Delays in Solar Power Projects Due to Land Acquisition Issues
POWER & RENEWABLE ENERGY

Delays in Solar Power Projects Due to Land Acquisition Issues

India’s ambitious renewable energy targets are facing significant delays in solar power project commissioning, largely due to land acquisition challenges and slow transmission capacity expansion. According to Ember’s latest report on renewable energy (RE) risks in India, utility-scale solar projects are experiencing an average delay of 17 months from their scheduled completion date, with extreme cases seeing delays of up to 34 months, and some projects even being abandoned.

The report highlights that these delays are measured from the Scheduled Commercial Operation Date (SCOD) specified in tender documents, which typically falls 18 to 24 months after the execution of power purchase agreements (PPAs).

Assessing Risk Premiums in Solar Investments The report evaluates risk premiums for solar power projects using two benchmarks:

P50 (Average Scenario): A balanced estimate, where there is a 50% probability that actual results will meet or exceed this level. P90 (Conservative Scenario): A more cautious estimate, used by risk-averse investors, where there is a 90% probability that actual results will meet or exceed this level. Investors use P50 and P90 estimates to assess risk tolerance. For example, if historical data shows a capacity utilisation factor (CUF) for a solar project between 18% and 22%, a risk-averse investor might assume 18%, while a less cautious investor might estimate 20%.

Key Factors Contributing to Project Delays 1. Land Acquisition Bottlenecks Land acquisition, expected to take 6-9 months, often extends to 18-24 months in some states, significantly affecting project timelines. Issues such as administrative hurdles, non-digitised land records, fragmented local regulations, and lack of centralised land policies make project development more complex and delay financial closure. 2. Grid Connectivity & Transmission Expansion Challenges General Network Access (GNA) or interstate transmission system (ISTS) connectivity takes between 4.5 and 13.5 months, depending on the need for network expansion. Transmission line construction can take 24-36 months, but delays are common due to: Right-of-way disputes Geographical barriers (rivers, hills, ecological zones) Environmental concerns, particularly the Great Indian Bustard (GIB) protection zones in Rajasthan, where construction timelines can extend up to 48 months. The Role of High-Voltage Direct Current (HVDC) Transmission To support renewable energy integration, significant HVDC transmission capacity has been planned and auctioned. However, HVDC systems take longer to commission than traditional High-Voltage Alternating Current (HVAC) networks, as they require specialised equipment such as converter stations and thyristor valves.

Future Outlook: Grid Expansion & Renewable Integration India has granted grid connectivity for solar, wind, and hybrid projects totaling 147 GW, but this capacity will only become fully operational over the next 3-5 years. Addressing land acquisition hurdles and transmission infrastructure constraints will be crucial in achieving India’s renewable energy targets and maintaining investor confidence in the sector.

India’s ambitious renewable energy targets are facing significant delays in solar power project commissioning, largely due to land acquisition challenges and slow transmission capacity expansion. According to Ember’s latest report on renewable energy (RE) risks in India, utility-scale solar projects are experiencing an average delay of 17 months from their scheduled completion date, with extreme cases seeing delays of up to 34 months, and some projects even being abandoned. The report highlights that these delays are measured from the Scheduled Commercial Operation Date (SCOD) specified in tender documents, which typically falls 18 to 24 months after the execution of power purchase agreements (PPAs). Assessing Risk Premiums in Solar Investments The report evaluates risk premiums for solar power projects using two benchmarks: P50 (Average Scenario): A balanced estimate, where there is a 50% probability that actual results will meet or exceed this level. P90 (Conservative Scenario): A more cautious estimate, used by risk-averse investors, where there is a 90% probability that actual results will meet or exceed this level. Investors use P50 and P90 estimates to assess risk tolerance. For example, if historical data shows a capacity utilisation factor (CUF) for a solar project between 18% and 22%, a risk-averse investor might assume 18%, while a less cautious investor might estimate 20%. Key Factors Contributing to Project Delays 1. Land Acquisition Bottlenecks Land acquisition, expected to take 6-9 months, often extends to 18-24 months in some states, significantly affecting project timelines. Issues such as administrative hurdles, non-digitised land records, fragmented local regulations, and lack of centralised land policies make project development more complex and delay financial closure. 2. Grid Connectivity & Transmission Expansion Challenges General Network Access (GNA) or interstate transmission system (ISTS) connectivity takes between 4.5 and 13.5 months, depending on the need for network expansion. Transmission line construction can take 24-36 months, but delays are common due to: Right-of-way disputes Geographical barriers (rivers, hills, ecological zones) Environmental concerns, particularly the Great Indian Bustard (GIB) protection zones in Rajasthan, where construction timelines can extend up to 48 months. The Role of High-Voltage Direct Current (HVDC) Transmission To support renewable energy integration, significant HVDC transmission capacity has been planned and auctioned. However, HVDC systems take longer to commission than traditional High-Voltage Alternating Current (HVAC) networks, as they require specialised equipment such as converter stations and thyristor valves. Future Outlook: Grid Expansion & Renewable Integration India has granted grid connectivity for solar, wind, and hybrid projects totaling 147 GW, but this capacity will only become fully operational over the next 3-5 years. Addressing land acquisition hurdles and transmission infrastructure constraints will be crucial in achieving India’s renewable energy targets and maintaining investor confidence in the sector.

Next Story
Equipment

Handling concrete better

Efficiently handling the transportation and placement of concrete is essential to help maintain the quality of construction, meet project timelines by minimising downtimes, and reduce costs – by 5 to 15 per cent, according to Sandeep Jain, Director, Arkade Developers. CW explores what the efficient handling of concrete entails.Select wellFirst, a word on choosing the right equipment, such as a mixer with a capacity aligned to the volume required onsite, from Vaibhav Kulkarni, Concrete Expert. “An overly large mixer will increase the idle time (and cost), while one that ..

Next Story
Real Estate

Elevated floors!

Raised access flooring, also called false flooring, is a less common interiors feature than false ceilings, but it has as many uses – if not more.A raised floor is a modular panel installed above the structural floor. The space beneath the raised flooring is typically used to accommodate utilities such as electrical cables, plumbing and HVAC systems. And so, raised flooring is usually associated with buildings with heavy cabling and precise air distribution needs, such as data centres.That said, CW interacted with designers and architects and discovered that false flooring can come in handy ..

Next Story
Infrastructure Urban

The Variation Challenge

A variation or change in scope clause is defined in construction contracts to take care of situations arising from change in the defined scope of work. Such changes may arise due to factors such as additions or deletions in the scope of work, modifications in the type, grade or specifications of materials, alterations in specifications or drawings, and acts or omissions of other contractors. Further, ineffective planning, inadequate investigations or surveys and requests from the employer or those within the project’s area of influence can contribute to changes in the scope of work. Ext..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?