About 483 infrastructure projects of Rs 150 cr each show cost overruns
ECONOMY & POLICY

About 483 infrastructure projects of Rs 150 cr each show cost overruns

483 infrastructure projects worth Rs 150 crore or more have cost overruns totalling more than Rs 4.43 lakh crore, according to a report.

Infrastructure projects worth more than Rs 150 crore are tracked by the Ministry of Statistics and Programme Implementation.

483 of the 1,781 projects had cost overruns, while 504 were delayed.

The total cost of these projects up to July 2021 was around Rs 13,22,515.87 crore, or 48.53% of the total cost estimate, according to the report.

However, if delays are calculated using the most recent completion schedule, the number of delayed projects drops to 369, according to the report.

Furthermore, neither the year of commissioning nor the estimated gestation period has been reported for 1,001 projects.

Out of the 504 projects that have been delayed, 92 have been delayed for 1 to 12 months, 118 have been delayed for 13 to 24 months, 178 have been delayed for 25 to 60 months, and 116 have been delayed for 61 months or more.

In these 504 delayed projects, the average time overrun is 46.85 months.

Delays in land acquisition, delays in obtaining forest and environmental clearances, and a lack of infrastructure support and linkages are among the reasons for time overruns, according to various project implementing agencies.

Other reasons include a delay in securing project financing, a delay in completing detailed engineering, a change in scope, a delay in tendering, ordering, and equipment supply, and law and order issues.

The report also cited state-by-state lockdowns caused by Covid-19 as a reason for the projects' delays.

Project agencies have also been observed not reporting revised cost estimates and commissioning schedules for many projects, implying that time or cost overrun figures are underreported.

Image Source


Also read: 470 infra projects show cost overruns worth Rs 4.38 lakh cr

483 infrastructure projects worth Rs 150 crore or more have cost overruns totalling more than Rs 4.43 lakh crore, according to a report. Infrastructure projects worth more than Rs 150 crore are tracked by the Ministry of Statistics and Programme Implementation. 483 of the 1,781 projects had cost overruns, while 504 were delayed. The total cost of these projects up to July 2021 was around Rs 13,22,515.87 crore, or 48.53% of the total cost estimate, according to the report. However, if delays are calculated using the most recent completion schedule, the number of delayed projects drops to 369, according to the report. Furthermore, neither the year of commissioning nor the estimated gestation period has been reported for 1,001 projects. Out of the 504 projects that have been delayed, 92 have been delayed for 1 to 12 months, 118 have been delayed for 13 to 24 months, 178 have been delayed for 25 to 60 months, and 116 have been delayed for 61 months or more. In these 504 delayed projects, the average time overrun is 46.85 months. Delays in land acquisition, delays in obtaining forest and environmental clearances, and a lack of infrastructure support and linkages are among the reasons for time overruns, according to various project implementing agencies. Other reasons include a delay in securing project financing, a delay in completing detailed engineering, a change in scope, a delay in tendering, ordering, and equipment supply, and law and order issues. The report also cited state-by-state lockdowns caused by Covid-19 as a reason for the projects' delays. Project agencies have also been observed not reporting revised cost estimates and commissioning schedules for many projects, implying that time or cost overrun figures are underreported. Image Source Also read: 470 infra projects show cost overruns worth Rs 4.38 lakh cr

Next Story
Infrastructure Urban

Designing Tomorrow: Amaravati’s Net Zero Landmark

Amaravati has achieved a defining landmark in India’s sustainable infrastructure journey with the inauguration of the APCRDA Project Office, the nation’s first government building to earn the IGBC Net Zero Energy Rating – Design Stage. Conceptualised by the Andhra Pradesh Capital Region Development Authority (APCRDA) and certified by the Indian Green Building Council (IGBC), the project exemplifies how governance, design and innovation can converge to deliver measurable environmental impact.A vision rooted in sustainabilitySet within a 4.3-acre site along the Seed Access Road in the Amar..

Next Story
Real Estate

Pidilite Elevates Construction with PPS

Pidilite Industries introduced Pidilite Professional Solutions (PPS) — a dedicated vertical for the construction and interiors ecosystem — at ACETECH Bengaluru 2025. Designed to empower architects, developers, contractors, and interior specialists, PPS delivers comprehensive support that extends far beyond products to ensure project excellence from concept to completion. Kavinder Singh, Joint Managing Director, Pidilite Industries, noted, “At Pidilite, we believe in enabling the construction fraternity to build boldly and sustainably. With Pidilite Professional Solutions (PPS),..

Next Story
Infrastructure Transport

Punjab, Centre Fast-Track Rajpura-Mohali Rail Line Development

The central government has fast-tracked the construction of the Rajpura-Mohali rail line to enhance connectivity in Punjab. This ambitious infrastructure project, aimed at improving transportation links between Rajpura and Mohali, has been identified as a key step in fostering regional economic growth. Union Minister for Railways, Ashwini Vaishnaw, announced the project’s acceleration during a recent assessment of the area. The rail line is expected to play a significant role in reducing travel time, promoting industrial growth, and boosting logistics efficiency in the region. The project,..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?