Delays in Solar Power Projects Due to Land Acquisition Issues
POWER & RENEWABLE ENERGY

Delays in Solar Power Projects Due to Land Acquisition Issues

India’s ambitious renewable energy targets are facing significant delays in solar power project commissioning, largely due to land acquisition challenges and slow transmission capacity expansion. According to Ember’s latest report on renewable energy (RE) risks in India, utility-scale solar projects are experiencing an average delay of 17 months from their scheduled completion date, with extreme cases seeing delays of up to 34 months, and some projects even being abandoned.

The report highlights that these delays are measured from the Scheduled Commercial Operation Date (SCOD) specified in tender documents, which typically falls 18 to 24 months after the execution of power purchase agreements (PPAs).

Assessing Risk Premiums in Solar Investments The report evaluates risk premiums for solar power projects using two benchmarks:

P50 (Average Scenario): A balanced estimate, where there is a 50% probability that actual results will meet or exceed this level. P90 (Conservative Scenario): A more cautious estimate, used by risk-averse investors, where there is a 90% probability that actual results will meet or exceed this level. Investors use P50 and P90 estimates to assess risk tolerance. For example, if historical data shows a capacity utilisation factor (CUF) for a solar project between 18% and 22%, a risk-averse investor might assume 18%, while a less cautious investor might estimate 20%.

Key Factors Contributing to Project Delays 1. Land Acquisition Bottlenecks Land acquisition, expected to take 6-9 months, often extends to 18-24 months in some states, significantly affecting project timelines. Issues such as administrative hurdles, non-digitised land records, fragmented local regulations, and lack of centralised land policies make project development more complex and delay financial closure. 2. Grid Connectivity & Transmission Expansion Challenges General Network Access (GNA) or interstate transmission system (ISTS) connectivity takes between 4.5 and 13.5 months, depending on the need for network expansion. Transmission line construction can take 24-36 months, but delays are common due to: Right-of-way disputes Geographical barriers (rivers, hills, ecological zones) Environmental concerns, particularly the Great Indian Bustard (GIB) protection zones in Rajasthan, where construction timelines can extend up to 48 months. The Role of High-Voltage Direct Current (HVDC) Transmission To support renewable energy integration, significant HVDC transmission capacity has been planned and auctioned. However, HVDC systems take longer to commission than traditional High-Voltage Alternating Current (HVAC) networks, as they require specialised equipment such as converter stations and thyristor valves.

Future Outlook: Grid Expansion & Renewable Integration India has granted grid connectivity for solar, wind, and hybrid projects totaling 147 GW, but this capacity will only become fully operational over the next 3-5 years. Addressing land acquisition hurdles and transmission infrastructure constraints will be crucial in achieving India’s renewable energy targets and maintaining investor confidence in the sector.

India’s ambitious renewable energy targets are facing significant delays in solar power project commissioning, largely due to land acquisition challenges and slow transmission capacity expansion. According to Ember’s latest report on renewable energy (RE) risks in India, utility-scale solar projects are experiencing an average delay of 17 months from their scheduled completion date, with extreme cases seeing delays of up to 34 months, and some projects even being abandoned. The report highlights that these delays are measured from the Scheduled Commercial Operation Date (SCOD) specified in tender documents, which typically falls 18 to 24 months after the execution of power purchase agreements (PPAs). Assessing Risk Premiums in Solar Investments The report evaluates risk premiums for solar power projects using two benchmarks: P50 (Average Scenario): A balanced estimate, where there is a 50% probability that actual results will meet or exceed this level. P90 (Conservative Scenario): A more cautious estimate, used by risk-averse investors, where there is a 90% probability that actual results will meet or exceed this level. Investors use P50 and P90 estimates to assess risk tolerance. For example, if historical data shows a capacity utilisation factor (CUF) for a solar project between 18% and 22%, a risk-averse investor might assume 18%, while a less cautious investor might estimate 20%. Key Factors Contributing to Project Delays 1. Land Acquisition Bottlenecks Land acquisition, expected to take 6-9 months, often extends to 18-24 months in some states, significantly affecting project timelines. Issues such as administrative hurdles, non-digitised land records, fragmented local regulations, and lack of centralised land policies make project development more complex and delay financial closure. 2. Grid Connectivity & Transmission Expansion Challenges General Network Access (GNA) or interstate transmission system (ISTS) connectivity takes between 4.5 and 13.5 months, depending on the need for network expansion. Transmission line construction can take 24-36 months, but delays are common due to: Right-of-way disputes Geographical barriers (rivers, hills, ecological zones) Environmental concerns, particularly the Great Indian Bustard (GIB) protection zones in Rajasthan, where construction timelines can extend up to 48 months. The Role of High-Voltage Direct Current (HVDC) Transmission To support renewable energy integration, significant HVDC transmission capacity has been planned and auctioned. However, HVDC systems take longer to commission than traditional High-Voltage Alternating Current (HVAC) networks, as they require specialised equipment such as converter stations and thyristor valves. Future Outlook: Grid Expansion & Renewable Integration India has granted grid connectivity for solar, wind, and hybrid projects totaling 147 GW, but this capacity will only become fully operational over the next 3-5 years. Addressing land acquisition hurdles and transmission infrastructure constraints will be crucial in achieving India’s renewable energy targets and maintaining investor confidence in the sector.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

KONE Opens India's First Digital Experience Centre in Pune

KONE, a global elevator and escalator manufacturer, has inaugurated its first Digital Experience Centre (DEC) in India, located in Pune. The facility aims to showcase how artificial intelligence (AI), connectivity and data-driven technologies can enhance customer experiences and improve building operations.The centre was inaugurated by Jussi Herlin, Executive Vice Chair, KONE Corporation; Philippe Delorme, President and CEO, KONE; and Nandan Nilekani, Co-founder and Chairman of the Board, Infosys.Designed as an interactive customer environment, the facility demonstrates digital solutions cover..

Next Story
Infrastructure Urban

CII GreenCo Launches Circularity Guidelines for Indian Industry

The Confederation of Indian Industry (CII) GreenCo Council has launched the CII GreenCo Circularity Guidelines – Pilot Version at the 17th CII GreenCo Waste & Resource Management Summit 2026 in Chennai. The initiative aims to strengthen resource efficiency, waste reduction and circular economy practices across Indian manufacturing and process industries.The guidelines introduce a structured framework with circularity indices covering raw materials, consumables, packaging and other resource inputs. These indicators will help industries assess existing practices, identify opportunities to ..

Next Story
Infrastructure Energy

Global Electronics Association Launches IPC-1783-CO2E Standard

The Global Electronics Association has introduced IPC-1783-CO2E, a new international standard aimed at improving consistency, transparency and comparability in product carbon footprint reporting across the electronics manufacturing industry.The standard, titled International Standard for Data Collection and Reporting of CO2 Equivalent (CO2e) Emissions for the Electronics Manufacturing Supply Chain, provides industry-specific guidance for collecting, estimating and reporting carbon emissions data.With increasing regulatory requirements and customer expectations, electronics manufacturers face c..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code