Telangana: Rail work to YTPS done, coal transportation to start soon
RAILWAYS & METRO RAIL

Telangana: Rail work to YTPS done, coal transportation to start soon

The railway officials conducted a trial run on the new railway line constructed from Vishnupuram to Yadadri Thermal Power Plant (YTPS) in Damaracherla mandal of Nalgonda district.

The work of the 8 km railway line was completed recently, paving the way for coal transportation to the power plant.

According to officials, this particular line had been connected to Secunderabad-Guntur and Motumarri-Jaggayyapet routes for smooth transportation of coal to the plant.

Construction of an overpass and two sub-lines was underway near Damaracherla, the officials said, adding that about 50,000 metric tonnes of coal was needed on a regular basis and ten rakes would be moving in and out on this line.

According to sources, the signaling system at Vishnupuram railway station was supposed to be completed by October 1, but due to repair work on Balharshah-Kazipet-Vijayawada railway line, some trains were diverted to the Bibinagar-Nadikudi route, which caused a delay in changing the signaling system at Vishnupuram.

Since the railway line works have been completed, the officials are expecting the commissioning of the two units of the plant shortly.

As part of testing the readiness for full production of power, two boiler units were ‘fired’ in May. It would take about five to six months before all the testing was completed to ensure every section of the two 800 MW units were working in synchrony, officials said, adding that once that was done, Unit I and Unit II would be ready for the commercial production of thermal power.

The Genco has set a deadline for Bharat Heavy Electricals Limited (BHEL), which is executing the project, to commission two units of Stage I by October and the three units of Stage II by March 2025. Due to delays in the construction of the railway line, the commissioning of the two units is likely to take place in November.

Although all five units should have been commissioned by October last year, there has been a time overrun for all five units. As the construction of the plant has already been delayed for more than three years, Genco is concerned that further delays will result in additional financial losses.

The project, when completed, is expected to cost around Rs 345.42 billion. (By Telangana Today)

The railway officials conducted a trial run on the new railway line constructed from Vishnupuram to Yadadri Thermal Power Plant (YTPS) in Damaracherla mandal of Nalgonda district. The work of the 8 km railway line was completed recently, paving the way for coal transportation to the power plant. According to officials, this particular line had been connected to Secunderabad-Guntur and Motumarri-Jaggayyapet routes for smooth transportation of coal to the plant. Construction of an overpass and two sub-lines was underway near Damaracherla, the officials said, adding that about 50,000 metric tonnes of coal was needed on a regular basis and ten rakes would be moving in and out on this line. According to sources, the signaling system at Vishnupuram railway station was supposed to be completed by October 1, but due to repair work on Balharshah-Kazipet-Vijayawada railway line, some trains were diverted to the Bibinagar-Nadikudi route, which caused a delay in changing the signaling system at Vishnupuram. Since the railway line works have been completed, the officials are expecting the commissioning of the two units of the plant shortly. As part of testing the readiness for full production of power, two boiler units were ‘fired’ in May. It would take about five to six months before all the testing was completed to ensure every section of the two 800 MW units were working in synchrony, officials said, adding that once that was done, Unit I and Unit II would be ready for the commercial production of thermal power. The Genco has set a deadline for Bharat Heavy Electricals Limited (BHEL), which is executing the project, to commission two units of Stage I by October and the three units of Stage II by March 2025. Due to delays in the construction of the railway line, the commissioning of the two units is likely to take place in November. Although all five units should have been commissioned by October last year, there has been a time overrun for all five units. As the construction of the plant has already been delayed for more than three years, Genco is concerned that further delays will result in additional financial losses. The project, when completed, is expected to cost around Rs 345.42 billion. (By Telangana Today)

Next Story
Infrastructure Transport

MMRDA advances 250 m on Orange Gate–Marine Drive tunnel

The Mumbai Metropolitan Region Development Authority (MMRDA) has completed 250 m of underground tunnelling for the Orange Gate–Marine Drive Urban Road Tunnel using India’s largest slurry shield tunnel boring machine (TBM) deployed for an urban road project.The project involves twin tunnels extending over 7 km beneath critical transport corridors, including Central Railway, Western Railway and Metro Line 3. The work requires high-precision engineering to navigate densely developed urban infrastructure.Once completed, the tunnel is expected to reduce travel time between Orange Gate and Marin..

Next Story
Infrastructure Urban

Hindustan Zinc Pays Rs 188.46 Billion in FY26

Hindustan Zinc contributed Rs 188.46 billion to the public exchequer in FY 2025-26, according to its 9th Tax Transparency Report. The contribution, equivalent to 46 per cent of the company’s revenue, included direct and indirect taxes, government royalties, dividends to the Government of India, withholding taxes and other statutory levies.The company’s five-year cumulative contribution to the exchequer stood at Rs 915.72 billion. In FY26, Hindustan Zinc reported revenue of Rs 408.44 billion, EBITDA of Rs 221.62 billion and profit after tax of Rs 138.32 billion. It also achieved its highest..

Next Story
Infrastructure Urban

World of Concrete India 2026 Opens in Mumbai

Informa Markets in India will host the 12th edition of World of Concrete India 2026 from 3–5 June 2026 at the Bombay Exhibition Centre, Mumbai. The specialised B2B exhibition will bring together manufacturers, suppliers, contractors, developers, architects, consultants, infrastructure companies, project leaders and government stakeholders.The event is expected to feature over 350 brands and more than 18,000 trade professionals. It will cover concrete and cement, dry mortar, precast technologies, formwork, construction chemicals, industrial and commercial flooring, scaffolding, safety solutio..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

-->