Infra projects show huge cost overruns
ECONOMY & POLICY

Infra projects show huge cost overruns

As per recent reports, 437 infrastructure projects, each worth Rs 1.50 billion or more have been adversely affected due to cost overruns, amounting to over Rs 4.37 trillion. Of 1,663 such projects, 531 projects witnessed time escalation, and 437 projects have reported cost overruns. Cost overrun quantum. The incurred expenditure on the projects stood at Rs 11.62 trillion till September, which was 45.60% of the expected cost.

All infrastructure projects worth Rs 1.50 billion and above are monitored by the Ministry of Statistics and Programme Implementation (MoSPI). The Ministry's latest report for September 2020 reported that the original cumulative cost for the 1,663 projects was Rs 21.09 trillion. However, the anticipated cost of completion of the projects is probably going to be Rs 25.47 trillion. The overall cost overruns indicated by this is of Rs 4.37 trillion, which is more than 20 per cent of the initially calculated cost.

However, the report said that if the delay is assessed based on the latest schedule of completion, the number of delayed projects reduces to 430.

The report also mentioned that neither the tentative gestation period nor the year of commissioning was reported for 924 projects.

Time overruns quantum. Of the 531 projects that have been delayed, 121 projects reflect a delay of 61 months and more; 160 projects show a delay of any duration between 25 to 60 months; 128 projects reflect a delay in the range of 13-24 months; while 122 projects show an overall delay from anywhere between 1-12 months. The average time overrun in all the 531 projects is 43.89 months.

Several project-implementing agencies reported various reasons for the time overruns. The reasons varied from delay in acquiring environment and forest clearances, a delay in acquisition of land or even a lack of linkages and infrastructural support.

The report mentioned tendering delays, delay in ordering and supplying of equipment, delay in finalisation of detailed engineering, delays in project financing tie-ups and issues with law and order as some of the other reasons.

The report also stated that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time and cost overrun figures are under-reported.

As per recent reports, 437 infrastructure projects, each worth Rs 1.50 billion or more have been adversely affected due to cost overruns, amounting to over Rs 4.37 trillion. Of 1,663 such projects, 531 projects witnessed time escalation, and 437 projects have reported cost overruns. Cost overrun quantum. The incurred expenditure on the projects stood at Rs 11.62 trillion till September, which was 45.60% of the expected cost. All infrastructure projects worth Rs 1.50 billion and above are monitored by the Ministry of Statistics and Programme Implementation (MoSPI). The Ministry's latest report for September 2020 reported that the original cumulative cost for the 1,663 projects was Rs 21.09 trillion. However, the anticipated cost of completion of the projects is probably going to be Rs 25.47 trillion. The overall cost overruns indicated by this is of Rs 4.37 trillion, which is more than 20 per cent of the initially calculated cost. However, the report said that if the delay is assessed based on the latest schedule of completion, the number of delayed projects reduces to 430. The report also mentioned that neither the tentative gestation period nor the year of commissioning was reported for 924 projects. Time overruns quantum. Of the 531 projects that have been delayed, 121 projects reflect a delay of 61 months and more; 160 projects show a delay of any duration between 25 to 60 months; 128 projects reflect a delay in the range of 13-24 months; while 122 projects show an overall delay from anywhere between 1-12 months. The average time overrun in all the 531 projects is 43.89 months. Several project-implementing agencies reported various reasons for the time overruns. The reasons varied from delay in acquiring environment and forest clearances, a delay in acquisition of land or even a lack of linkages and infrastructural support. The report mentioned tendering delays, delay in ordering and supplying of equipment, delay in finalisation of detailed engineering, delays in project financing tie-ups and issues with law and order as some of the other reasons. The report also stated that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time and cost overrun figures are under-reported.

Next Story
Real Estate

Indian REITs Offer 6-7.5 per cent Yield, Surpassing Many Global Markets

Indian Real Estate Investment Trusts (REITs) are delivering average yields of 6–7.5 per cent for unitholders, outperforming many mature markets, including the US, according to a report by Credai and Anarock.Credai, the apex body of Indian real estate developers, and property consultant Anarock released the report Indian REITs – A Gateway to Institutional Real Estate at an event in India.Currently, India has five listed REITs – Brookfield India Real Estate Trust, Embassy Office Parks REIT, Mindspace Business Parks REIT, Nexus Select Trust, and Knowledge Realty Trust. Nexus Select Trust pr..

Next Story
Infrastructure Energy

Insolation Energy Wins 226 MW Solar Projects Under PM-KUSUM

Insolation Energy on Monday announced securing multiple solar projects totalling 226.45 MW, with an investment of Rs 7.5 billion, under the PM-KUSUM scheme. The orders were awarded to its wholly-owned subsidiary, Insolation Green Energy Pvt Ltd, by Jaipur Vidyut Vitran Nigam Limited for 20 sites and Ajmer Vidyut Vitran Nigam Limited for 115 sites, the company informed the exchanges.“The combined SPV solar power plants will total 226.45 MW under PM-KUSUM Component A, with the final levelised tariff at Rs 3.04 per unit for 16 sites, Rs 2.82 per unit for 5 sites, Rs 2.75 per unit for 53 sites, ..

Next Story
Infrastructure Energy

Numaligarh Refinery Awards EPC Contract for Rooftop Solar Projects

State-owned Numaligarh Refinery Ltd. (NRL) has awarded a Letter of Award to Solarium Green Energy Ltd. for the rate contract covering the Engineering, Procurement, and Construction (EPC) of grid-connected rooftop solar PV projects at various locations. The projects fall within the categories of 51–200 kW and 201–1000 kW. Notable projects include a 140 kW rooftop solar plant at NRL Assam, a 760 kW plant at NRL Assam, and a 280 kW plant at NRL West Bengal.The supply order covers ex-manufacturing works and the dispatch price for plant and equipment for the 140 kW, 760 kW, and 280 kW rooftop s..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?