Maharashtra Plans 11 EV Charging Stations in Transport Hubs
POWER & RENEWABLE ENERGY

Maharashtra Plans 11 EV Charging Stations in Transport Hubs

The Maharashtra State Road Transport Corporation (MSRTC) has initiated a significant move to enhance its electric vehicle (EV) charging infrastructure by releasing separate tenders for the installation of 11 EV charging stations. These charging stations are set to be strategically located around different bus and railway depots in the state, improving accessibility for EV users.

The locations for these proposed charging stations, along with their estimated project costs, are as follows:

1. Mumbai Central Depot: ?109.8 million (~$1.45 million) 2. Borivali Depot: ?89.9 million (~$1.19 million) 3. Santacruz Depot: ?65.5 million (~$872,000) 4. Kurla Depot: ?89.9 million (~$1.19 million) 5. Thane Depot: ?69.8 million (~$928,000) 6. Panvel Depot: ?75.5 million (~$1 million) 7. Pune Station Depot: ?75.5 million (~$1 million) 8. Swargate Depot: ?93.4 million (~$1.24 million) 9. Pune Divisional Office, Shivajinagar: ?79.8 million (~$1.06 million) 10. Shivajinagar Railway Depot: ?85.6 million (~$1.14 million) 11. Yerwada Bus Stand: ?94.5 million (~$1.26 million)

The deadline for bid submissions is set for October 30, 2023, and the bids will be opened on November 1. The tender process also involves a 2% security deposit requirement for each of these charging station projects. This deposit is divided into two parts:

1. 1% of the individual project cost, which converts the earnest money deposit into a security deposit. 2. Another 1% initial security deposit is required before the work order is issued, with a validity period of 120 days from the date of opening.

The timeline for the completion of these projects is expected to be three months, starting from the date of the written work order. To encourage competitive bidding and safeguard the interests of the contracting parties, the tender outlines a mechanism for performance bank guarantees (PBG) in case the bidder's offer is below the estimated cost. Here's how the PBG requirement is structured:

1. If the bidder's quoted offer is between 1% and 10% below the estimated cost, a PBG equivalent to 1% of the estimated cost is mandatory.

2. In cases where the offer is more than 10% but up to 15% below the estimated cost, an additional PBG is required. This extra security is calculated at a rate of 1% for every percent below the estimated cost. For example, if the bid is 14% below the cost (14% - 10% = 4%), an additional security of 5% would be necessary.

3. When the bid is more than 15% below the estimated cost in the tender, an additional performance security of 2% for each per cent below the cost must be furnished. For instance, if the bid is 19% below the cost (19% - 15% = 4%), an additional security of 14% of the estimated cost would be required.

Failure to submit the PBG within eight days from the date of the financial opening will lead to the rejection of the tender. In such cases, the second lowest bidder (L-2 Bidder) will be informed in writing. The L-2 bidder will have the opportunity to negotiate, and if they agree to perform the work at a rate lower than the offer of the L-1 bidder, their tender will be accepted.

These tenders emphasise the importance of certification and experience in executing similar work. To be eligible to bid for these projects, contractors must have a valid certificate as a registered contractor with the Government of Maharashtra, which is applicable for works with an estimated amount less than ?15 million (~$180,203).

