MERC Leaves Extension Decision on 730 MW Solar Project to Parties
POWER & RENEWABLE ENERGY

MERC Leaves Extension Decision on 730 MW Solar Project to Parties

The Maharashtra Electricity Regulatory Commission (MERC) has disposed of a petition concerning Carbon Minus Energy’s 730 MW grid-connected solar project, leaving the decision on extending its Scheduled Commencement of Supply Date (SCSD) and Financial Closure timeline to the developer and Maharashtra State Electricity Distribution Company (MSEDCL).

The project was awarded under Maharashtra’s scheme for solarisation of lift irrigation systems after MSEDCL’s competitive bidding process. MSEDCL had initially invited bids for 800 MW of projects on spare Water Resource Department land, with Carbon Minus Energy later selected for 730 MW. Its Letter of Award was issued on October 7, 2024, while power purchase agreements (PPAs) covering 505 MW and 225 MW were signed in April 2025.

Carbonminus Maharashtra One (CMOPL), the special purpose vehicle established for the project, sought extensions after delays in receiving registered land and grid connectivity. It said these conditions were necessary for achieving Financial Closure and meeting the SCSD. CMOPL also reported in-principle approval from Power Finance Corporation, although final closure remained pending because the land lease deed had not been executed and connectivity was unavailable.

MSEDCL disputed the developer’s position, maintaining that bidders could arrange alternative land at their own cost and that CMOPL had missed the contractual Financial Closure deadline. The utility also alleged that a Performance Bank Guarantee submitted by the parent company was invalid. A complaint was filed with the Economic Offences Wing in Mumbai, after which CMOPL submitted electronic guarantees of Rs. 252.5 mn and Rs. 112.5 mn.

The land issue subsequently eased. In April 2026, MSEDCL allowed CMOPL to use private land for 660 MW, and the developer submitted procurement documents relating to the Alephata substation. At a July hearing, MSEDCL raised no objection to extensions, while CMOPL said procurement was nearly complete and Financial Closure would follow shortly. MERC held that the consensus removed the dispute requiring adjudication.

The Commission clarified that the PPA permits MSEDCL to extend the SCSD by up to two months, subject to documentary evidence. Any longer extension must be handled through the contractual mechanism for amending the PPAs. MERC noted the tariff of Rs. 0.88/kWh but said this did not give it jurisdiction to change the timeline without an active dispute. The parties may return to the Commission if a new disagreement arises.

The Maharashtra Electricity Regulatory Commission (MERC) has disposed of a petition concerning Carbon Minus Energy’s 730 MW grid-connected solar project, leaving the decision on extending its Scheduled Commencement of Supply Date (SCSD) and Financial Closure timeline to the developer and Maharashtra State Electricity Distribution Company (MSEDCL). The project was awarded under Maharashtra’s scheme for solarisation of lift irrigation systems after MSEDCL’s competitive bidding process. MSEDCL had initially invited bids for 800 MW of projects on spare Water Resource Department land, with Carbon Minus Energy later selected for 730 MW. Its Letter of Award was issued on October 7, 2024, while power purchase agreements (PPAs) covering 505 MW and 225 MW were signed in April 2025. Carbonminus Maharashtra One (CMOPL), the special purpose vehicle established for the project, sought extensions after delays in receiving registered land and grid connectivity. It said these conditions were necessary for achieving Financial Closure and meeting the SCSD. CMOPL also reported in-principle approval from Power Finance Corporation, although final closure remained pending because the land lease deed had not been executed and connectivity was unavailable. MSEDCL disputed the developer’s position, maintaining that bidders could arrange alternative land at their own cost and that CMOPL had missed the contractual Financial Closure deadline. The utility also alleged that a Performance Bank Guarantee submitted by the parent company was invalid. A complaint was filed with the Economic Offences Wing in Mumbai, after which CMOPL submitted electronic guarantees of Rs. 252.5 mn and Rs. 112.5 mn. The land issue subsequently eased. In April 2026, MSEDCL allowed CMOPL to use private land for 660 MW, and the developer submitted procurement documents relating to the Alephata substation. At a July hearing, MSEDCL raised no objection to extensions, while CMOPL said procurement was nearly complete and Financial Closure would follow shortly. MERC held that the consensus removed the dispute requiring adjudication. The Commission clarified that the PPA permits MSEDCL to extend the SCSD by up to two months, subject to documentary evidence. Any longer extension must be handled through the contractual mechanism for amending the PPAs. MERC noted the tariff of Rs. 0.88/kWh but said this did not give it jurisdiction to change the timeline without an active dispute. The parties may return to the Commission if a new disagreement arises.

Related Stories

Gold Stories

Next Story
Resources

Hettich India And ECO Schulte Form Joint Venture In India

Hettich India and German company ECO Schulte have announced a strategic joint venture to strengthen their presence in India's architectural hardware market. The partnership was announced at ACETECH Mumbai on November 20, 2026, bringing together the two family-owned businesses with a combined engineering heritage of 238 years.The venture combines Hettich's expertise in furniture fittings and interior solutions with ECO Schulte's experience in architectural door hardware and engineered door systems. Its focus will span residential, commercial, institutional and infrastructure projects.Hettich, w..

Next Story
Real Estate

Address Maker sells over 200 Apollo Address plots in six weeks

The Address Maker Group has sold more than two-thirds of the inventory at its Apollo Address villa-plot development in Nelamangala, North-West Bengaluru, within six weeks of its launch. With over 200 plots purchased and approximately 100 remaining, the project has recorded the fastest sales pace in the developer's history.Spread across 23 acres within a larger 90-acre township, Apollo Address offers villa plots ranging from 1,200 to 2,400 sq ft. Inspired by classical Greek architecture, the development features planned infrastructure, landscaped open spaces and residential amenities.Nearly 30 ..

Next Story
Equipment

Zoomlion strengthens equipment partnerships in Australia

Zoomlion Heavy Industry Science & Technology has reaffirmed its commitment to expanding operations in Australia, with Chairman and CEO Zhan Chunxin meeting customers and business partners in Sydney to strengthen long-term partnerships and discuss opportunities for closer collaboration.The meeting, held on 4 November 2026, focused on equipment quality, technical support, spare parts availability, local training and customer service improvements. Representatives from the tower crane, concrete machinery, earthmoving, aerial work platform, agricultural machinery and financial sectors participa..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code