Metro-rail in India high on construction cost
RAILWAYS & METRO RAIL

Metro-rail in India high on construction cost

The cost of a metro project depends on the geographical location as well as many development constraints and requirements.

According to Rahul Shah, COO-Urban Infrastructure, Tata Projects, “The overall construction costs invested in materials, equipment and electrical components depend on various parameters.” In fact, all these parameters are specified within tenders, which itself differ from one another.

Based on the data available in various DPR, Mohammad Athar, Partner, PricewaterhouseCoopers, says, “The cost of an elevated metro project is in the range of Rs 2.25-300 billion per km and underground metro is about Rs 5.50-5.75 billion per km.”   

For his part, Nalin Gupta, Managing Director, J Kumar Infraprojects, says the overall cost invested in construction materials, equipment and electrical components, etc, on average, is 50-60 per cent. Commenting on the per-km construction cost involved in underground metro, he shares, “It depends upon availability of specialised machinery and equipment (owned/hired/new) and experts to operate it. As for elevated metro, it depends upon availability of machinery and equipment and experienced men and the location of the site.” He adds that average investment return depends upon the availability of funds (capital plus interest for construction purpose).

Take the case of the Nagpur Metro project. According to Sunil Mathur, Director (Rolling Stock & Systems), Maharashtra Metro Rail Corporation, about 10 per cent of the total project cost comprises electrical installation. “The per-km construction cost for the traction distribution system (TRD) of the elevated metro line comes to around Rs 100 million (per route km),” he shares. 

SHRIYAL SETHUMADHAVAN

The cost of a metro project depends on the geographical location as well as many development constraints and requirements.According to Rahul Shah, COO-Urban Infrastructure, Tata Projects, “The overall construction costs invested in materials, equipment and electrical components depend on various parameters.” In fact, all these parameters are specified within tenders, which itself differ from one another.Based on the data available in various DPR, Mohammad Athar, Partner, PricewaterhouseCoopers, says, “The cost of an elevated metro project is in the range of Rs 2.25-300 billion per km and underground metro is about Rs 5.50-5.75 billion per km.”   For his part, Nalin Gupta, Managing Director, J Kumar Infraprojects, says the overall cost invested in construction materials, equipment and electrical components, etc, on average, is 50-60 per cent. Commenting on the per-km construction cost involved in underground metro, he shares, “It depends upon availability of specialised machinery and equipment (owned/hired/new) and experts to operate it. As for elevated metro, it depends upon availability of machinery and equipment and experienced men and the location of the site.” He adds that average investment return depends upon the availability of funds (capital plus interest for construction purpose).Take the case of the Nagpur Metro project. According to Sunil Mathur, Director (Rolling Stock & Systems), Maharashtra Metro Rail Corporation, about 10 per cent of the total project cost comprises electrical installation. “The per-km construction cost for the traction distribution system (TRD) of the elevated metro line comes to around Rs 100 million (per route km),” he shares. SHRIYAL SETHUMADHAVAN

Next Story
Infrastructure Urban

PM GatiShakti Reviews Major Road, Rail and Metro Plans

The Network Planning Group (NPG) under the PM GatiShakti initiative has evaluated multiple infrastructure projects spanning road, rail, and metro systems. The review covered two highway projects by the Ministry of Road Transport and Highways (MoRTH), two railway proposals by the Ministry of Railways, and one metro project under the Ministry of Housing and Urban Affairs (MoHUA). According to the Ministry of Commerce and Industry, the projects were assessed for alignment with PM GatiShakti’s principles of integrated multimodal connectivity, last-mile linkage to economic and social hubs, and t..

Next Story
Real Estate

MahaRERA Fast-Tracks 809 Project Approvals Ahead of Diwali

As Diwali 2025 approaches, the Maharashtra Real Estate Regulatory Authority (MahaRERA) is expediting approvals for new housing projects to ensure compliance with legal, technical, and financial standards before launch. The festive season, especially Dussehra and Diwali, traditionally marks a peak period for real estate launches as developers seek to capitalise on auspicious timings and heightened buyer sentiment. This year, MahaRERA has taken a proactive approach to facilitate timely project approvals ahead of the celebrations. A total of 809 project applications were approved recently, cover..

Next Story
Infrastructure Energy

HFCL Bags Rs 2.8 Billion Export Order for Fibre Cables

Telecom equipment manufacturer HFCL has secured an export order worth USD 32.02 million (around Rs 2.8 billion) for the supply of optical fibre cables to an international client. In a regulatory filing, the company stated that the order was received through its wholly owned overseas subsidiary and is scheduled for execution by December 2026. The contract entails the supply of optical fibre cables customised to the client’s specifications, underscoring HFCL’s strong manufacturing expertise and technological capability in the global telecom infrastructure space. This order further strengt..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?