+
Maharashtra Plans 11 EV Charging Stations in Transport Hubs
POWER & RENEWABLE ENERGY

Maharashtra Plans 11 EV Charging Stations in Transport Hubs

The Maharashtra State Road Transport Corporation (MSRTC) has initiated a significant move to enhance its electric vehicle (EV) charging infrastructure by releasing separate tenders for the installation of 11 EV charging stations. These charging stations are set to be strategically located around different bus and railway depots in the state, improving accessibility for EV users.

The locations for these proposed charging stations, along with their estimated project costs, are as follows:

1. Mumbai Central Depot: ?109.8 million (~$1.45 million) 2. Borivali Depot: ?89.9 million (~$1.19 million) 3. Santacruz Depot: ?65.5 million (~$872,000) 4. Kurla Depot: ?89.9 million (~$1.19 million) 5. Thane Depot: ?69.8 million (~$928,000) 6. Panvel Depot: ?75.5 million (~$1 million) 7. Pune Station Depot: ?75.5 million (~$1 million) 8. Swargate Depot: ?93.4 million (~$1.24 million) 9. Pune Divisional Office, Shivajinagar: ?79.8 million (~$1.06 million) 10. Shivajinagar Railway Depot: ?85.6 million (~$1.14 million) 11. Yerwada Bus Stand: ?94.5 million (~$1.26 million)

The deadline for bid submissions is set for October 30, 2023, and the bids will be opened on November 1. The tender process also involves a 2% security deposit requirement for each of these charging station projects. This deposit is divided into two parts:

1. 1% of the individual project cost, which converts the earnest money deposit into a security deposit. 2. Another 1% initial security deposit is required before the work order is issued, with a validity period of 120 days from the date of opening.

The timeline for the completion of these projects is expected to be three months, starting from the date of the written work order. To encourage competitive bidding and safeguard the interests of the contracting parties, the tender outlines a mechanism for performance bank guarantees (PBG) in case the bidder's offer is below the estimated cost. Here's how the PBG requirement is structured:

1. If the bidder's quoted offer is between 1% and 10% below the estimated cost, a PBG equivalent to 1% of the estimated cost is mandatory.

2. In cases where the offer is more than 10% but up to 15% below the estimated cost, an additional PBG is required. This extra security is calculated at a rate of 1% for every percent below the estimated cost. For example, if the bid is 14% below the cost (14% - 10% = 4%), an additional security of 5% would be necessary.

3. When the bid is more than 15% below the estimated cost in the tender, an additional performance security of 2% for each per cent below the cost must be furnished. For instance, if the bid is 19% below the cost (19% - 15% = 4%), an additional security of 14% of the estimated cost would be required.

Failure to submit the PBG within eight days from the date of the financial opening will lead to the rejection of the tender. In such cases, the second lowest bidder (L-2 Bidder) will be informed in writing. The L-2 bidder will have the opportunity to negotiate, and if they agree to perform the work at a rate lower than the offer of the L-1 bidder, their tender will be accepted.

These tenders emphasise the importance of certification and experience in executing similar work. To be eligible to bid for these projects, contractors must have a valid certificate as a registered contractor with the Government of Maharashtra, which is applicable for works with an estimated amount less than ?15 million (~$180,203).

