Chennai Completes 95 Per Cent of Storm Water Drain Works
WATER & WASTE

Chennai Completes 95 Per Cent of Storm Water Drain Works

The Greater Chennai Corporation (GCC) has completed nearly 1,314 km of the 1,385-km storm water drain (SWD) network taken up since 2022, putting overall progress at about 95 per cent. The civic body aims to finish the remaining works by the end of September, before the northeast monsoon, with projects across various schemes costing Rs. 6.07 bn.

The Asian Development Bank-funded Kosasthalaiyar Basin network is nearly complete, with 651.10 km of the planned 652.40 km finished at a cost of Rs. 30.59 bn. The KfW-funded Kovalam Basin project has completed 272.80 km of 310 km, leaving 37.20 km. Under the Capital Fund, 120.10 km of 131.70 km has been completed at Rs. 4.71 bn.

The Arcot Road project remains a major bottleneck. Only 7.20 km of its planned 18 km has been completed under the Rs. 1.03 bn project, which has been divided into 18 packages. Construction is restricted to between midnight and 4am because of traffic congestion. The drainage system will divert water towards the Virugambakkam canal and Cooum, and through Porur towards the Adyar, while 100-HP pumps are planned as a contingency around Porur and near six Metro Rail stations.

The GCC has identified 105 locations with missing drainage links. Connections have been provided at 37 locations, while work remains at 68. The Water Resources Department is desilting four river mouths and has sanctioned 200 desilting works in Chennai’s waterbodies at Rs. 420 mn, with about 48 per cent nearing completion.

For the monsoon, the corporation has identified 219 vulnerable zones, inspected 215 relief centres and arranged 111 kitchens supported by Amma Canteens and 44 central kitchens. More than 1,320 motors, including 150-200 HP pumps, are ready. The GCC has 38 boats and has arranged another 258 through the Fisheries Department and local fishermen. Forecasting agencies have indicated normal to above-normal rainfall, while councillors have raised concerns about slower preparedness and incomplete desilting in some wards.

The Greater Chennai Corporation (GCC) has completed nearly 1,314 km of the 1,385-km storm water drain (SWD) network taken up since 2022, putting overall progress at about 95 per cent. The civic body aims to finish the remaining works by the end of September, before the northeast monsoon, with projects across various schemes costing Rs. 6.07 bn. The Asian Development Bank-funded Kosasthalaiyar Basin network is nearly complete, with 651.10 km of the planned 652.40 km finished at a cost of Rs. 30.59 bn. The KfW-funded Kovalam Basin project has completed 272.80 km of 310 km, leaving 37.20 km. Under the Capital Fund, 120.10 km of 131.70 km has been completed at Rs. 4.71 bn. The Arcot Road project remains a major bottleneck. Only 7.20 km of its planned 18 km has been completed under the Rs. 1.03 bn project, which has been divided into 18 packages. Construction is restricted to between midnight and 4am because of traffic congestion. The drainage system will divert water towards the Virugambakkam canal and Cooum, and through Porur towards the Adyar, while 100-HP pumps are planned as a contingency around Porur and near six Metro Rail stations. The GCC has identified 105 locations with missing drainage links. Connections have been provided at 37 locations, while work remains at 68. The Water Resources Department is desilting four river mouths and has sanctioned 200 desilting works in Chennai’s waterbodies at Rs. 420 mn, with about 48 per cent nearing completion. For the monsoon, the corporation has identified 219 vulnerable zones, inspected 215 relief centres and arranged 111 kitchens supported by Amma Canteens and 44 central kitchens. More than 1,320 motors, including 150-200 HP pumps, are ready. The GCC has 38 boats and has arranged another 258 through the Fisheries Department and local fishermen. Forecasting agencies have indicated normal to above-normal rainfall, while councillors have raised concerns about slower preparedness and incomplete desilting in some wards.

Related Stories

Gold Stories

Next Story
Real Estate

Ajyal Holding Acquires 25% Stake in Sterling Ark

Sterling Ark, an independent integrated real estate advisory and project delivery firm, has announced a strategic alliance with Abu Dhabi-headquartered Ajyal Holding. Under the agreement, Ajyal Holding has acquired a 25 per cent stake in Sterling Ark.The alliance is expected to provide Sterling Ark with a broader platform to pursue opportunities and expand its presence across the region. Ajyal Holding operates across real estate, contracting, fit-out, building materials and technology, among other sectors.Sterling Ark provides end-to-end advisory and project delivery capabilities across real e..

Next Story
Infrastructure Urban

YEIDA Allots Land for Five Projects Worth Rs 4.69 bn

A significant step towards converting industrial investment proposals into on-ground projects was taken at the inauguration of the Uttar Pradesh International Trade Show (UPITS) 2026. Union Home and Cooperation Minister Amit Shah presented Letters of Allotment to representatives of five companies investing in the Yamuna Expressway Industrial Development Authority (YEIDA) region.The five projects have been allotted a total of 71,190 sq m of land and involve a proposed investment of Rs 4.69 bn, with the potential to generate 4,625 employment opportunities.C&R Textiles Private Limited has bee..

Next Story
Infrastructure Energy

Hindustan Zinc Restores 1,105 Hectares of Land

Hindustan Zinc Limited has restored 1,105 hectares of land as part of its efforts to integrate ecological restoration with responsible mining. The rehabilitated area, equivalent to more than 1,500 football fields, covers mining and operational landscapes restored through reclamation, plantation, biodiversity enhancement and sustainable land-use practices.The initiatives form part of Hindustan Zinc’s Sustainability Goals 2030 and its broader focus on creating long-term ecological value alongside business growth.Amarendu Prakash, CEO, Hindustan Zinc, said: “The future of mining will increasi..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code