Infra projects show huge cost overruns
ECONOMY & POLICY

Infra projects show huge cost overruns

As per recent reports, 437 infrastructure projects, each worth Rs 1.50 billion or more have been adversely affected due to cost overruns, amounting to over Rs 4.37 trillion. Of 1,663 such projects, 531 projects witnessed time escalation, and 437 projects have reported cost overruns. Cost overrun quantum. The incurred expenditure on the projects stood at Rs 11.62 trillion till September, which was 45.60% of the expected cost.

All infrastructure projects worth Rs 1.50 billion and above are monitored by the Ministry of Statistics and Programme Implementation (MoSPI). The Ministry's latest report for September 2020 reported that the original cumulative cost for the 1,663 projects was Rs 21.09 trillion. However, the anticipated cost of completion of the projects is probably going to be Rs 25.47 trillion. The overall cost overruns indicated by this is of Rs 4.37 trillion, which is more than 20 per cent of the initially calculated cost.

However, the report said that if the delay is assessed based on the latest schedule of completion, the number of delayed projects reduces to 430.

The report also mentioned that neither the tentative gestation period nor the year of commissioning was reported for 924 projects.

Time overruns quantum. Of the 531 projects that have been delayed, 121 projects reflect a delay of 61 months and more; 160 projects show a delay of any duration between 25 to 60 months; 128 projects reflect a delay in the range of 13-24 months; while 122 projects show an overall delay from anywhere between 1-12 months. The average time overrun in all the 531 projects is 43.89 months.

Several project-implementing agencies reported various reasons for the time overruns. The reasons varied from delay in acquiring environment and forest clearances, a delay in acquisition of land or even a lack of linkages and infrastructural support.

The report mentioned tendering delays, delay in ordering and supplying of equipment, delay in finalisation of detailed engineering, delays in project financing tie-ups and issues with law and order as some of the other reasons.

The report also stated that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time and cost overrun figures are under-reported.

As per recent reports, 437 infrastructure projects, each worth Rs 1.50 billion or more have been adversely affected due to cost overruns, amounting to over Rs 4.37 trillion. Of 1,663 such projects, 531 projects witnessed time escalation, and 437 projects have reported cost overruns. Cost overrun quantum. The incurred expenditure on the projects stood at Rs 11.62 trillion till September, which was 45.60% of the expected cost. All infrastructure projects worth Rs 1.50 billion and above are monitored by the Ministry of Statistics and Programme Implementation (MoSPI). The Ministry's latest report for September 2020 reported that the original cumulative cost for the 1,663 projects was Rs 21.09 trillion. However, the anticipated cost of completion of the projects is probably going to be Rs 25.47 trillion. The overall cost overruns indicated by this is of Rs 4.37 trillion, which is more than 20 per cent of the initially calculated cost. However, the report said that if the delay is assessed based on the latest schedule of completion, the number of delayed projects reduces to 430. The report also mentioned that neither the tentative gestation period nor the year of commissioning was reported for 924 projects. Time overruns quantum. Of the 531 projects that have been delayed, 121 projects reflect a delay of 61 months and more; 160 projects show a delay of any duration between 25 to 60 months; 128 projects reflect a delay in the range of 13-24 months; while 122 projects show an overall delay from anywhere between 1-12 months. The average time overrun in all the 531 projects is 43.89 months. Several project-implementing agencies reported various reasons for the time overruns. The reasons varied from delay in acquiring environment and forest clearances, a delay in acquisition of land or even a lack of linkages and infrastructural support. The report mentioned tendering delays, delay in ordering and supplying of equipment, delay in finalisation of detailed engineering, delays in project financing tie-ups and issues with law and order as some of the other reasons. The report also stated that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time and cost overrun figures are under-reported.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

Autodesk Elevates Nikhil Bagalkotkar to Lead AEC in India, SAARC

Autodesk has elevated Nikhil Bagalkotkar as Head – Architecture, Engineering and Construction (AEC), India and SAARC, with immediate effect.In his new role, Bagalkotkar will lead Autodesk's AEC business strategy across the region and drive adoption of the company's Design and Make platform. He will also focus on promoting digital design and construction technologies to help customers accelerate innovation and deliver more sustainable and resilient infrastructure.Bagalkotkar will be responsible for expanding Autodesk's AEC business, strengthening customer and partner engagement, and accelerat..

Next Story
Real Estate

Listed Developers' Pre-Sales Seen Rising 22.3 Per Cent in FY27

India's leading listed residential developers are expected to sustain strong sales momentum in FY27, with combined pre-sales of 11 major players projected to rise 22.3 per cent year-on-year, according to an analysis by ANAROCK Research & Advisory.Combined pre-sales of the developers are estimated to increase from Rs 1.49 trillion in FY26 to Rs 1.82 lakh crore in FY27. ANAROCK attributed the growth to sustained end-user demand, new project launches and strong execution despite higher property prices, construction costs and global uncertainties.Dr Prashant Thakur, Executive Director and Head..

Next Story
Infrastructure Urban

Balu Forge Q1 FY27 Profit Rises 15.9 Per Cent to Rs 661 Mn

Balu Forge Industries Ltd (BFIL) reported a 29 per cent year-on-year increase in revenue from operations to Rs 3,007 million for the quarter ended June 30, 2026, compared with Rs 2,332 million in Q1 FY26.The precision engineering and manufacturing company recorded EBITDA of Rs 848 million, up 17.3 per cent from Rs 723 million in the corresponding quarter last year. EBITDA margin stood at 28.2 per cent, compared with 31 per cent in Q1 FY26.Profit after tax increased 15.9 per cent YoY to Rs 661 million from Rs 570 million, while PAT margin stood at 21.7 per cent. Earnings per share rose 8.9 per ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement