Shortage of Critical Equipment Hits Madhya Pradesh Power Transmission Expansion
POWER & RENEWABLE ENERGY

Shortage of Critical Equipment Hits Madhya Pradesh Power Transmission Expansion

Madhya Pradesh’s power transmission expansion programme is facing shortages of critical equipment, including high-voltage insulators and power transformers, as renewable energy development accelerates. The constraints have raised concerns about the timely execution of infrastructure projects needed to move electricity from generation plants to distribution substations.

Madhya Pradesh has a population of around 90 mn and installed power generation capacity of 12,090 MW, including solar power. Madhya Pradesh Power Transmission Company, known as MP Transco, transmits electricity from generating stations to distribution companies that supply households, industries and commercial establishments.

MP Transco officials said domestic manufacturing had not declined, but rapid infrastructure development across India had widened the gap between demand and supply. Availability of raw materials for porcelain insulators has become difficult, while gas shortages associated with disruptions in the global energy supply chain have affected production at some manufacturing units.

Thousands of insulator strings across different voltage capacities are required each year, while some specialised products continue to be imported. Manufacturers are increasingly adopting polymer and composite insulators because they are lighter, easier to handle and require less maintenance, particularly in polluted and dusty environments. Delivery schedules for certain insulator categories have increased from 12 to 15 months to around 18 to 20 months.

Transformer manufacturers are also facing higher demand for extra-high-voltage transformers, auto-transformers and interconnecting transformers used in 400 kV, 220 kV and 132 kV substations. These products require cold-rolled grain-oriented electrical steel, copper conductors, insulation materials, high-voltage bushings and on-load tap changers. Limited availability of some components has extended delivery periods for large extra-high-voltage transformers from 8 to 12 months to as much as 18 to 24 months.

More than 88 GW of renewable energy capacity has been auctioned in India over the past two years, increasing the need for new transmission corridors, pooling substations and grid interconnections. Madhya Pradesh is developing several solar and other renewable energy projects, requiring additional extra-high-voltage lines and substations. Industry representatives have called for stronger domestic manufacturing, assured supplies of raw materials and expanded production capacity to reduce import dependence and protect grid reliability.

Madhya Pradesh’s power transmission expansion programme is facing shortages of critical equipment, including high-voltage insulators and power transformers, as renewable energy development accelerates. The constraints have raised concerns about the timely execution of infrastructure projects needed to move electricity from generation plants to distribution substations. Madhya Pradesh has a population of around 90 mn and installed power generation capacity of 12,090 MW, including solar power. Madhya Pradesh Power Transmission Company, known as MP Transco, transmits electricity from generating stations to distribution companies that supply households, industries and commercial establishments. MP Transco officials said domestic manufacturing had not declined, but rapid infrastructure development across India had widened the gap between demand and supply. Availability of raw materials for porcelain insulators has become difficult, while gas shortages associated with disruptions in the global energy supply chain have affected production at some manufacturing units. Thousands of insulator strings across different voltage capacities are required each year, while some specialised products continue to be imported. Manufacturers are increasingly adopting polymer and composite insulators because they are lighter, easier to handle and require less maintenance, particularly in polluted and dusty environments. Delivery schedules for certain insulator categories have increased from 12 to 15 months to around 18 to 20 months. Transformer manufacturers are also facing higher demand for extra-high-voltage transformers, auto-transformers and interconnecting transformers used in 400 kV, 220 kV and 132 kV substations. These products require cold-rolled grain-oriented electrical steel, copper conductors, insulation materials, high-voltage bushings and on-load tap changers. Limited availability of some components has extended delivery periods for large extra-high-voltage transformers from 8 to 12 months to as much as 18 to 24 months. More than 88 GW of renewable energy capacity has been auctioned in India over the past two years, increasing the need for new transmission corridors, pooling substations and grid interconnections. Madhya Pradesh is developing several solar and other renewable energy projects, requiring additional extra-high-voltage lines and substations. Industry representatives have called for stronger domestic manufacturing, assured supplies of raw materials and expanded production capacity to reduce import dependence and protect grid reliability.

Related Stories

Gold Stories

Next Story
Building Material

MCi Carbon, JSW Steel and JAKSON Green sign MoU

Australian clean technology company MCi Carbon, JSW Steel Limited and JAKSON Green Ltd. have signed a tripartite Memorandum of Understanding (MoU) to evaluate the technical and commercial feasibility of using MCi Carbon’s mineral carbonation technology to convert steel slag and CO₂ streams from JSW Steel’s operations in India into carbon-embedded materials.Under the agreement, JSW Steel will provide operational knowledge, representative slag samples and process information. JAKSON Green will coordinate the project, providing engineering, cost and logistics inputs, along with its engineer..

Next Story
Building Material

JSW Dulux launches Velvet Touch Eterna High Sheen

JSW Dulux (formerly Akzo Nobel India) has launched Velvet Touch™ Eterna High Sheen, a new addition to its premium Velvet Touch™ Eterna portfolio. The interior emulsion features a reflective finish, colour protection technology and a 12-year warranty.The product was unveiled in Kolkata in the presence of the company's sales leadership, distributors, dealers and channel partners from Eastern India. It is designed to provide a light-reflecting finish that adds depth and radiance to interior spaces.Commenting on the launch, Vandana Krishnia, Chief Marketing Officer, JSW Dulux Limited, said, â€..

Next Story
Real Estate

Concorde signs JDA for residential project in North Bengaluru

Bengaluru-based real estate developer Concorde has signed a Joint Development Agreement (JDA) for a premium residential project on a 3-acre land parcel in North Bengaluru. The development has an estimated potential of 400,000 sq ft and a Gross Development Value (GDV) of ₹4.5 billion.The project will add to Concorde's residential portfolio, with a focus on contemporary architecture, construction quality and lifestyle amenities.Commenting on the development, Anil RG, Managing Director, Concorde, said, “North Bengaluru is emerging as a significant growth destination, and this development mark..

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code