+
 Developers in Maharashtra may get extension for lapsed projects
Real Estate

Developers in Maharashtra may get extension for lapsed projects

Developers are unable to get consent from 51% of the buyers to seek an extension to complete lapsed projects listed by the Maharashtra Real Estate Regulatory Authority (MahaRERA).

According to the latest orders, developers can seek a joint meeting with MahaRERA and the buyers to consider an extension with other conditions.

The authority lists 3,371 expired projects for which the promoters had not applied for an extension and not uploaded in Form 4, a certificate from the architect after completing the project. MahaRERA has a total of 30,668 registered projects, from which 7,214 projects are completed.

Vasant Prabhu, Secretary of MahaRERA, said that the developers of the lapsed projects should follow the procedure and then upload it in Form 4.

Chairman of Maharashtra Society Welfare Association (MSWA), Ramesh Prabhu, told the media that the authority is allowing the developers to complete their lapsed projects.

He said that the allottees must form an association and seek MahaRERA to take over the lapsed projects. They will have land possession by collecting the balance dues or contributing the required amount, so they will be able to complete the project.

Prabhu said that the association might sell unsold properties to release the funds required to complete the project. If the association has to spend more than agreed, the complaint to recover the extra with interest may be filed before MahaRERA, and it is possible to recover the amount.

An advocate of Bombay High Court, Manjunath Kakkalameli, said that a standard operating procedure (SOP) would work only for actual developers who want to complete their project and the authority may allow an extension to complete the lapsed project.

According to the order, if any promoter does not apply for an extension or does not respond, the developer can apply to the MahaRERA under Section 7 to get help.

Image Source


Also read: Delayed realty projects in India face procedural roadblocks now

Also read: First-sale property e-registrations in Maharashtra to begin from Oct

Developers are unable to get consent from 51% of the buyers to seek an extension to complete lapsed projects listed by the Maharashtra Real Estate Regulatory Authority (MahaRERA). According to the latest orders, developers can seek a joint meeting with MahaRERA and the buyers to consider an extension with other conditions. The authority lists 3,371 expired projects for which the promoters had not applied for an extension and not uploaded in Form 4, a certificate from the architect after completing the project. MahaRERA has a total of 30,668 registered projects, from which 7,214 projects are completed. Vasant Prabhu, Secretary of MahaRERA, said that the developers of the lapsed projects should follow the procedure and then upload it in Form 4. Chairman of Maharashtra Society Welfare Association (MSWA), Ramesh Prabhu, told the media that the authority is allowing the developers to complete their lapsed projects. He said that the allottees must form an association and seek MahaRERA to take over the lapsed projects. They will have land possession by collecting the balance dues or contributing the required amount, so they will be able to complete the project. Prabhu said that the association might sell unsold properties to release the funds required to complete the project. If the association has to spend more than agreed, the complaint to recover the extra with interest may be filed before MahaRERA, and it is possible to recover the amount. An advocate of Bombay High Court, Manjunath Kakkalameli, said that a standard operating procedure (SOP) would work only for actual developers who want to complete their project and the authority may allow an extension to complete the lapsed project. According to the order, if any promoter does not apply for an extension or does not respond, the developer can apply to the MahaRERA under Section 7 to get help. Image SourceAlso read: Delayed realty projects in India face procedural roadblocks now Also read: First-sale property e-registrations in Maharashtra to begin from Oct

Next Story
Infrastructure Transport

MMRDA Installs 325-Tonne Steel Spans on Mumbai Metro Line 4

The Mumbai Metropolitan Region Development Authority (MMRDA) has achieved a key construction milestone on Metro Line 4 with the successful installation of three large steel spans at Bhandup West during overnight operations.The spans, together weighing 325 metric tonnes, were launched using eight heavy-duty cranes and 12 multi-axle vehicles. The operation required precise engineering and meticulous planning to minimise disruption in the densely populated suburban area.Due to effective inter-agency coordination, the work—originally scheduled across four nights—was completed within just two n..

Next Story
Infrastructure Transport

CMRL Targets March 2027 Opening for Vadapalani–Panagal Park

Chennai Metro Rail Limited (CMRL) is progressing as scheduled to open the Vadapalani–Panagal Park section of Phase II’s Corridor 4 by March 2027. The 3.5 km underground stretch is part of the 26.1 km Corridor 4 connecting Lighthouse with Poonamallee Bypass.Construction activities are advancing steadily, with tunnelling works between Vadapalani and Panagal Park already completed. Track-laying operations are expected to commence shortly. At Panagal Park station, structural works have reached the concourse and platform levels, while excavation continues at the lowest level.CMRL is also consid..

Next Story
Infrastructure Transport

Maha-Metro Invites Pune Metro Civil Maintenance Bids

Maharashtra Metro Rail Corporation Limited (Maha-Metro) has invited bids for the annual civil maintenance contract of the Pune Metro Rail Project. The tender, bearing ID and number P1-O&M-20/2025, is scheduled to close on 23 February 2026, with a pre-bid meeting slated for 10 February 2026. The earnest money deposit (EMD) for the contract is Rs 3,50,500, and the duration of the contract is one year.The scope of work includes annual civil maintenance of 28 elevated and underground stations, 28.079 km of elevated viaduct including steel bridges, 12.15 km of tunnels, and two depots under the ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Open In App