+
Gail India completes delayed Kochi-Mangaluru pipeline
OIL & GAS

Gail India completes delayed Kochi-Mangaluru pipeline

After a six-year delay, national energy giant GAIL India’s Kochi-Mangaluru natural gas pipeline project has finally reached its completion. According to Gail officials, the pipeline has finished the final 540 m long perilous patch across the Chandragiri river in northern Kerala and is at last ready for commissioning any day now.

Launched in the year 2009, at an approximate cost of almost Rs 2,915 crore, the 444 km long pipeline of natural gas was due to be commissioned in the year 2014. However, resistance on the grounds of safety and commercial feasibility both from the public and political parties kept the project in limbo.

Additionally, the land price proved to be a major hurdle in the scheme of things. Subsequently, the cost of the project almost doubled and is estimated at approximately Rs 5,750 crore now.

Gail officials said that they managed to complete the most challenging stretch that existed across the Chandragiri river in Kasargod district in northern Kerala. Testing has been initiated and is all set to be finished in an ensuing couple of days, he added. Further, he said that within this week itself the 444 km pipeline will deliver gas to Mangaluru. Depending on the availability of the minister, formal commissioning will be carried out later, he concluded.

Presently, the pipeline is charged up to Kannur and extends up to Kuttanad in Palakkad district, with Kuttanad acting as the main junction of this pipeline project. Earlier in 2013, the commission of the first phase of this project was carried out in the Kochi metropolitan area with domestic and industrial supplies from February 2016 by Adani Gas.

The commissioning of the pipeline is projected to increase the gas demand in the state from its present figure of 60 million cu m per annum to an estimated figure of about 80-90 million cu m per annum. Subsequently, the pipeline also doubles up as a major boost to Petronet’s straining Kochi LNT Terminal which currently possesses an annual capacity of 5

After a six-year delay, national energy giant GAIL India’s Kochi-Mangaluru natural gas pipeline project has finally reached its completion. According to Gail officials, the pipeline has finished the final 540 m long perilous patch across the Chandragiri river in northern Kerala and is at last ready for commissioning any day now. Launched in the year 2009, at an approximate cost of almost Rs 2,915 crore, the 444 km long pipeline of natural gas was due to be commissioned in the year 2014. However, resistance on the grounds of safety and commercial feasibility both from the public and political parties kept the project in limbo.Additionally, the land price proved to be a major hurdle in the scheme of things. Subsequently, the cost of the project almost doubled and is estimated at approximately Rs 5,750 crore now. Gail officials said that they managed to complete the most challenging stretch that existed across the Chandragiri river in Kasargod district in northern Kerala. Testing has been initiated and is all set to be finished in an ensuing couple of days, he added. Further, he said that within this week itself the 444 km pipeline will deliver gas to Mangaluru. Depending on the availability of the minister, formal commissioning will be carried out later, he concluded. Presently, the pipeline is charged up to Kannur and extends up to Kuttanad in Palakkad district, with Kuttanad acting as the main junction of this pipeline project. Earlier in 2013, the commission of the first phase of this project was carried out in the Kochi metropolitan area with domestic and industrial supplies from February 2016 by Adani Gas. The commissioning of the pipeline is projected to increase the gas demand in the state from its present figure of 60 million cu m per annum to an estimated figure of about 80-90 million cu m per annum. Subsequently, the pipeline also doubles up as a major boost to Petronet’s straining Kochi LNT Terminal which currently possesses an annual capacity of 5

Related Stories

Gold Stories

Next Story
Infrastructure Transport

97 Per Cent Of Rongjeng-Mangsang-Adokgre Road Nears Completion

Deputy Chief Minister in-charge of public works Prestone Tynsong said in Shillong on 26 August that 97 per cent physical progress had been achieved on the ongoing Rongjeng-Mangsang-Adokgre road being constructed under the Non-Lapsable Central Pool of Resources (NLCPR). He noted the project was sanctioned in 2017 and that the stipulated time for completion had been 24 months from issue of the final work order. The deputy chief minister informed the assembly that the government had decided to include the remaining work under a World Bank project. In reply to a query from Rongjeng MLA Jim M Sangm..

Next Story
Infrastructure Transport

First TBM Starts Digging Five Point Three Kilometre Tunnel Under SGNP

The Goregaon-Mulund Link Road (GMLR) Phase three (B) project has reached a key milestone as the first tunnel boring machine (TBM) began excavation of the first of two tunnels beneath the Sanjay Gandhi National Park (SGNP). The machine, named Tulsi, started cutting a five point three kilometre bore that will link Dadasaheb Phalke Chitranagari in Goregaon East with Amar Nagar in Mulund West. Officials issued a statement noting the commencement of tunnelling work under the protected green belt. The twin tunnels are being constructed using mechanised tunnelling methods that aim to limit surface di..

Next Story
Infrastructure Transport

UP Approves Two Expressways And Rs 240 bn Infrastructure Push

The Uttar Pradesh Cabinet approved a series of infrastructure and industrial investment proposals totalling Rs 240 billion (Rs 240 bn), including two major expressway projects, a manufacturing and logistics cluster in Sultanpur and incentives for 11 industrial projects across the state. The decisions, taken at a meeting chaired by Chief Minister Yogi Adityanath, underline the state government’s focus on expanding road connectivity around emerging industrial hubs while attracting manufacturing investment to districts beyond major urban centres. The approvals cover both greenfield expressway c..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code