MERC Approves Tariffs for 2,000 MW/4,000 MWh Battery Storage
POWER & RENEWABLE ENERGY

MERC Approves Tariffs for 2,000 MW/4,000 MWh Battery Storage

The Maharashtra Electricity Regulatory Commission (MERC) has approved tariffs for the Maharashtra State Electricity Distribution Company (MSEDCL) to procure 2,000 MW/4,000 MWh of battery energy storage capacity for 15 years. Under its November 23, 2026 order in Case No. 218 of 2026, the commission approved monthly tariffs of Rs. 240,000 per MW for Part-A and Rs. 238,000 per MW for Part-B. The procurement will receive Viability Gap Funding (VGF) support through the Power System Development Fund.

The approved projects will operate for one cycle per day with a two-hour discharge duration. Part-A covers 500 MW/1,000 MWh at MSEDCL substations and is reserved for eligible developers under the Mukhyamantri Saur Krushi Vahini Yojana 2.0. Part-B covers 1,500 MW/3,000 MWh at Maharashtra State Electricity Transmission Company substations and sites co-located with existing solar projects contracted with MSEDCL.

The tender, issued on June 30, 2026, received 45 bids, which were opened in August. Reverse auctions on August 31 established the final tariffs after the highest bidders were disqualified under the tender conditions. MSEDCL issued Letters of Award to the selected developers on September 18.

Five developers were selected for Part-A, with Oriana Power receiving the largest allocation at 400 MW. Seven developers were awarded capacity under Part-B, including Oriana Power with 500 MW, BSL Engineering Service with 300 MW and ArMee Infotech with 250 MW. Each selected developer has committed to maintaining minimum round-trip efficiency of 85 per cent.

MSEDCL has reserved VGF support of up to Rs. 1.8 mn per MWh for developers selected through the new process. MERC said the tariffs were reasonable compared with recent storage tenders by other utilities. The approved capacity may count towards MSEDCL’s Energy Storage Obligation, which rises to 4 per cent by FY 2029-30, with commissioning scheduled during FY 2027-28. MSEDCL must execute Battery Energy Storage Purchase Agreements within 15 days and submit them to the commission.

The Maharashtra Electricity Regulatory Commission (MERC) has approved tariffs for the Maharashtra State Electricity Distribution Company (MSEDCL) to procure 2,000 MW/4,000 MWh of battery energy storage capacity for 15 years. Under its November 23, 2026 order in Case No. 218 of 2026, the commission approved monthly tariffs of Rs. 240,000 per MW for Part-A and Rs. 238,000 per MW for Part-B. The procurement will receive Viability Gap Funding (VGF) support through the Power System Development Fund. The approved projects will operate for one cycle per day with a two-hour discharge duration. Part-A covers 500 MW/1,000 MWh at MSEDCL substations and is reserved for eligible developers under the Mukhyamantri Saur Krushi Vahini Yojana 2.0. Part-B covers 1,500 MW/3,000 MWh at Maharashtra State Electricity Transmission Company substations and sites co-located with existing solar projects contracted with MSEDCL. The tender, issued on June 30, 2026, received 45 bids, which were opened in August. Reverse auctions on August 31 established the final tariffs after the highest bidders were disqualified under the tender conditions. MSEDCL issued Letters of Award to the selected developers on September 18. Five developers were selected for Part-A, with Oriana Power receiving the largest allocation at 400 MW. Seven developers were awarded capacity under Part-B, including Oriana Power with 500 MW, BSL Engineering Service with 300 MW and ArMee Infotech with 250 MW. Each selected developer has committed to maintaining minimum round-trip efficiency of 85 per cent. MSEDCL has reserved VGF support of up to Rs. 1.8 mn per MWh for developers selected through the new process. MERC said the tariffs were reasonable compared with recent storage tenders by other utilities. The approved capacity may count towards MSEDCL’s Energy Storage Obligation, which rises to 4 per cent by FY 2029-30, with commissioning scheduled during FY 2027-28. MSEDCL must execute Battery Energy Storage Purchase Agreements within 15 days and submit them to the commission.

Related Stories

Gold Stories

Next Story
Infrastructure Transport

Shillong Airport Expansion on Track for December 2027 Finish

Work on the expansion of Shillong Airport and its runway is progressing according to schedule, with completion targeted for December 2027, Transport and Civil Aviation Department Secretary Sanjay Goyal said. The construction is being carried out under the approved master plan, and officials are monitoring progress to ensure the planned timeline is maintained. Goyal said the work was in full swing and there was currently no reason to anticipate a delay. The project is intended to improve the airport’s capacity and strengthen air connectivity to and from the region as demand for air travel inc..

Next Story
Infrastructure Transport

GMR Hyderabad Airport Enhances Cargo Capacity

GMR Hyderabad International Airport has enhanced its cargo-handling infrastructure by commissioning an upgraded Elevated Transfer Vehicle (ETV)-based storage system at its Cargo Terminal. The facility has been upgraded within the existing terminal footprint, allowing the airport to expand capacity without requiring additional space. The new system has increased Unit Load Device (ULD) storage capacity from 33 to 80 ULDs. This represents an increase of more than double and is intended to provide greater operational flexibility as cargo volumes and freighter activity expand. The additional storag..

Next Story
Infrastructure Urban

Visteon Expands Chennai Manufacturing with Cellular NAD Line

Visteon has launched a production line for Cellular Network Access Device (NAD) modules at its manufacturing plant in Chennai, Tamil Nadu. The investment expands the automotive technology company’s local manufacturing capabilities and strengthens its regional supply chain. The line was inaugurated by Sachin Lawande, Visteon’s President and Chief Executive Officer, along with members of the company’s leadership team. Production in Chennai positions India as a manufacturing base for Cellular NAD technology and enables the company to serve customers in international markets from the region...

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code