The Maharashtra State Road Transport Corporation (MSRTC) has initiated a significant move to enhance its electric vehicle (EV) charging infrastructure by releasing separate tenders for the installation of 11 EV charging stations. These charging stations are set to be strategically located around different bus and railway depots in the state, improving accessibility for EV users. The locations for these proposed charging stations, along with their estimated project costs, are as follows: 1. Mumbai Central Depot: ?109.8 million (~$1.45 million) 2. Borivali Depot: ?89.9 million (~$1.19 million) 3. Santacruz Depot: ?65.5 million (~$872,000) 4. Kurla Depot: ?89.9 million (~$1.19 million) 5. Thane Depot: ?69.8 million (~$928,000) 6. Panvel Depot: ?75.5 million (~$1 million) 7. Pune Station Depot: ?75.5 million (~$1 million) 8. Swargate Depot: ?93.4 million (~$1.24 million) 9. Pune Divisional Office, Shivajinagar: ?79.8 million (~$1.06 million) 10. Shivajinagar Railway Depot: ?85.6 million (~$1.14 million) 11. Yerwada Bus Stand: ?94.5 million (~$1.26 million) The deadline for bid submissions is set for October 30, 2023, and the bids will be opened on November 1. The tender process also involves a 2% security deposit requirement for each of these charging station projects. This deposit is divided into two parts: 1. 1% of the individual project cost, which converts the earnest money deposit into a security deposit. 2. Another 1% initial security deposit is required before the work order is issued, with a validity period of 120 days from the date of opening. The timeline for the completion of these projects is expected to be three months, starting from the date of the written work order. To encourage competitive bidding and safeguard the interests of the contracting parties, the tender outlines a mechanism for performance bank guarantees (PBG) in case the bidder's offer is below the estimated cost. Here's how the PBG requirement is structured: 1. If the bidder's quoted offer is between 1% and 10% below the estimated cost, a PBG equivalent to 1% of the estimated cost is mandatory. 2. In cases where the offer is more than 10% but up to 15% below the estimated cost, an additional PBG is required. This extra security is calculated at a rate of 1% for every percent below the estimated cost. For example, if the bid is 14% below the cost (14% - 10% = 4%), an additional security of 5% would be necessary. 3. When the bid is more than 15% below the estimated cost in the tender, an additional performance security of 2% for each per cent below the cost must be furnished. For instance, if the bid is 19% below the cost (19% - 15% = 4%), an additional security of 14% of the estimated cost would be required. Failure to submit the PBG within eight days from the date of the financial opening will lead to the rejection of the tender. In such cases, the second lowest bidder (L-2 Bidder) will be informed in writing. The L-2 bidder will have the opportunity to negotiate, and if they agree to perform the work at a rate lower than the offer of the L-1 bidder, their tender will be accepted. These tenders emphasise the importance of certification and experience in executing similar work. To be eligible to bid for these projects, contractors must have a valid certificate as a registered contractor with the Government of Maharashtra, which is applicable for works with an estimated amount less than ?15 million (~$180,203).

Related Stories

Gold Stories

Next Story
Real Estate

The Energy-Smart Buildings

Passive design is an integral part of energy-efficient architecture. Sophisticated building systems also contribute to this end. But what role do materials play in enhancing a building’s energy-efficiency?“Material selection is one of the earliest opportunities to influence how a building performs,” says Tejbeer Singh, Principal Architect & Founder, Expressionist by Tejbeer Singh. “The objective is not simply to select materials that look appropriate but to understand how they behave within the climate and construction system.”To read the full article Click Here ..

Next Story
Infrastructure Transport

When the Lowest Bid Comes at a Cost

India's infrastructure sector is building at a scale few markets can match. New highways, expressways, metros, bridges and complex engineering projects are transforming the country's landscape. Yet, behind this rapid expansion is a growing concern within the contracting community: Can infrastructure be delivered sustainably when competition pushes prices below commercially viable levels?For Praveen Sethia, Founder & Director, Infra Advisors, who moderated the discussion, the question goes beyond the contractor's commercial interests. Contractors may be one of the two parties to a contract,..

Next Story
Real Estate

Ultra-Luxury Projects Reshape Gurugram’s Housing Market

Gurugram’s luxury housing market has expanded beyond its traditional prime locations, with corridors such as Dwarka Expressway and Golf Course Extension Road emerging as key centres for premium residential development. Larger homes, integrated developments and amenity-led communities are attracting demand from end-users and investors.A 2025 report by Sotheby’s International Realty in collaboration with CRE Matrix identified Gurugram as India’s fastest-growing ultra-luxury housing market. The city overtook Mumbai in total sales value for homes priced above Rs 10 crore, recording nearly Rs..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code