Why are infrastructure projects facing time and cost overrun?
ROADS & HIGHWAYS

Why are infrastructure projects facing time and cost overrun?

Every project is unique and has its own challenges, which result in delays and cost overruns. Some typical reasons encountered are delays in land acquisition and/or land transfer for project execution; statutory approvals such as environmental compliances, forest clearances and coastal zone clearances; and project funding constraints.
In addition to the typical reasons, as India starts implementing mega projects, Jai Prakash Shivahare, Managing Director, Dholera Industrial City Development Company (DICDL), shares some of the less talked about but still quite common reasons that result in delays: “Unrealistic expectations of project timelines, which get mandated in the contract; delays in invoice payments by owners; contractors not adequately understanding or prepared for the bid; and lack of use of internationally accepted contractual standards such as FIDIC (which is especially important in international tenders).”
For his part, the only reason for delay Sunil Srivastava, Managing Director, BARSYL, quotes is “bad planning, be it timelines, money, manpower, etc.” Bad planning starts with undercutting budgets to get the plan approved.
Meanwhile, Devendra Jain, Executive Director and CEO, Dilip Buildcon, views project delays from two perspectives: That of the company or contractors, and that of the client (government agencies). “There are external scenarios such as compensation to land owners, arbitration over ownership of land and impediments despite 80-90 per cent of the land being in place,” he points out. Jain drives the point that if contractors have the capacity and ability to commission the project on time, the government should support them by putting permissions in place. He adds, “At times, when in-house project engineers or independent agencies identify some discrepancies, government agencies take time in amending suggested changes.” 
Yogesh Jain, Managing Director, PNC Infratech, lays emphasis on, “delay in shifting of utilities and securing forest clearances for either diversion or tree cutting also contribute to considerable delays.”
And, though HAM has proved to be a successful model to date, Devendra Jain adds, “PSU banks are reluctant to fund these projects. While banks have their own NPA issues to sort out, they are unable to provide the required funding for working capital.” 
With regard to funding, Dr Ritesh Chandrashekar Tiwari, Director-Highways & Structures, Egis India, says, “Lack of clarity leads to conflict and lack of funds. And, in some way, both are intertwined. There is a lack of central planning for cities, which can look at long-term plans, say for the next 50 years, and then start allocating funds and resources.” Once this is in place, the implementing bodies could be empowered to take on day-to-day operations to complete the project.
In the view of Sandeep Upadhyay, Managing Director & CEO, Centrum Infrastructure Advisory, financial stress is something that actually has to circle back with the model of the government. “We are definitely better on the policy side but issues of land acquisition, approvals and clearances have been languishing for the past four to five years. This will result in immense financial stress for the contractors.” 
Adding to the list, Dr A Sivathanu Pillai, President, Project Management Associates India, says: “There is lack of review and corrective system. Also, project management methods and techniques are not used. Project managers are identified on the basis of their functional/engineering experience and qualification, which may not have any correlation with their competence levels of successfully managing projects.” Weighing in, Jagdish Salgaonkar, Senior Vice President-Major Programmes, Aecom, says, “We lack accurate technology to execute the projects. Because labour is not expensive, we avoid the machines that could easily expedite the schedule.” 
And, RK Pandey, Member-Projects, National Highways Authority of India (NHAI), affirms, “While there are many issues pertaining to project delays, NHAI has taken a stand whereby we will award the project only if we acquire 90 per cent right of way. That is why we have awarded fewer projects during the year. Recently, we have also modified the documents for land acquisition and contractual terms.” 
SHRIYAL SETHUMADHAVAN and RAHUL KAMAT
 

