About 483 infrastructure projects of Rs 150 cr each show cost overruns
ECONOMY & POLICY

About 483 infrastructure projects of Rs 150 cr each show cost overruns

483 infrastructure projects worth Rs 150 crore or more have cost overruns totalling more than Rs 4.43 lakh crore, according to a report.

Infrastructure projects worth more than Rs 150 crore are tracked by the Ministry of Statistics and Programme Implementation.

483 of the 1,781 projects had cost overruns, while 504 were delayed.

The total cost of these projects up to July 2021 was around Rs 13,22,515.87 crore, or 48.53% of the total cost estimate, according to the report.

However, if delays are calculated using the most recent completion schedule, the number of delayed projects drops to 369, according to the report.

Furthermore, neither the year of commissioning nor the estimated gestation period has been reported for 1,001 projects.

Out of the 504 projects that have been delayed, 92 have been delayed for 1 to 12 months, 118 have been delayed for 13 to 24 months, 178 have been delayed for 25 to 60 months, and 116 have been delayed for 61 months or more.

In these 504 delayed projects, the average time overrun is 46.85 months.

Delays in land acquisition, delays in obtaining forest and environmental clearances, and a lack of infrastructure support and linkages are among the reasons for time overruns, according to various project implementing agencies.

Other reasons include a delay in securing project financing, a delay in completing detailed engineering, a change in scope, a delay in tendering, ordering, and equipment supply, and law and order issues.

The report also cited state-by-state lockdowns caused by Covid-19 as a reason for the projects' delays.

Project agencies have also been observed not reporting revised cost estimates and commissioning schedules for many projects, implying that time or cost overrun figures are underreported.

Image Source


Also read: 470 infra projects show cost overruns worth Rs 4.38 lakh cr

483 infrastructure projects worth Rs 150 crore or more have cost overruns totalling more than Rs 4.43 lakh crore, according to a report. Infrastructure projects worth more than Rs 150 crore are tracked by the Ministry of Statistics and Programme Implementation. 483 of the 1,781 projects had cost overruns, while 504 were delayed. The total cost of these projects up to July 2021 was around Rs 13,22,515.87 crore, or 48.53% of the total cost estimate, according to the report. However, if delays are calculated using the most recent completion schedule, the number of delayed projects drops to 369, according to the report. Furthermore, neither the year of commissioning nor the estimated gestation period has been reported for 1,001 projects. Out of the 504 projects that have been delayed, 92 have been delayed for 1 to 12 months, 118 have been delayed for 13 to 24 months, 178 have been delayed for 25 to 60 months, and 116 have been delayed for 61 months or more. In these 504 delayed projects, the average time overrun is 46.85 months. Delays in land acquisition, delays in obtaining forest and environmental clearances, and a lack of infrastructure support and linkages are among the reasons for time overruns, according to various project implementing agencies. Other reasons include a delay in securing project financing, a delay in completing detailed engineering, a change in scope, a delay in tendering, ordering, and equipment supply, and law and order issues. The report also cited state-by-state lockdowns caused by Covid-19 as a reason for the projects' delays. Project agencies have also been observed not reporting revised cost estimates and commissioning schedules for many projects, implying that time or cost overrun figures are underreported. Image Source Also read: 470 infra projects show cost overruns worth Rs 4.38 lakh cr

Next Story
Infrastructure Transport

Metro Line 2B Phase 1 to Boost Realty in Mumbai’s Eastern Suburbs

Mumbai’s real estate sector is set for a major boost as Phase 1 of Metro Line 2B, between Mandale and Diamond Garden, nears completion. The Mumbai Metropolitan Region Development Authority (MMRDA) has confirmed that mandatory rectifications are done, and inspections by the Commissioner of Metro Railway Safety (CMRS) have been carried out. The 5.39-km stretch with five stations forms part of the larger DN Nagar–Mandale corridor, designed to ease congestion and improve east–west connectivity. Passenger operations are expected by December 2025, with the full line slated for 2027. ..

Next Story
Resources

WattPower wins Best Inverter award at Global Solar Expo 2025

WattPower, a leading renewable energy solutions provider, has won the award for “Best Inverter in the Utility Segment” at the Global Solar Expo 2025. The recognition underscores the company’s commitment to delivering reliable, high-performance and future-ready solar solutions for large-scale projects. At the forefront of utility-scale solar, WattPower manufactures advanced string inverters that directly feed power into the Indian grid. With robust technology, high-quality components and comprehensive product lifecycle support, its solutions stand among the most sophisticated in the ..

Next Story
Real Estate

Awfis delivers 67,000 sq. ft. innovation hub for eBay in Bengaluru

Awfis Space Solutions, India’s largest flexible workspace provider and the first publicly listed workspace solutions platform, has partnered with eBay to establish a 67,000 sq. ft. innovation hub at Embassy Tech Village, Bengaluru. The mandate covers design, build and management of the new office, which will act as a strategic hub supporting diverse functions and accelerating eBay’s AI-first commerce strategy. The centre will focus on artificial intelligence, engineering, product development and applied research, strengthening eBay’s growth in India. Embassy Tech Village, North Beng..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?