HCC completes first tunnel for Mumbai Metro-III project
RAILWAYS & METRO RAIL

HCC completes first tunnel for Mumbai Metro-III project

Hindustan Construction Company (HCC) emerged as the sole contractor among all packages to finish the entire length of a tunnel after it completed the south bound tunnel between CST and Mumbai Central stations. 

As communicated by the company, the construction team built the 3.82-km tunnel in tough geological and urban conditions. These included the proximity of the project to the sea; the fact that the land to be tunnelled through was heterogeneous reclaimed area; congested working areas; and the need to leave buildings (most over 100 years old) undisturbed while tunnelling directly below them. 

MMRCL had awarded the contract to HCC in July 2016, for the design and construction of twin tunnels by tunnel-boring machine (TBM) method and the construction of four underground metro stations, including one at CST.

Two TBMs were procured from China with 117-m-long, single-shield, dual-mode hard rock with a 6.68 m diameter and weighing around 848 mt. They are equipped to operate in both open and closed mode, in the predominantly fresh and slightly to moderately weathered basalt and breccia anticipated in the Mumbai Metro project. After months of geotechnical investigations, planning and a lengthy procurement phase, the HCC team launched Vaitarna I (the first TBM) from the project site at CST on December 04, 2017. This TBM requires around 32 people to operate, which includes operators, engineers and labourers.

As the alignment of the tunnel passes through one of Mumbai’s most thickly populated residential areas, a thorough geological survey was conducted along the entire stretch of the project. Prior to tunnelling, a structural survey was carried out across a 30-m influence zone on either side of the alignment to assess the impact of tunnelling on the buildings. 

The construction of station buildings is currently underway. While all the station buildings are unique in design, the CST station is a completely cut-and-cover station; the remaining three stations will be made by NATM method. Vaitarna II was launched in February 2018 and is expected to complete its tunnelling by December 2019.

Hindustan Construction Company (HCC) emerged as the sole contractor among all packages to finish the entire length of a tunnel after it completed the south bound tunnel between CST and Mumbai Central stations. As communicated by the company, the construction team built the 3.82-km tunnel in tough geological and urban conditions. These included the proximity of the project to the sea; the fact that the land to be tunnelled through was heterogeneous reclaimed area; congested working areas; and the need to leave buildings (most over 100 years old) undisturbed while tunnelling directly below them. MMRCL had awarded the contract to HCC in July 2016, for the design and construction of twin tunnels by tunnel-boring machine (TBM) method and the construction of four underground metro stations, including one at CST.Two TBMs were procured from China with 117-m-long, single-shield, dual-mode hard rock with a 6.68 m diameter and weighing around 848 mt. They are equipped to operate in both open and closed mode, in the predominantly fresh and slightly to moderately weathered basalt and breccia anticipated in the Mumbai Metro project. After months of geotechnical investigations, planning and a lengthy procurement phase, the HCC team launched Vaitarna I (the first TBM) from the project site at CST on December 04, 2017. This TBM requires around 32 people to operate, which includes operators, engineers and labourers.As the alignment of the tunnel passes through one of Mumbai’s most thickly populated residential areas, a thorough geological survey was conducted along the entire stretch of the project. Prior to tunnelling, a structural survey was carried out across a 30-m influence zone on either side of the alignment to assess the impact of tunnelling on the buildings. The construction of station buildings is currently underway. While all the station buildings are unique in design, the CST station is a completely cut-and-cover station; the remaining three stations will be made by NATM method. Vaitarna II was launched in February 2018 and is expected to complete its tunnelling by December 2019.

Next Story
Real Estate

Bennet & Bernard Unveil Dutch-Inspired ‘Casa El Toledo’ in Goa

Bennet & Bernard Group, Goa’s leading luxury real estate developer, has launched its newest project, Casa El Toledo, in Assagao. The enclave features 18 ultra-luxury 4 BHK Dutch-style villas blending European charm with tropical elegance. Each villa includes a private pool, double-height ceilings, open courtyards, alfresco dining areas, and English-inspired landscaping. The interiors are curated by noted Dutch designer Kelly Marie.   Reflecting the grandeur of the Dutch Golden Age, Casa El Toledo harmonises heritage aesthetics with modern sensibilities. Expansive interiors flow..

Next Story
Equipment

Godrej Delivers Heaviest Ecolaire Surface Condenser to US Project

Godrej Enterprises Group’s Process Equipment business has manufactured and delivered its heaviest Ecolaire® Surface Condenser to date, weighing nearly 450 metric tonnes, for a power-generation project in the United States. The project, powered by natural gas and partly designed for hydrogen compatibility, marks another step in advancing clean energy systems. Produced at the company’s GreenCo-certified Dahej facility in Gujarat, the equipment demonstrates India’s growing engineering capabilities and reinforces Godrej’s ‘Make in India for the World’ vision.  Hussain S..

Next Story
Infrastructure Energy

India, Brazil Discuss Energy Ties And Oil Investments

Union Minister for Petroleum and Natural Gas Hardeep Singh Puri held discussions with Celso Luis Nunes Amorim, Special Advisor to the President of Brazil, and senior Brazilian officials to strengthen bilateral cooperation in the oil, gas, and energy transition sectors. The talks took place during a dinner hosted by Kenneth H da Nobrega, Ambassador of Brazil to India, at his residence in New Delhi.Mr Puri said the meeting focused on Indian investments in Brazil’s oil and gas sector, as well as expanding collaboration in energy transition and biofuels. “The enriching conversation revolved ar..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?