About 483 infrastructure projects of Rs 150 cr each show cost overruns
ECONOMY & POLICY

About 483 infrastructure projects of Rs 150 cr each show cost overruns

483 infrastructure projects worth Rs 150 crore or more have cost overruns totalling more than Rs 4.43 lakh crore, according to a report.

Infrastructure projects worth more than Rs 150 crore are tracked by the Ministry of Statistics and Programme Implementation.

483 of the 1,781 projects had cost overruns, while 504 were delayed.

The total cost of these projects up to July 2021 was around Rs 13,22,515.87 crore, or 48.53% of the total cost estimate, according to the report.

However, if delays are calculated using the most recent completion schedule, the number of delayed projects drops to 369, according to the report.

Furthermore, neither the year of commissioning nor the estimated gestation period has been reported for 1,001 projects.

Out of the 504 projects that have been delayed, 92 have been delayed for 1 to 12 months, 118 have been delayed for 13 to 24 months, 178 have been delayed for 25 to 60 months, and 116 have been delayed for 61 months or more.

In these 504 delayed projects, the average time overrun is 46.85 months.

Delays in land acquisition, delays in obtaining forest and environmental clearances, and a lack of infrastructure support and linkages are among the reasons for time overruns, according to various project implementing agencies.

Other reasons include a delay in securing project financing, a delay in completing detailed engineering, a change in scope, a delay in tendering, ordering, and equipment supply, and law and order issues.

The report also cited state-by-state lockdowns caused by Covid-19 as a reason for the projects' delays.

Project agencies have also been observed not reporting revised cost estimates and commissioning schedules for many projects, implying that time or cost overrun figures are underreported.

Image Source


Also read: 470 infra projects show cost overruns worth Rs 4.38 lakh cr

483 infrastructure projects worth Rs 150 crore or more have cost overruns totalling more than Rs 4.43 lakh crore, according to a report. Infrastructure projects worth more than Rs 150 crore are tracked by the Ministry of Statistics and Programme Implementation. 483 of the 1,781 projects had cost overruns, while 504 were delayed. The total cost of these projects up to July 2021 was around Rs 13,22,515.87 crore, or 48.53% of the total cost estimate, according to the report. However, if delays are calculated using the most recent completion schedule, the number of delayed projects drops to 369, according to the report. Furthermore, neither the year of commissioning nor the estimated gestation period has been reported for 1,001 projects. Out of the 504 projects that have been delayed, 92 have been delayed for 1 to 12 months, 118 have been delayed for 13 to 24 months, 178 have been delayed for 25 to 60 months, and 116 have been delayed for 61 months or more. In these 504 delayed projects, the average time overrun is 46.85 months. Delays in land acquisition, delays in obtaining forest and environmental clearances, and a lack of infrastructure support and linkages are among the reasons for time overruns, according to various project implementing agencies. Other reasons include a delay in securing project financing, a delay in completing detailed engineering, a change in scope, a delay in tendering, ordering, and equipment supply, and law and order issues. The report also cited state-by-state lockdowns caused by Covid-19 as a reason for the projects' delays. Project agencies have also been observed not reporting revised cost estimates and commissioning schedules for many projects, implying that time or cost overrun figures are underreported. Image Source Also read: 470 infra projects show cost overruns worth Rs 4.38 lakh cr

Next Story
Resources

ULCCS Showcases Cooperative Model at UN Symposium

Uralungal Labour Contract Co-operative Society (ULCCS) showcased its community-led development model at the United Nations Headquarters in New York, where it participated as a panellist at the International Symposium on Cooperative Financial Institutions held on 28–29 May 2026.Jointly organised by the United Nations Department of Economic and Social Affairs (UN DESA), the International Cooperative Banking Association (ICBA), and the International Cooperative Alliance (ICA), the symposium was held under the theme ‘Fuelling Inclusive and Equitable Growth’ and brought together policymakers,..

Next Story
Infrastructure Transport

Delhi Airport to Finalise 20-Year Master Plan

Delhi International Airport Ltd (DIAL) is finalising a 20-year master plan to guide long term infrastructure and operational development at Indira Gandhi International Airport, an official said. The operator expects the plan to reflect changes in the airline industry, shifts in the competitive landscape and evolving infrastructure requirements across terminals, airside and support services. The official said the document is likely to be ready in the next two to two-and-a-half months as the operator moves through planning stages. The plan will be prepared after consultations with airport users ..

Next Story
Real Estate

Aadhar Housing Finance Targets Rs 500 bn AUM By FY29

Aadhar Housing Finance has set a target to raise its asset under management to Rs 500 billion (bn) by the end of FY29, aiming to achieve this over the next three financial years through an 18-20 per cent loan growth trajectory. The firm focuses on the low-income segment with a ticket size of less than Rs 1.5 million (mn) and has relied on that segment to drive expansion. The company closed FY26 with an AUM of Rs 305.71 bn, reflecting the expansion in recent years, and it reported a net profit rise of 22 per cent to Rs 11.08 bn. Management indicated that gross non-performing assets stood at 1.0..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement