About 483 infrastructure projects of Rs 150 cr each show cost overruns
ECONOMY & POLICY

About 483 infrastructure projects of Rs 150 cr each show cost overruns

483 infrastructure projects worth Rs 150 crore or more have cost overruns totalling more than Rs 4.43 lakh crore, according to a report.

Infrastructure projects worth more than Rs 150 crore are tracked by the Ministry of Statistics and Programme Implementation.

483 of the 1,781 projects had cost overruns, while 504 were delayed.

The total cost of these projects up to July 2021 was around Rs 13,22,515.87 crore, or 48.53% of the total cost estimate, according to the report.

However, if delays are calculated using the most recent completion schedule, the number of delayed projects drops to 369, according to the report.

Furthermore, neither the year of commissioning nor the estimated gestation period has been reported for 1,001 projects.

Out of the 504 projects that have been delayed, 92 have been delayed for 1 to 12 months, 118 have been delayed for 13 to 24 months, 178 have been delayed for 25 to 60 months, and 116 have been delayed for 61 months or more.

In these 504 delayed projects, the average time overrun is 46.85 months.

Delays in land acquisition, delays in obtaining forest and environmental clearances, and a lack of infrastructure support and linkages are among the reasons for time overruns, according to various project implementing agencies.

Other reasons include a delay in securing project financing, a delay in completing detailed engineering, a change in scope, a delay in tendering, ordering, and equipment supply, and law and order issues.

The report also cited state-by-state lockdowns caused by Covid-19 as a reason for the projects' delays.

Project agencies have also been observed not reporting revised cost estimates and commissioning schedules for many projects, implying that time or cost overrun figures are underreported.

Image Source


Also read: 470 infra projects show cost overruns worth Rs 4.38 lakh cr

483 infrastructure projects worth Rs 150 crore or more have cost overruns totalling more than Rs 4.43 lakh crore, according to a report. Infrastructure projects worth more than Rs 150 crore are tracked by the Ministry of Statistics and Programme Implementation. 483 of the 1,781 projects had cost overruns, while 504 were delayed. The total cost of these projects up to July 2021 was around Rs 13,22,515.87 crore, or 48.53% of the total cost estimate, according to the report. However, if delays are calculated using the most recent completion schedule, the number of delayed projects drops to 369, according to the report. Furthermore, neither the year of commissioning nor the estimated gestation period has been reported for 1,001 projects. Out of the 504 projects that have been delayed, 92 have been delayed for 1 to 12 months, 118 have been delayed for 13 to 24 months, 178 have been delayed for 25 to 60 months, and 116 have been delayed for 61 months or more. In these 504 delayed projects, the average time overrun is 46.85 months. Delays in land acquisition, delays in obtaining forest and environmental clearances, and a lack of infrastructure support and linkages are among the reasons for time overruns, according to various project implementing agencies. Other reasons include a delay in securing project financing, a delay in completing detailed engineering, a change in scope, a delay in tendering, ordering, and equipment supply, and law and order issues. The report also cited state-by-state lockdowns caused by Covid-19 as a reason for the projects' delays. Project agencies have also been observed not reporting revised cost estimates and commissioning schedules for many projects, implying that time or cost overrun figures are underreported. Image Source Also read: 470 infra projects show cost overruns worth Rs 4.38 lakh cr

Next Story
Infrastructure Urban

Implementation Status of Jal Jeevan Mission

Since August 2019 the Government has implemented Jal Jeevan Mission to provide assured potable water through household tap connections in rural India. At the start of the mission only 32.3 million (mn) rural households, representing 16.7 per cent, were reported to have tap water connections. States and union territories have reported that 125.8 mn additional rural households have since been provided with tap connections. As a result, of about 193.6 mn rural households roughly 158.2 mn, or 81.71 per cent, are reported to have tap water supply at home.\n\nThe State, district and village level st..

Next Story
Infrastructure Urban

Jal Jeevan Mission Reaches Eighty One Per Cent Rural Coverage

The Government reported substantial progress under the Jal Jeevan Mission, launched in August 2019 to provide tap water to every rural household. At launch only 32.3 million (mn) rural households had tap connections and states and Union territories reported provision of 125.8 mn additional households by March 2026. Consequently, out of about 193.6 mn rural households around 158.2 mn, or 81.71 per cent, are reported to have tap water at home. The Finance Minister announced extension of the mission until 2028 in the 2025-26 budget speech. The Swachh Bharat Mission Grameen, launched in October 20..

Next Story
Infrastructure Urban

Empowering Local Governance for Sustainable Rural Water Supply

The Ministry of Jal Shakti has aligned the Jal Jeevan Mission (JJM) with the 73rd Amendment to strengthen village level planning and community ownership of water supply. Gram Panchayats, village water and sanitation committees and Pani Samitis are to plan, implement, manage and maintain piped water systems, with gram sabha processes formalising handover and oversight. Implementation support agencies including non government organisations, community based organisations and self help groups have been empanelled to train local committees and promote women participation. Under JJM, the department ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement