The Critical Path
RAILWAYS & METRO RAIL

The Critical Path

In Ircon International Ltd v. Afcons Infrastructure Ltd, OMP (Comm) 279/2019, the Delhi High Court examined how delay and extension of time (‘EOT’) are to be assessed in construction contracts, particularly in the context of the ‘critical path’ while dealing with challenge to an arbitra...

In Ircon International Ltd v. Afcons Infrastructure Ltd, OMP (Comm) 279/2019, the Delhi High Court examined how delay and extension of time (‘EOT’) are to be assessed in construction contracts, particularly in the context of the ‘critical path’ while dealing with challenge to an arbitral award under Section 34 of the Arbitration and Conciliation Act 1996 (‘the Act’). The High Court’s observations regarding the critical path are of significant import for construction and infrastructure projects and related arbitration. The parties entered into a contract for construction of Tunnel T-74R on the Udhampur-Srinagar-Baramulla railway line. The project was to be completed within 33 months from the date of commencement, with 17 ‘key dates’ (KDs) prescribed under Appendix XV of the contract. During the execution of works, several delays were encountered by Afcons and it sought extension of time of 171 days for KD 3 (completion of adit excavation), citing adverse geology, inclement weather and law-and-order issues. Subsequently, Afcons sought further extensions aggregating to 504 days up to September 15, 2016, on similar grounds. However, Ircon granted an extension of only 21 days for KD 3 to Afcons. At the same time, Ircon imposed liquidated damages for delay beyond the extended period, including a sum of Rs 2,67,05,797/- for delay in achieving the relevant KDs, on Afcons. Disputes arose between the parties and Afcons invoked arbitration on November 19, 2016. In its statement of claim, Afcons sought, inter alia, overall extension of time up to September 15, 2016, without levy of liquidated damages and refund of Rs 9,69,18,488/- deducted by Ircon towards liquidated damages. In its defence, Ircon alleged that the delays were attributable to Afcons and justified the levy of damages. After analysing the evidence, the arbitral tribunal granted an extension of 484 days up to September 15, 2016, to Afcons, holding that the delays were not attributable to it. The tribunal identified three principal causes of delay: 847 days on account of adverse geological conditions; 73 days due to inclement weather; and 93 days due to law-and-order issues. Based on this analysis, the tribunal concluded that Afcons was entitled to a net extension of 484 days beyond the originally stipulated duration. A key aspect of the award was the tribunal’s determination of the critical path. It held that completion of the main tunnel Banihal (KD 14) was on the critical path for overall project completion in terms of the key dates stipulated under the contract. It observed that other tunnel works were being executed concurrently and would be completed prior to completion of the Banihal tunnel. Accordingly, delay in the Banihal tunnel would necessarily delay the entire project. On this basis, the tribunal granted the extension of 484 days to the project as a whole and rejected the need for separate extensions for each tunnel. Ircon challenged the award under Section 34 of the Act, contending that the contract did not recognise the concept of critical path; each tunnel had independent key dates requiring separate analysis; and that the tribunal had granted a uniform extension without contractual basis, thereby rewriting the contract. The High Court rejected these contentions and held that the tribunal’s determination of the critical path was based on the sequencing of activities reflected in the key dates and was a plausible interpretation of the contract. The Court held that completion of the main tunnel governed overall completion and, therefore, the tribunal was justified in treating it as the critical activity as it comprised technically qualified members who were capable of determining ‘critical path’ with respect to a construction project. Thus, the challenge to the award was rejected and the petition dismissed. Importance of critical pathThe judgement underscores the significance of the critical path in construction disputes. The critical path represents the sequence of activities that determines the overall duration of the project. Any delay in such activities directly impacts project completion.In the case discussed above, the tribunal’s identification of the main tunnel Banihal as part of the critical path allowed it to assess delay holistically rather than in isolation for each activity. This avoided duplication and ensured that extension of time reflected actual delays. The Court’s acceptance of this approach indicates that even where the contract does not expressly refer to the critical path, it may still be relied upon as a legitimate analytical tool, provided it is grounded in the contractual framework and evidence.About the author: Ronak Desai is a construction lawyer and heads International Construction Law Offices, Mumbai (ICLO). Email: rd@constructionlawoffices.com

Next Story
Infrastructure Urban

Panasonic Showcases Connected Display Solutions

Panasonic Life Solutions India showcased its integrated display, projection, broadcast and communication technologies at Panasonic Tech Summit 2026 in New Delhi. Hosted through its System Solutions Division, the two-day event highlighted connected technology solutions for education, healthcare, retail, transportation, corporate offices and entertainment.The summit, themed ‘Turning Technology into Value’, featured experience-led zones covering QSR, retail, transit, corporate offices, healthcare, education, security, projection, home theatre and professional displays. Panasonic also introduc..

Next Story
Infrastructure Transport

Kapsch to Deliver India’s First C-ITS Project

"Kapsch TrafficCom will deliver India’s first Cooperative Intelligent Transport Systems project on a key expressway near New Delhi. The project will be implemented with Superwave Communication And Infrasolution Limited to demonstrate how connected mobility can improve road safety and traffic efficiency.The pilot will use real-time connectivity and AI-enabled situational awareness to support road users, especially in high-risk areas such as temporary work zones. Drivers will receive alerts on roadworks, maintenance vehicles, hazardous locations, traffic queues and temporary virtual signage di..

Next Story
Infrastructure Urban

Eurobond Net Profit Rises 44 Per Cent

Euro Panel Products, the parent company of Eurobond, reported a 44.13 per cent year-on-year rise in net profit for FY25–26. The company’s revenue from operations grew 18.91 per cent to Rs 503.20 crore, compared to Rs 423.18 crore in the previous financial year.The company’s full-year EBITDA stood at Rs 56.67 crore, marking a 31.82 per cent increase. Profit after tax rose to Rs 26.56 crore, while net worth increased 20.15 per cent to Rs 160.07 crore. Earnings per share for the year stood at Rs 10.84.Divyam Rajesh Shah, Whole Time Director and CFO, Euro Panel Products, said the company’s..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

-->