The Maharashtra State Road Transport Corporation (MSRTC) has initiated a significant move to enhance its electric vehicle (EV) charging infrastructure by releasing separate tenders for the installation of 11 EV charging stations. These charging stations are set to be strategically located around different bus and railway depots in the state, improving accessibility for EV users. The locations for these proposed charging stations, along with their estimated project costs, are as follows: 1. Mumbai Central Depot: ?109.8 million (~$1.45 million) 2. Borivali Depot: ?89.9 million (~$1.19 million) 3. Santacruz Depot: ?65.5 million (~$872,000) 4. Kurla Depot: ?89.9 million (~$1.19 million) 5. Thane Depot: ?69.8 million (~$928,000) 6. Panvel Depot: ?75.5 million (~$1 million) 7. Pune Station Depot: ?75.5 million (~$1 million) 8. Swargate Depot: ?93.4 million (~$1.24 million) 9. Pune Divisional Office, Shivajinagar: ?79.8 million (~$1.06 million) 10. Shivajinagar Railway Depot: ?85.6 million (~$1.14 million) 11. Yerwada Bus Stand: ?94.5 million (~$1.26 million) The deadline for bid submissions is set for October 30, 2023, and the bids will be opened on November 1. The tender process also involves a 2% security deposit requirement for each of these charging station projects. This deposit is divided into two parts: 1. 1% of the individual project cost, which converts the earnest money deposit into a security deposit. 2. Another 1% initial security deposit is required before the work order is issued, with a validity period of 120 days from the date of opening. The timeline for the completion of these projects is expected to be three months, starting from the date of the written work order. To encourage competitive bidding and safeguard the interests of the contracting parties, the tender outlines a mechanism for performance bank guarantees (PBG) in case the bidder's offer is below the estimated cost. Here's how the PBG requirement is structured: 1. If the bidder's quoted offer is between 1% and 10% below the estimated cost, a PBG equivalent to 1% of the estimated cost is mandatory. 2. In cases where the offer is more than 10% but up to 15% below the estimated cost, an additional PBG is required. This extra security is calculated at a rate of 1% for every percent below the estimated cost. For example, if the bid is 14% below the cost (14% - 10% = 4%), an additional security of 5% would be necessary. 3. When the bid is more than 15% below the estimated cost in the tender, an additional performance security of 2% for each per cent below the cost must be furnished. For instance, if the bid is 19% below the cost (19% - 15% = 4%), an additional security of 14% of the estimated cost would be required. Failure to submit the PBG within eight days from the date of the financial opening will lead to the rejection of the tender. In such cases, the second lowest bidder (L-2 Bidder) will be informed in writing. The L-2 bidder will have the opportunity to negotiate, and if they agree to perform the work at a rate lower than the offer of the L-1 bidder, their tender will be accepted. These tenders emphasise the importance of certification and experience in executing similar work. To be eligible to bid for these projects, contractors must have a valid certificate as a registered contractor with the Government of Maharashtra, which is applicable for works with an estimated amount less than ?15 million (~$180,203).

Next Story
Infrastructure Energy

South West Pinnacle Wins Rs 30 Cr Oman Mining Contract

South West Pinnacle Exploration Ltd has secured a Rs 30 crore contract from Minerals Development Oman (MDO) for mining exploration in concession areas 12B and 13.The two-year project will be carried out via Alara Resources LLC, a JV in Oman. MDO, backed by Oman’s investment authorities, focuses on monetising mineral wealth.The contract covers copper, gold, and chromite and highlights South West Pinnacle’s growing footprint in international exploration and mining services. ..

Next Story
Equipment

Godrej GEG Boosts Intralogistics with AI and Green Tech

Godrej Enterprises Group (GEG) is revolutionising warehouse and factory logistics through its Material Handling Equipment and Storage Solutions arms by integrating AI, IoT, and automation.With 20–25% market share and 85% local sourcing, GEG champions Atmanirbhar Bharat and sustainability. The Chennai plant, a green manufacturing leader, uses RoHS-compliant materials and has slashed energy consumption by 60%.GEG serves e-commerce, FMCG, retail, and cold chains with high-performance racking and electric forklifts. Upcoming IoT-enabled forklifts and telematics solutions aim to improve speed, sa..

Next Story
Infrastructure Urban

Amit Shah Inaugurates Key Projects Across Gujarat

Union Home Minister Amit Shah inaugurated and laid the foundation stone for various projects in Gujarat’s Panchmahal district and Ahmedabad.In Godhra, he inaugurated the Center of Excellence building, sports complex, reservoir, and Miyawaki plantation. In Ahmedabad, he unveiled a new cooperative complex in Adaroda village and a primary school in Juwal.These projects, under the Model Co-op Village scheme, aim to boost education, sustainability, and rural development across the state. ..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?