months before all the testing was completed to ensure every section of the two 800 MW units were working in synchrony, officials said, adding that once that was done, Unit I and Unit II would be ready for the commercial production of thermal power.

The Genco has set a deadline for Bharat Heavy Electricals Limited (BHEL), which is executing the project, to commission two units of Stage I by October and the three units of Stage II by March 2025. Due to delays in the construction of the railway line, the commissioning of the two units is likely to take place in November.

Although all five units should have been commissioned by October last year, there has been a time overrun for all five units. As the construction of the plant has already been delayed for more than three years, Genco is concerned that further delays will result in additional financial losses.

The project, when completed, is expected to cost around Rs 345.42 billion. (By Telangana Today)

The railway officials conducted a trial run on the new railway line constructed from Vishnupuram to Yadadri Thermal Power Plant (YTPS) in Damaracherla mandal of Nalgonda district. The work of the 8 km railway line was completed recently, paving the way for coal transportation to the power plant. According to officials, this particular line had been connected to Secunderabad-Guntur and Motumarri-Jaggayyapet routes for smooth transportation of coal to the plant. Construction of an overpass and two sub-lines was underway near Damaracherla, the officials said, adding that about 50,000 metric tonnes of coal was needed on a regular basis and ten rakes would be moving in and out on this line. According to sources, the signaling system at Vishnupuram railway station was supposed to be completed by October 1, but due to repair work on Balharshah-Kazipet-Vijayawada railway line, some trains were diverted to the Bibinagar-Nadikudi route, which caused a delay in changing the signaling system at Vishnupuram. Since the railway line works have been completed, the officials are expecting the commissioning of the two units of the plant shortly. As part of testing the readiness for full production of power, two boiler units were ‘fired’ in May. It would take about five to six months before all the testing was completed to ensure every section of the two 800 MW units were working in synchrony, officials said, adding that once that was done, Unit I and Unit II would be ready for the commercial production of thermal power. The Genco has set a deadline for Bharat Heavy Electricals Limited (BHEL), which is executing the project, to commission two units of Stage I by October and the three units of Stage II by March 2025. Due to delays in the construction of the railway line, the commissioning of the two units is likely to take place in November. Although all five units should have been commissioned by October last year, there has been a time overrun for all five units. As the construction of the plant has already been delayed for more than three years, Genco is concerned that further delays will result in additional financial losses. The project, when completed, is expected to cost around Rs 345.42 billion. (By Telangana Today)

Next Story
Infrastructure Transport

CPCL crosses $10 million revenue milestone

Chaitanya Projects Consultancy (CPCL), a leading infrastructure and engineering consultancy, has surpassed $10 million in annual revenue for FY 2024–25, marking a five-year compound annual growth rate of 28.2 per cent—well above the industry average. Established in 2004, CPCL has delivered over 300 projects across highways, bridges, urban infrastructure, water, transport, and environmental sectors. Its achievements include over 600 km of six-lane highways, 2,000 km of national highways, and 100 major bridges. “Our goal has always been to improve India’s infrastructure,” sai..

Next Story
Resources

KPIL secures new orders worth Rs 37.89 billion

Kalpataru Projects International Ltd (KPIL), a major EPC player in power transmission and civil infrastructure, has secured new orders worth approximately Rs 37.89 billion along with its international subsidiaries. The orders include a significant contract in the Buildings and Factories (B&F) segment in India, marking KPIL’s largest B&F order to date. The project involves the development of over 12 million sq ft of residential space with supporting infrastructure, awarded on a design-build basis. Additionally, the company has won new transmission and distribution (T&D) order..

Next Story
Real Estate

Apartment loading rises to 40 per cent in top cities

Driven by rising demand for premium amenities, the average apartment loading across India’s top seven cities has reached 40 per cent in Q1 2025, up from 31 per cent in 2019, according to ANAROCK Research. The loading factor, or the area paid for beyond the usable carpet area, covers common spaces such as lobbies, staircases, and clubhouses. Mumbai Metropolitan Region (MMR) continues to lead with the highest loading at 43 per cent. Bengaluru saw the sharpest jump, from 30 per cent in 2019 to 41 per cent in Q1 2025. Chennai recorded the lowest average loading at 36 per cent. “Sixty..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?