Every project is unique and has its own challenges, which result in delays and cost overruns. Some typical reasons encountered are delays in land acquisition and/or land transfer for project execution; statutory approvals such as environmental compliances, forest clearances and coastal zone clearances; and project funding constraints. In addition to the typical reasons, as India starts implementing mega projects, Jai Prakash Shivahare, Managing Director, Dholera Industrial City Development Company (DICDL), shares some of the less talked about but still quite common reasons that result in delays: “Unrealistic expectations of project timelines, which get mandated in the contract; delays in invoice payments by owners; contractors not adequately understanding or prepared for the bid; and lack of use of internationally accepted contractual standards such as FIDIC (which is especially important in international tenders).” For his part, the only reason for delay Sunil Srivastava, Managing Director, BARSYL, quotes is “bad planning, be it timelines, money, manpower, etc.” Bad planning starts with undercutting budgets to get the plan approved. Meanwhile, Devendra Jain, Executive Director and CEO, Dilip Buildcon, views project delays from two perspectives: That of the company or contractors, and that of the client (government agencies). “There are external scenarios such as compensation to land owners, arbitration over ownership of land and impediments despite 80-90 per cent of the land being in place,” he points out. Jain drives the point that if contractors have the capacity and ability to commission the project on time, the government should support them by putting permissions in place. He adds, “At times, when in-house project engineers or independent agencies identify some discrepancies, government agencies take time in amending suggested changes.”  Yogesh Jain, Managing Director, PNC Infratech, lays emphasis on, “delay in shifting of utilities and securing forest clearances for either diversion or tree cutting also contribute to considerable delays.” And, though HAM has proved to be a successful model to date, Devendra Jain adds, “PSU banks are reluctant to fund these projects. While banks have their own NPA issues to sort out, they are unable to provide the required funding for working capital.”  With regard to funding, Dr Ritesh Chandrashekar Tiwari, Director-Highways & Structures, Egis India, says, “Lack of clarity leads to conflict and lack of funds. And, in some way, both are intertwined. There is a lack of central planning for cities, which can look at long-term plans, say for the next 50 years, and then start allocating funds and resources.” Once this is in place, the implementing bodies could be empowered to take on day-to-day operations to complete the project. In the view of Sandeep Upadhyay, Managing Director & CEO, Centrum Infrastructure Advisory, financial stress is something that actually has to circle back with the model of the government. “We are definitely better on the policy side but issues of land acquisition, approvals and clearances have been languishing for the past four to five years. This will result in immense financial stress for the contractors.”  Adding to the list, Dr A Sivathanu Pillai, President, Project Management Associates India, says: “There is lack of review and corrective system. Also, project management methods and techniques are not used. Project managers are identified on the basis of their functional/engineering experience and qualification, which may not have any correlation with their competence levels of successfully managing projects.” Weighing in, Jagdish Salgaonkar, Senior Vice President-Major Programmes, Aecom, says, “We lack accurate technology to execute the projects. Because labour is not expensive, we avoid the machines that could easily expedite the schedule.”  And, RK Pandey, Member-Projects, National Highways Authority of India (NHAI), affirms, “While there are many issues pertaining to project delays, NHAI has taken a stand whereby we will award the project only if we acquire 90 per cent right of way. That is why we have awarded fewer projects during the year. Recently, we have also modified the documents for land acquisition and contractual terms.”  SHRIYAL SETHUMADHAVAN and RAHUL KAMAT  

Next Story
Infrastructure Urban

CRCL, IIT Delhi Sign MoU to Boost Science and Ease of Business

The Central Revenues Control Laboratory (CRCL), Central Board of Indirect Taxes and Customs (CBIC), Department of Revenue, Ministry of Finance, and the Indian Institute of Technology (IIT) Delhi signed a Memorandum of Understanding (MoU) toward trade facilitation and improving the ease of doing business. This MoU collaboration aims to foster R&D, innovation, and scientific excellence at CRCL, bolstering trade facilitation and regulatory efficiency.The MoU was signed by Prof. Rangan Banerjee, Director, IIT Delhi, and Shri V. Suresh, Director, CRCL, in presence of Shri Surjit Bhujabal, Speci..

Next Story
Infrastructure Urban

CAQM Sub-Committee Activates 27-Point Plan to Improve NCR Air Quality

The daily average AQI of Delhi has been hovering marginally above 200 threshold with forecast of slight improvement since last two days. Today, Delhi’s daily average Air Quality Index (AQI) clocked 213 (‘Poor’ category), as per the daily AQI Bulletin provided by the Central Pollution Control Board (CPCB), owing to variable winds. In wake of the average/ overall air quality of Delhi recording ‘Poor’ air quality category ranging between 201-300, the CAQM Sub-Committee on GRAP met today to take stock of the current air quality scenario of Delhi-NCR. While comprehensively reviewing the a..

Next Story
Infrastructure Urban

DoT Launches Financial Fraud Risk Indicator to Boost Cybersecurity

In a major step towards combating cyber fraud and financial crime, the Department of Telecommunications (DoT) has announced sharing of “Financial Fraud Risk Indicator (FRI)” with stakeholders- an output from a multi- dimensional analytical tool developed as part of the Digital Intelligence Platform (DIP) to empower financial institutions with advance actionable intelligence for cyber fraud prevention. This will enhance cyber protection and validation checks in case of mobile numbers flagged with this tool when digital payment is proposed to be made to such numbers.What is the “Financial ..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?