About 483 infrastructure projects of Rs 150 cr each show cost overruns
ECONOMY & POLICY

About 483 infrastructure projects of Rs 150 cr each show cost overruns

483 infrastructure projects worth Rs 150 crore or more have cost overruns totalling more than Rs 4.43 lakh crore, according to a report.

Infrastructure projects worth more than Rs 150 crore are tracked by the Ministry of Statistics and Programme Implementation.

483 of the 1,781 projects had cost overruns, while 504 were delayed.

The total cost of these projects up to July 2021 was around Rs 13,22,515.87 crore, or 48.53% of the total cost estimate, according to the report.

However, if delays are calculated using the most recent completion schedule, the number of delayed projects drops to 369, according to the report.

Furthermore, neither the year of commissioning nor the estimated gestation period has been reported for 1,001 projects.

Out of the 504 projects that have been delayed, 92 have been delayed for 1 to 12 months, 118 have been delayed for 13 to 24 months, 178 have been delayed for 25 to 60 months, and 116 have been delayed for 61 months or more.

In these 504 delayed projects, the average time overrun is 46.85 months.

Delays in land acquisition, delays in obtaining forest and environmental clearances, and a lack of infrastructure support and linkages are among the reasons for time overruns, according to various project implementing agencies.

Other reasons include a delay in securing project financing, a delay in completing detailed engineering, a change in scope, a delay in tendering, ordering, and equipment supply, and law and order issues.

The report also cited state-by-state lockdowns caused by Covid-19 as a reason for the projects' delays.

Project agencies have also been observed not reporting revised cost estimates and commissioning schedules for many projects, implying that time or cost overrun figures are underreported.

Image Source


Also read: 470 infra projects show cost overruns worth Rs 4.38 lakh cr

483 infrastructure projects worth Rs 150 crore or more have cost overruns totalling more than Rs 4.43 lakh crore, according to a report. Infrastructure projects worth more than Rs 150 crore are tracked by the Ministry of Statistics and Programme Implementation. 483 of the 1,781 projects had cost overruns, while 504 were delayed. The total cost of these projects up to July 2021 was around Rs 13,22,515.87 crore, or 48.53% of the total cost estimate, according to the report. However, if delays are calculated using the most recent completion schedule, the number of delayed projects drops to 369, according to the report. Furthermore, neither the year of commissioning nor the estimated gestation period has been reported for 1,001 projects. Out of the 504 projects that have been delayed, 92 have been delayed for 1 to 12 months, 118 have been delayed for 13 to 24 months, 178 have been delayed for 25 to 60 months, and 116 have been delayed for 61 months or more. In these 504 delayed projects, the average time overrun is 46.85 months. Delays in land acquisition, delays in obtaining forest and environmental clearances, and a lack of infrastructure support and linkages are among the reasons for time overruns, according to various project implementing agencies. Other reasons include a delay in securing project financing, a delay in completing detailed engineering, a change in scope, a delay in tendering, ordering, and equipment supply, and law and order issues. The report also cited state-by-state lockdowns caused by Covid-19 as a reason for the projects' delays. Project agencies have also been observed not reporting revised cost estimates and commissioning schedules for many projects, implying that time or cost overrun figures are underreported. Image Source Also read: 470 infra projects show cost overruns worth Rs 4.38 lakh cr

Related Stories

Gold Stories

Next Story
Resources

Schindler named among Forbes’ World’s Best Employers 2026

Schindler has been named among Forbes’ World’s Best Employers 2026, a global ranking recognising companies for their workplace environments.Compiled by Forbes in partnership with Statista, the ranking is based on independent employee feedback, including whether employees would recommend their organisation to friends and family.The company said the recognition reflected its focus on creating a workplace where employees can develop their expertise and build careers. ..

Next Story
Infrastructure Urban

India needs an export-execution mindset: Vishesh Jain

Interview with Vishesh Jain, Founder & CEO, EximpleWhat gaps in India’s global trade ecosystem led you to build Eximple, and what problem did you see businesses struggling with most?Eximple came out of a problem that all three founders had seen from different choke points in the trade ecosystem. India has millions of MSMEs and manufacturers, and many of them can make products that are genuinely competitive on quality. Yet only a small fraction is able to build meaningful international businesses. In our experience, the gap is usually not manufacturing capability; it is the ability to exe..

Next Story
Building Material

Nuvoco reports 13.5% revenue growth in Q2 FY27

Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code