Infra projects show huge cost overruns
ECONOMY & POLICY

Infra projects show huge cost overruns

As per recent reports, 437 infrastructure projects, each worth Rs 1.50 billion or more have been adversely affected due to cost overruns, amounting to over Rs 4.37 trillion. Of 1,663 such projects, 531 projects witnessed time escalation, and 437 projects have reported cost overruns. Cost overrun quantum. The incurred expenditure on the projects stood at Rs 11.62 trillion till September, which was 45.60% of the expected cost.

All infrastructure projects worth Rs 1.50 billion and above are monitored by the Ministry of Statistics and Programme Implementation (MoSPI). The Ministry's latest report for September 2020 reported that the original cumulative cost for the 1,663 projects was Rs 21.09 trillion. However, the anticipated cost of completion of the projects is probably going to be Rs 25.47 trillion. The overall cost overruns indicated by this is of Rs 4.37 trillion, which is more than 20 per cent of the initially calculated cost.

However, the report said that if the delay is assessed based on the latest schedule of completion, the number of delayed projects reduces to 430.

The report also mentioned that neither the tentative gestation period nor the year of commissioning was reported for 924 projects.

Time overruns quantum. Of the 531 projects that have been delayed, 121 projects reflect a delay of 61 months and more; 160 projects show a delay of any duration between 25 to 60 months; 128 projects reflect a delay in the range of 13-24 months; while 122 projects show an overall delay from anywhere between 1-12 months. The average time overrun in all the 531 projects is 43.89 months.

Several project-implementing agencies reported various reasons for the time overruns. The reasons varied from delay in acquiring environment and forest clearances, a delay in acquisition of land or even a lack of linkages and infrastructural support.

The report mentioned tendering delays, delay in ordering and supplying of equipment, delay in finalisation of detailed engineering, delays in project financing tie-ups and issues with law and order as some of the other reasons.

The report also stated that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time and cost overrun figures are under-reported.

As per recent reports, 437 infrastructure projects, each worth Rs 1.50 billion or more have been adversely affected due to cost overruns, amounting to over Rs 4.37 trillion. Of 1,663 such projects, 531 projects witnessed time escalation, and 437 projects have reported cost overruns. Cost overrun quantum. The incurred expenditure on the projects stood at Rs 11.62 trillion till September, which was 45.60% of the expected cost. All infrastructure projects worth Rs 1.50 billion and above are monitored by the Ministry of Statistics and Programme Implementation (MoSPI). The Ministry's latest report for September 2020 reported that the original cumulative cost for the 1,663 projects was Rs 21.09 trillion. However, the anticipated cost of completion of the projects is probably going to be Rs 25.47 trillion. The overall cost overruns indicated by this is of Rs 4.37 trillion, which is more than 20 per cent of the initially calculated cost. However, the report said that if the delay is assessed based on the latest schedule of completion, the number of delayed projects reduces to 430. The report also mentioned that neither the tentative gestation period nor the year of commissioning was reported for 924 projects. Time overruns quantum. Of the 531 projects that have been delayed, 121 projects reflect a delay of 61 months and more; 160 projects show a delay of any duration between 25 to 60 months; 128 projects reflect a delay in the range of 13-24 months; while 122 projects show an overall delay from anywhere between 1-12 months. The average time overrun in all the 531 projects is 43.89 months. Several project-implementing agencies reported various reasons for the time overruns. The reasons varied from delay in acquiring environment and forest clearances, a delay in acquisition of land or even a lack of linkages and infrastructural support. The report mentioned tendering delays, delay in ordering and supplying of equipment, delay in finalisation of detailed engineering, delays in project financing tie-ups and issues with law and order as some of the other reasons. The report also stated that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time and cost overrun figures are under-reported.

Next Story
Products

TOTO India Launches Premium G & L Showers with Sleek Faucet Range

TOTO India has launched its G Shower and L Shower series, alongside an expanded range of GT, LH, and Pull-Out lavatory faucets. The collection blends advanced technology, refined aesthetics, and everyday comfort, staying true to TOTO’s philosophy of creating spaces that are both beautiful and functional. The G Shower series delivers the 3Rs of showering: Relaxing, Refreshing, and Revitalizing. Features include the Calming Shawl spray mode, Warm Spa technology, and multiple overhead and hand-shower options across eight finishes. The L Shower complements this with easy-to-use controls sui..

Next Story
Infrastructure Energy

Hero Future Energies Secures Funding for 120 MW Hybrid Project

Hero Future Energies (HFE), through its SPV Clean Renewable Energy Hybrid Three, has secured Rs 19.08 billion in funding from the State Bank of India (lead) and Canara Bank. The funds will be used to develop and construct HFE’s 120 MW renewable energy hybrid project at Kurnool, Andhra Pradesh. The project, contracted with SJVN, integrates wind, solar, and storage technologies to deliver reliable peak power. With a 21-year repayment period, the funding ensures timely execution and the commencement of commercial operations. The financial closure demonstrates continued lender confidence in..

Next Story
Infrastructure Energy

IOC GPS Renewables Raises Rs 8.36 billion Debt for Compressed Biogas Plants

IOC GPS Renewables Private Limited (IGRPL), a joint venture between IndianOil Corporation  and GPS Renewables, has raised Rs 8.36 billion (approx. US$ 95 million) in debt financing from Indian Bank to execute nine Compressed Biogas (CBG) projects across India.   The funding is the largest single-bank debt raise in the CBG sector and the first fully non-recourse financing in India for these projects. The plants—four in Haryana, three in Uttar Pradesh, one each in Chhattisgarh and Andhra Pradesh—will each produce 15 tonnes of CBG per day using paddy straw as feedstock. All nin..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?