Maharashtra Plans 11 EV Charging Stations in Transport Hubs
POWER & RENEWABLE ENERGY

Maharashtra Plans 11 EV Charging Stations in Transport Hubs

The Maharashtra State Road Transport Corporation (MSRTC) has initiated a significant move to enhance its electric vehicle (EV) charging infrastructure by releasing separate tenders for the installation of 11 EV charging stations. These charging stations are set to be strategically located around different bus and railway depots in the state, improving accessibility for EV users.

The locations for these proposed charging stations, along with their estimated project costs, are as follows:

1. Mumbai Central Depot: ?109.8 million (~$1.45 million) 2. Borivali Depot: ?89.9 million (~$1.19 million) 3. Santacruz Depot: ?65.5 million (~$872,000) 4. Kurla Depot: ?89.9 million (~$1.19 million) 5. Thane Depot: ?69.8 million (~$928,000) 6. Panvel Depot: ?75.5 million (~$1 million) 7. Pune Station Depot: ?75.5 million (~$1 million) 8. Swargate Depot: ?93.4 million (~$1.24 million) 9. Pune Divisional Office, Shivajinagar: ?79.8 million (~$1.06 million) 10. Shivajinagar Railway Depot: ?85.6 million (~$1.14 million) 11. Yerwada Bus Stand: ?94.5 million (~$1.26 million)

The deadline for bid submissions is set for October 30, 2023, and the bids will be opened on November 1. The tender process also involves a 2% security deposit requirement for each of these charging station projects. This deposit is divided into two parts:

1. 1% of the individual project cost, which converts the earnest money deposit into a security deposit. 2. Another 1% initial security deposit is required before the work order is issued, with a validity period of 120 days from the date of opening.

The timeline for the completion of these projects is expected to be three months, starting from the date of the written work order. To encourage competitive bidding and safeguard the interests of the contracting parties, the tender outlines a mechanism for performance bank guarantees (PBG) in case the bidder's offer is below the estimated cost. Here's how the PBG requirement is structured:

1. If the bidder's quoted offer is between 1% and 10% below the estimated cost, a PBG equivalent to 1% of the estimated cost is mandatory.

2. In cases where the offer is more than 10% but up to 15% below the estimated cost, an additional PBG is required. This extra security is calculated at a rate of 1% for every percent below the estimated cost. For example, if the bid is 14% below the cost (14% - 10% = 4%), an additional security of 5% would be necessary.

3. When the bid is more than 15% below the estimated cost in the tender, an additional performance security of 2% for each per cent below the cost must be furnished. For instance, if the bid is 19% below the cost (19% - 15% = 4%), an additional security of 14% of the estimated cost would be required.

Failure to submit the PBG within eight days from the date of the financial opening will lead to the rejection of the tender. In such cases, the second lowest bidder (L-2 Bidder) will be informed in writing. The L-2 bidder will have the opportunity to negotiate, and if they agree to perform the work at a rate lower than the offer of the L-1 bidder, their tender will be accepted.

These tenders emphasise the importance of certification and experience in executing similar work. To be eligible to bid for these projects, contractors must have a valid certificate as a registered contractor with the Government of Maharashtra, which is applicable for works with an estimated amount less than ?15 million (~$180,203).

