Delays in Solar Power Projects Due to Land Acquisition Issues
POWER & RENEWABLE ENERGY

Delays in Solar Power Projects Due to Land Acquisition Issues

India’s ambitious renewable energy targets are facing significant delays in solar power project commissioning, largely due to land acquisition challenges and slow transmission capacity expansion. According to Ember’s latest report on renewable energy (RE) risks in India, utility-scale solar projects are experiencing an average delay of 17 months from their scheduled completion date, with extreme cases seeing delays of up to 34 months, and some projects even being abandoned.

The report highlights that these delays are measured from the Scheduled Commercial Operation Date (SCOD) specified in tender documents, which typically falls 18 to 24 months after the execution of power purchase agreements (PPAs).

Assessing Risk Premiums in Solar Investments The report evaluates risk premiums for solar power projects using two benchmarks:

P50 (Average Scenario): A balanced estimate, where there is a 50% probability that actual results will meet or exceed this level. P90 (Conservative Scenario): A more cautious estimate, used by risk-averse investors, where there is a 90% probability that actual results will meet or exceed this level. Investors use P50 and P90 estimates to assess risk tolerance. For example, if historical data shows a capacity utilisation factor (CUF) for a solar project between 18% and 22%, a risk-averse investor might assume 18%, while a less cautious investor might estimate 20%.

Key Factors Contributing to Project Delays 1. Land Acquisition Bottlenecks Land acquisition, expected to take 6-9 months, often extends to 18-24 months in some states, significantly affecting project timelines. Issues such as administrative hurdles, non-digitised land records, fragmented local regulations, and lack of centralised land policies make project development more complex and delay financial closure. 2. Grid Connectivity & Transmission Expansion Challenges General Network Access (GNA) or interstate transmission system (ISTS) connectivity takes between 4.5 and 13.5 months, depending on the need for network expansion. Transmission line construction can take 24-36 months, but delays are common due to: Right-of-way disputes Geographical barriers (rivers, hills, ecological zones) Environmental concerns, particularly the Great Indian Bustard (GIB) protection zones in Rajasthan, where construction timelines can extend up to 48 months. The Role of High-Voltage Direct Current (HVDC) Transmission To support renewable energy integration, significant HVDC transmission capacity has been planned and auctioned. However, HVDC systems take longer to commission than traditional High-Voltage Alternating Current (HVAC) networks, as they require specialised equipment such as converter stations and thyristor valves.

Future Outlook: Grid Expansion & Renewable Integration India has granted grid connectivity for solar, wind, and hybrid projects totaling 147 GW, but this capacity will only become fully operational over the next 3-5 years. Addressing land acquisition hurdles and transmission infrastructure constraints will be crucial in achieving India’s renewable energy targets and maintaining investor confidence in the sector.

India’s ambitious renewable energy targets are facing significant delays in solar power project commissioning, largely due to land acquisition challenges and slow transmission capacity expansion. According to Ember’s latest report on renewable energy (RE) risks in India, utility-scale solar projects are experiencing an average delay of 17 months from their scheduled completion date, with extreme cases seeing delays of up to 34 months, and some projects even being abandoned. The report highlights that these delays are measured from the Scheduled Commercial Operation Date (SCOD) specified in tender documents, which typically falls 18 to 24 months after the execution of power purchase agreements (PPAs). Assessing Risk Premiums in Solar Investments The report evaluates risk premiums for solar power projects using two benchmarks: P50 (Average Scenario): A balanced estimate, where there is a 50% probability that actual results will meet or exceed this level. P90 (Conservative Scenario): A more cautious estimate, used by risk-averse investors, where there is a 90% probability that actual results will meet or exceed this level. Investors use P50 and P90 estimates to assess risk tolerance. For example, if historical data shows a capacity utilisation factor (CUF) for a solar project between 18% and 22%, a risk-averse investor might assume 18%, while a less cautious investor might estimate 20%. Key Factors Contributing to Project Delays 1. Land Acquisition Bottlenecks Land acquisition, expected to take 6-9 months, often extends to 18-24 months in some states, significantly affecting project timelines. Issues such as administrative hurdles, non-digitised land records, fragmented local regulations, and lack of centralised land policies make project development more complex and delay financial closure. 2. Grid Connectivity & Transmission Expansion Challenges General Network Access (GNA) or interstate transmission system (ISTS) connectivity takes between 4.5 and 13.5 months, depending on the need for network expansion. Transmission line construction can take 24-36 months, but delays are common due to: Right-of-way disputes Geographical barriers (rivers, hills, ecological zones) Environmental concerns, particularly the Great Indian Bustard (GIB) protection zones in Rajasthan, where construction timelines can extend up to 48 months. The Role of High-Voltage Direct Current (HVDC) Transmission To support renewable energy integration, significant HVDC transmission capacity has been planned and auctioned. However, HVDC systems take longer to commission than traditional High-Voltage Alternating Current (HVAC) networks, as they require specialised equipment such as converter stations and thyristor valves. Future Outlook: Grid Expansion & Renewable Integration India has granted grid connectivity for solar, wind, and hybrid projects totaling 147 GW, but this capacity will only become fully operational over the next 3-5 years. Addressing land acquisition hurdles and transmission infrastructure constraints will be crucial in achieving India’s renewable energy targets and maintaining investor confidence in the sector.

Related Stories

Gold Stories

Next Story
Resources

Schindler named among Forbes’ World’s Best Employers 2026

Schindler has been named among Forbes’ World’s Best Employers 2026, a global ranking recognising companies for their workplace environments.Compiled by Forbes in partnership with Statista, the ranking is based on independent employee feedback, including whether employees would recommend their organisation to friends and family.The company said the recognition reflected its focus on creating a workplace where employees can develop their expertise and build careers. ..

Next Story
Infrastructure Urban

India needs an export-execution mindset: Vishesh Jain

Interview with Vishesh Jain, Founder & CEO, EximpleWhat gaps in India’s global trade ecosystem led you to build Eximple, and what problem did you see businesses struggling with most?Eximple came out of a problem that all three founders had seen from different choke points in the trade ecosystem. India has millions of MSMEs and manufacturers, and many of them can make products that are genuinely competitive on quality. Yet only a small fraction is able to build meaningful international businesses. In our experience, the gap is usually not manufacturing capability; it is the ability to exe..

Next Story
Building Material

Nuvoco reports 13.5% revenue growth in Q2 FY27

Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code