Delays in Solar Power Projects Due to Land Acquisition Issues
POWER & RENEWABLE ENERGY

Delays in Solar Power Projects Due to Land Acquisition Issues

India’s ambitious renewable energy targets are facing significant delays in solar power project commissioning, largely due to land acquisition challenges and slow transmission capacity expansion. According to Ember’s latest report on renewable energy (RE) risks in India, utility-scale solar projects are experiencing an average delay of 17 months from their scheduled completion date, with extreme cases seeing delays of up to 34 months, and some projects even being abandoned.

The report highlights that these delays are measured from the Scheduled Commercial Operation Date (SCOD) specified in tender documents, which typically falls 18 to 24 months after the execution of power purchase agreements (PPAs).

Assessing Risk Premiums in Solar Investments The report evaluates risk premiums for solar power projects using two benchmarks:

P50 (Average Scenario): A balanced estimate, where there is a 50% probability that actual results will meet or exceed this level. P90 (Conservative Scenario): A more cautious estimate, used by risk-averse investors, where there is a 90% probability that actual results will meet or exceed this level. Investors use P50 and P90 estimates to assess risk tolerance. For example, if historical data shows a capacity utilisation factor (CUF) for a solar project between 18% and 22%, a risk-averse investor might assume 18%, while a less cautious investor might estimate 20%.

Key Factors Contributing to Project Delays 1. Land Acquisition Bottlenecks Land acquisition, expected to take 6-9 months, often extends to 18-24 months in some states, significantly affecting project timelines. Issues such as administrative hurdles, non-digitised land records, fragmented local regulations, and lack of centralised land policies make project development more complex and delay financial closure. 2. Grid Connectivity & Transmission Expansion Challenges General Network Access (GNA) or interstate transmission system (ISTS) connectivity takes between 4.5 and 13.5 months, depending on the need for network expansion. Transmission line construction can take 24-36 months, but delays are common due to: Right-of-way disputes Geographical barriers (rivers, hills, ecological zones) Environmental concerns, particularly the Great Indian Bustard (GIB) protection zones in Rajasthan, where construction timelines can extend up to 48 months. The Role of High-Voltage Direct Current (HVDC) Transmission To support renewable energy integration, significant HVDC transmission capacity has been planned and auctioned. However, HVDC systems take longer to commission than traditional High-Voltage Alternating Current (HVAC) networks, as they require specialised equipment such as converter stations and thyristor valves.

Future Outlook: Grid Expansion & Renewable Integration India has granted grid connectivity for solar, wind, and hybrid projects totaling 147 GW, but this capacity will only become fully operational over the next 3-5 years. Addressing land acquisition hurdles and transmission infrastructure constraints will be crucial in achieving India’s renewable energy targets and maintaining investor confidence in the sector.

India’s ambitious renewable energy targets are facing significant delays in solar power project commissioning, largely due to land acquisition challenges and slow transmission capacity expansion. According to Ember’s latest report on renewable energy (RE) risks in India, utility-scale solar projects are experiencing an average delay of 17 months from their scheduled completion date, with extreme cases seeing delays of up to 34 months, and some projects even being abandoned. The report highlights that these delays are measured from the Scheduled Commercial Operation Date (SCOD) specified in tender documents, which typically falls 18 to 24 months after the execution of power purchase agreements (PPAs). Assessing Risk Premiums in Solar Investments The report evaluates risk premiums for solar power projects using two benchmarks: P50 (Average Scenario): A balanced estimate, where there is a 50% probability that actual results will meet or exceed this level. P90 (Conservative Scenario): A more cautious estimate, used by risk-averse investors, where there is a 90% probability that actual results will meet or exceed this level. Investors use P50 and P90 estimates to assess risk tolerance. For example, if historical data shows a capacity utilisation factor (CUF) for a solar project between 18% and 22%, a risk-averse investor might assume 18%, while a less cautious investor might estimate 20%. Key Factors Contributing to Project Delays 1. Land Acquisition Bottlenecks Land acquisition, expected to take 6-9 months, often extends to 18-24 months in some states, significantly affecting project timelines. Issues such as administrative hurdles, non-digitised land records, fragmented local regulations, and lack of centralised land policies make project development more complex and delay financial closure. 2. Grid Connectivity & Transmission Expansion Challenges General Network Access (GNA) or interstate transmission system (ISTS) connectivity takes between 4.5 and 13.5 months, depending on the need for network expansion. Transmission line construction can take 24-36 months, but delays are common due to: Right-of-way disputes Geographical barriers (rivers, hills, ecological zones) Environmental concerns, particularly the Great Indian Bustard (GIB) protection zones in Rajasthan, where construction timelines can extend up to 48 months. The Role of High-Voltage Direct Current (HVDC) Transmission To support renewable energy integration, significant HVDC transmission capacity has been planned and auctioned. However, HVDC systems take longer to commission than traditional High-Voltage Alternating Current (HVAC) networks, as they require specialised equipment such as converter stations and thyristor valves. Future Outlook: Grid Expansion & Renewable Integration India has granted grid connectivity for solar, wind, and hybrid projects totaling 147 GW, but this capacity will only become fully operational over the next 3-5 years. Addressing land acquisition hurdles and transmission infrastructure constraints will be crucial in achieving India’s renewable energy targets and maintaining investor confidence in the sector.

Related Stories

Gold Stories

Next Story
Products

Koemmerling opens Navi Mumbai experience centre

Koemmerling, a brand of the profine Group, has expanded its presence in the Mumbai metropolitan region with the opening of a new experience centre in Navi Mumbai and launched its Allure S46 minimal sliding door system for the Indian market.Located in CBD Belapur, the facility was inaugurated by Peter Mrosik, Owner and CEO, profine Group, along with Farid Khan, Chairman and Managing Director, profine India, and Kamal Bajaj, CEO, profine India.The company said the new centre will showcase its portfolio of uPVC and aluminium window and door systems to architects, developers and homeowners.The ina..

Next Story
Products

India's waterproofing market nears Rs 150 bn milestone

India's waterproofing industry is approaching a market size of Rs 150 billion and is expected to surpass the $2 billion milestone, according to speakers at the 2nd India International Waterproofers Conference & Expo 2026 organised by the Waterproofers Association of India (WAI) in New Delhi.The two-day event brought together more than 20 speakers, 55 international delegates and 53 exhibition booths, with discussions focusing on climate-resilient construction, advanced waterproofing technologies and international collaboration.Inaugurating the event, Durga Shanker Mishra, former Secretary, ..

Next Story
Real Estate

Dilip Buildcon Q1 FY27 Revenue at Rs 23.78 billion

Dilip Buildcon Limited reported consolidated revenue from operations of Rs 2,378 crore in Q1 FY27, along with EBITDA of Rs 429 crore and profit after tax of Rs 128 crore.Consolidated EBITDA margin stood at 18.1%, improving from 17.1% in Q4 FY26. On a standalone basis, revenue from operations was Rs 1,930 crore, EBITDA stood at Rs 199 crore and PAT was Rs 39 crore, with an EBITDA margin of 10.3%.The company’s order book stood at Rs 27,691 crore as of 30 June 2026, compared with Rs 28,830 crore as of 31 March 2026. Roads and highways accounted for 17.1% of the order book, irrigation and water ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement