+
Maharashtra Government to uplift the face of Dharavi
Equipment

Maharashtra Government to uplift the face of Dharavi

To fast-track the long-pending development of Dharavi, the Maharashtra Cabinet has approved the establishment of a special purpose vehicle (SPV) and decided to invite global tenders for the project. The SPV will have 80 per cent stake of the developer with the remaining under the government’s ownership.

The SPV is expected to make a master plan for Dharavi as well as execute the project. Elaborating on the same, SVR Srinivas, Chief Executive, Dharavi Redevelopment Project Authority (DRPA), says, “The SPV will be formed once the bid is finalised and it will be along with the government. Commencing a JV, the government and private companies will have an SPV, where the government will also be on the board of directors.”

Spread over 200 hectare, as many as 1,000 residents of Dharavi are eligible for a new house after redevelopment. The project to redevelop Asia’s largest slum was conceived in 2003 but failed to see the light of the day. Ever since, the project has been a topic of discussion. Although previous efforts to get developers on board have been unsuccessful (twice), the government aims to be an active participant and stakeholder in the proposed SPV. Calling the project a high-risk one, Srinivas adds, “The project requires huge investment, for which investors should be made comfortable. Also, there should be policy stability. Both were missing last time because it was left to developers and the project was more developer-driven. However, this time, there is a SPV where the government is a partner. With this, more investments are likely to come in, bringing in a fundamental shift.” He further assured policy stability.

At an expected cost of Rs 220 billion, the entire area is reportedly set for redevelopment with over 1 lakh structures to be constructed in seven years. As reported, the railways has agreed to give up 90 acre of its land in Matunga and Dadar for the project.

According to the previous plans, the slum was expected to be developed into five sectors. In 2012, the government had given the project to the Maharashtra Housing Area Development Authority (MHADA). However, as reported, there was not much progress since then, until the recently organised pre-bid meeting.

The pre-bid meeting, conducted by Dharavi Redevelopment Project that falls under the Slum Rehabilitation Authority, managed to gain considerable interest among realty developers and major contractors as around 20 entities and their JV partners reportedly attended the meet. The project will be awarded to the entity that bids above the base price of Rs 31.5 billion.

To fast-track the long-pending development of Dharavi, the Maharashtra Cabinet has approved the establishment of a special purpose vehicle (SPV) and decided to invite global tenders for the project. The SPV will have 80 per cent stake of the developer with the remaining under the government’s ownership. The SPV is expected to make a master plan for Dharavi as well as execute the project. Elaborating on the same, SVR Srinivas, Chief Executive, Dharavi Redevelopment Project Authority (DRPA), says, “The SPV will be formed once the bid is finalised and it will be along with the government. Commencing a JV, the government and private companies will have an SPV, where the government will also be on the board of directors.” Spread over 200 hectare, as many as 1,000 residents of Dharavi are eligible for a new house after redevelopment. The project to redevelop Asia’s largest slum was conceived in 2003 but failed to see the light of the day. Ever since, the project has been a topic of discussion. Although previous efforts to get developers on board have been unsuccessful (twice), the government aims to be an active participant and stakeholder in the proposed SPV. Calling the project a high-risk one, Srinivas adds, “The project requires huge investment, for which investors should be made comfortable. Also, there should be policy stability. Both were missing last time because it was left to developers and the project was more developer-driven. However, this time, there is a SPV where the government is a partner. With this, more investments are likely to come in, bringing in a fundamental shift.” He further assured policy stability. At an expected cost of Rs 220 billion, the entire area is reportedly set for redevelopment with over 1 lakh structures to be constructed in seven years. As reported, the railways has agreed to give up 90 acre of its land in Matunga and Dadar for the project. According to the previous plans, the slum was expected to be developed into five sectors. In 2012, the government had given the project to the Maharashtra Housing Area Development Authority (MHADA). However, as reported, there was not much progress since then, until the recently organised pre-bid meeting. The pre-bid meeting, conducted by Dharavi Redevelopment Project that falls under the Slum Rehabilitation Authority, managed to gain considerable interest among realty developers and major contractors as around 20 entities and their JV partners reportedly attended the meet. The project will be awarded to the entity that bids above the base price of Rs 31.5 billion.

Next Story
Infrastructure Transport

MMRDA Installs 325-Tonne Steel Spans on Mumbai Metro Line 4

The Mumbai Metropolitan Region Development Authority (MMRDA) has achieved a key construction milestone on Metro Line 4 with the successful installation of three large steel spans at Bhandup West during overnight operations.The spans, together weighing 325 metric tonnes, were launched using eight heavy-duty cranes and 12 multi-axle vehicles. The operation required precise engineering and meticulous planning to minimise disruption in the densely populated suburban area.Due to effective inter-agency coordination, the work—originally scheduled across four nights—was completed within just two n..

Next Story
Infrastructure Transport

CMRL Targets March 2027 Opening for Vadapalani–Panagal Park

Chennai Metro Rail Limited (CMRL) is progressing as scheduled to open the Vadapalani–Panagal Park section of Phase II’s Corridor 4 by March 2027. The 3.5 km underground stretch is part of the 26.1 km Corridor 4 connecting Lighthouse with Poonamallee Bypass.Construction activities are advancing steadily, with tunnelling works between Vadapalani and Panagal Park already completed. Track-laying operations are expected to commence shortly. At Panagal Park station, structural works have reached the concourse and platform levels, while excavation continues at the lowest level.CMRL is also consid..

Next Story
Infrastructure Transport

Maha-Metro Invites Pune Metro Civil Maintenance Bids

Maharashtra Metro Rail Corporation Limited (Maha-Metro) has invited bids for the annual civil maintenance contract of the Pune Metro Rail Project. The tender, bearing ID and number P1-O&M-20/2025, is scheduled to close on 23 February 2026, with a pre-bid meeting slated for 10 February 2026. The earnest money deposit (EMD) for the contract is Rs 3,50,500, and the duration of the contract is one year.The scope of work includes annual civil maintenance of 28 elevated and underground stations, 28.079 km of elevated viaduct including steel bridges, 12.15 km of tunnels, and two depots under the ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Open In App