+
 Infra projects show huge cost overruns
ECONOMY & POLICY

Infra projects show huge cost overruns

As per recent reports, 437 infrastructure projects, each worth Rs 1.50 billion or more have been adversely affected due to cost overruns, amounting to over Rs 4.37 trillion. Of 1,663 such projects, 531 projects witnessed time escalation, and 437 projects have reported cost overruns. Cost overrun quantum. The incurred expenditure on the projects stood at Rs 11.62 trillion till September, which was 45.60% of the expected cost.

All infrastructure projects worth Rs 1.50 billion and above are monitored by the Ministry of Statistics and Programme Implementation (MoSPI). The Ministry's latest report for September 2020 reported that the original cumulative cost for the 1,663 projects was Rs 21.09 trillion. However, the anticipated cost of completion of the projects is probably going to be Rs 25.47 trillion. The overall cost overruns indicated by this is of Rs 4.37 trillion, which is more than 20 per cent of the initially calculated cost.

However, the report said that if the delay is assessed based on the latest schedule of completion, the number of delayed projects reduces to 430.

The report also mentioned that neither the tentative gestation period nor the year of commissioning was reported for 924 projects.

Time overruns quantum. Of the 531 projects that have been delayed, 121 projects reflect a delay of 61 months and more; 160 projects show a delay of any duration between 25 to 60 months; 128 projects reflect a delay in the range of 13-24 months; while 122 projects show an overall delay from anywhere between 1-12 months. The average time overrun in all the 531 projects is 43.89 months.

Several project-implementing agencies reported various reasons for the time overruns. The reasons varied from delay in acquiring environment and forest clearances, a delay in acquisition of land or even a lack of linkages and infrastructural support.

The report mentioned tendering delays, delay in ordering and supplying of equipment, delay in finalisation of detailed engineering, delays in project financing tie-ups and issues with law and order as some of the other reasons.

The report also stated that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time and cost overrun figures are under-reported.

As per recent reports, 437 infrastructure projects, each worth Rs 1.50 billion or more have been adversely affected due to cost overruns, amounting to over Rs 4.37 trillion. Of 1,663 such projects, 531 projects witnessed time escalation, and 437 projects have reported cost overruns. Cost overrun quantum. The incurred expenditure on the projects stood at Rs 11.62 trillion till September, which was 45.60% of the expected cost. All infrastructure projects worth Rs 1.50 billion and above are monitored by the Ministry of Statistics and Programme Implementation (MoSPI). The Ministry's latest report for September 2020 reported that the original cumulative cost for the 1,663 projects was Rs 21.09 trillion. However, the anticipated cost of completion of the projects is probably going to be Rs 25.47 trillion. The overall cost overruns indicated by this is of Rs 4.37 trillion, which is more than 20 per cent of the initially calculated cost. However, the report said that if the delay is assessed based on the latest schedule of completion, the number of delayed projects reduces to 430. The report also mentioned that neither the tentative gestation period nor the year of commissioning was reported for 924 projects. Time overruns quantum. Of the 531 projects that have been delayed, 121 projects reflect a delay of 61 months and more; 160 projects show a delay of any duration between 25 to 60 months; 128 projects reflect a delay in the range of 13-24 months; while 122 projects show an overall delay from anywhere between 1-12 months. The average time overrun in all the 531 projects is 43.89 months. Several project-implementing agencies reported various reasons for the time overruns. The reasons varied from delay in acquiring environment and forest clearances, a delay in acquisition of land or even a lack of linkages and infrastructural support. The report mentioned tendering delays, delay in ordering and supplying of equipment, delay in finalisation of detailed engineering, delays in project financing tie-ups and issues with law and order as some of the other reasons. The report also stated that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time and cost overrun figures are under-reported.

Related Stories

Gold Stories

Next Story
Real Estate

Kamdhenu Realities acquires 4-acre Navi Mumbai land parcel

Kamdhenu Realities has acquired a 4-acre land parcel from RPG Life Sciences on Thane-Belapur Road for approximately Rs 1.5 billion, expanding its commercial real estate portfolio in Navi Mumbai.The parcel has a total developable potential of 1.8 million sq ft, on which Kamdhenu plans to develop a destination-scale commercial and lifestyle ecosystem. The proposed development will combine corporate office suites with high-street retail, F&B outlets, double-height lobbies, business infrastructure and lifestyle amenities.Located close to IKEA and opposite the upcoming Pawane Railway Station, t..

Next Story
Infrastructure Transport

97 Per Cent Of Rongjeng-Mangsang-Adokgre Road Nears Completion

Deputy Chief Minister in-charge of public works Prestone Tynsong said in Shillong on 26 August that 97 per cent physical progress had been achieved on the ongoing Rongjeng-Mangsang-Adokgre road being constructed under the Non-Lapsable Central Pool of Resources (NLCPR). He noted the project was sanctioned in 2017 and that the stipulated time for completion had been 24 months from issue of the final work order. The deputy chief minister informed the assembly that the government had decided to include the remaining work under a World Bank project. In reply to a query from Rongjeng MLA Jim M Sangm..

Next Story
Infrastructure Transport

First TBM Starts Digging Five Point Three Kilometre Tunnel Under SGNP

The Goregaon-Mulund Link Road (GMLR) Phase three (B) project has reached a key milestone as the first tunnel boring machine (TBM) began excavation of the first of two tunnels beneath the Sanjay Gandhi National Park (SGNP). The machine, named Tulsi, started cutting a five point three kilometre bore that will link Dadasaheb Phalke Chitranagari in Goregaon East with Amar Nagar in Mulund West. Officials issued a statement noting the commencement of tunnelling work under the protected green belt. The twin tunnels are being constructed using mechanised tunnelling methods that aim to limit surface di..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code