The Maharashtra State Road Transport Corporation (MSRTC) has initiated a significant move to enhance its electric vehicle (EV) charging infrastructure by releasing separate tenders for the installation of 11 EV charging stations. These charging stations are set to be strategically located around different bus and railway depots in the state, improving accessibility for EV users. The locations for these proposed charging stations, along with their estimated project costs, are as follows: 1. Mumbai Central Depot: ?109.8 million (~$1.45 million) 2. Borivali Depot: ?89.9 million (~$1.19 million) 3. Santacruz Depot: ?65.5 million (~$872,000) 4. Kurla Depot: ?89.9 million (~$1.19 million) 5. Thane Depot: ?69.8 million (~$928,000) 6. Panvel Depot: ?75.5 million (~$1 million) 7. Pune Station Depot: ?75.5 million (~$1 million) 8. Swargate Depot: ?93.4 million (~$1.24 million) 9. Pune Divisional Office, Shivajinagar: ?79.8 million (~$1.06 million) 10. Shivajinagar Railway Depot: ?85.6 million (~$1.14 million) 11. Yerwada Bus Stand: ?94.5 million (~$1.26 million) The deadline for bid submissions is set for October 30, 2023, and the bids will be opened on November 1. The tender process also involves a 2% security deposit requirement for each of these charging station projects. This deposit is divided into two parts: 1. 1% of the individual project cost, which converts the earnest money deposit into a security deposit. 2. Another 1% initial security deposit is required before the work order is issued, with a validity period of 120 days from the date of opening. The timeline for the completion of these projects is expected to be three months, starting from the date of the written work order. To encourage competitive bidding and safeguard the interests of the contracting parties, the tender outlines a mechanism for performance bank guarantees (PBG) in case the bidder's offer is below the estimated cost. Here's how the PBG requirement is structured: 1. If the bidder's quoted offer is between 1% and 10% below the estimated cost, a PBG equivalent to 1% of the estimated cost is mandatory. 2. In cases where the offer is more than 10% but up to 15% below the estimated cost, an additional PBG is required. This extra security is calculated at a rate of 1% for every percent below the estimated cost. For example, if the bid is 14% below the cost (14% - 10% = 4%), an additional security of 5% would be necessary. 3. When the bid is more than 15% below the estimated cost in the tender, an additional performance security of 2% for each per cent below the cost must be furnished. For instance, if the bid is 19% below the cost (19% - 15% = 4%), an additional security of 14% of the estimated cost would be required. Failure to submit the PBG within eight days from the date of the financial opening will lead to the rejection of the tender. In such cases, the second lowest bidder (L-2 Bidder) will be informed in writing. The L-2 bidder will have the opportunity to negotiate, and if they agree to perform the work at a rate lower than the offer of the L-1 bidder, their tender will be accepted. These tenders emphasise the importance of certification and experience in executing similar work. To be eligible to bid for these projects, contractors must have a valid certificate as a registered contractor with the Government of Maharashtra, which is applicable for works with an estimated amount less than ?15 million (~$180,203).

Next Story
Infrastructure Transport

RVNL secures Rs 1.65 billion railway bridge project from North Eastern Railway

Rail Vikas Nigam (RVNL) has received a Letter of Award (LoA) from North Eastern Railway for a Rs 1.65 billion railway infrastructure project, strengthening its order book and showcasing its expertise in complex railway construction.The project involves constructing the substructure of a major railway bridge over the Gandak River, located between Paniyahwa and Valmikinagar stations. This is part of the doubling of the Gorakhpur Cantt–Valmikinagar railway section, aimed at improving line capacity and operational efficiency.The bridge will feature 14 spans of 61 metres each, built on double D-t..

Next Story
Infrastructure Transport

Raebareli’s Modern Coach Factory rolls out 15,000th railway coach

The Modern Coach Factory (MCF) at Raebareli in Uttar Pradesh has achieved a major manufacturing milestone with the rollout of its 15,000th railway coach on December 15, the Ministry of Railways said.In a press note, the ministry said that MCF has already produced 1,310 coaches in the current financial year 2025–26, reflecting sustained high output at one of Indian Railways’ most advanced passenger coach manufacturing units.Established in 2007 at Lalganj in Raebareli district, MCF was built at a cost of Rs 31.92 billion with an initial annual production capacity of 1,000 coaches. The factor..

Next Story
Infrastructure Transport

RailTel wins Rs 260.88 million IT infrastructure order from VOC Port

Navratna public sector undertaking RailTel Corporation of India has secured an IT infrastructure order worth Rs 260.88 million from V.O. Chidambaranar Port Authority (VOC Port), strengthening its presence in port-led digital transformation projects.According to an exchange filing dated December 16, 2025, RailTel has received a Letter of Acceptance (LoA) from VOC Port Authority for the implementation of advanced IT infrastructure at the port. The project is domestic in nature and is scheduled to be completed by August 15, 2026.The company said the order has been awarded in the normal course of ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Open In App