Infra projects show huge cost overruns
ECONOMY & POLICY

Infra projects show huge cost overruns

As per recent reports, 437 infrastructure projects, each worth Rs 1.50 billion or more have been adversely affected due to cost overruns, amounting to over Rs 4.37 trillion. Of 1,663 such projects, 531 projects witnessed time escalation, and 437 projects have reported cost overruns. Cost overrun quantum. The incurred expenditure on the projects stood at Rs 11.62 trillion till September, which was 45.60% of the expected cost.

All infrastructure projects worth Rs 1.50 billion and above are monitored by the Ministry of Statistics and Programme Implementation (MoSPI). The Ministry's latest report for September 2020 reported that the original cumulative cost for the 1,663 projects was Rs 21.09 trillion. However, the anticipated cost of completion of the projects is probably going to be Rs 25.47 trillion. The overall cost overruns indicated by this is of Rs 4.37 trillion, which is more than 20 per cent of the initially calculated cost.

However, the report said that if the delay is assessed based on the latest schedule of completion, the number of delayed projects reduces to 430.

The report also mentioned that neither the tentative gestation period nor the year of commissioning was reported for 924 projects.

Time overruns quantum. Of the 531 projects that have been delayed, 121 projects reflect a delay of 61 months and more; 160 projects show a delay of any duration between 25 to 60 months; 128 projects reflect a delay in the range of 13-24 months; while 122 projects show an overall delay from anywhere between 1-12 months. The average time overrun in all the 531 projects is 43.89 months.

Several project-implementing agencies reported various reasons for the time overruns. The reasons varied from delay in acquiring environment and forest clearances, a delay in acquisition of land or even a lack of linkages and infrastructural support.

The report mentioned tendering delays, delay in ordering and supplying of equipment, delay in finalisation of detailed engineering, delays in project financing tie-ups and issues with law and order as some of the other reasons.

The report also stated that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time and cost overrun figures are under-reported.

As per recent reports, 437 infrastructure projects, each worth Rs 1.50 billion or more have been adversely affected due to cost overruns, amounting to over Rs 4.37 trillion. Of 1,663 such projects, 531 projects witnessed time escalation, and 437 projects have reported cost overruns. Cost overrun quantum. The incurred expenditure on the projects stood at Rs 11.62 trillion till September, which was 45.60% of the expected cost. All infrastructure projects worth Rs 1.50 billion and above are monitored by the Ministry of Statistics and Programme Implementation (MoSPI). The Ministry's latest report for September 2020 reported that the original cumulative cost for the 1,663 projects was Rs 21.09 trillion. However, the anticipated cost of completion of the projects is probably going to be Rs 25.47 trillion. The overall cost overruns indicated by this is of Rs 4.37 trillion, which is more than 20 per cent of the initially calculated cost. However, the report said that if the delay is assessed based on the latest schedule of completion, the number of delayed projects reduces to 430. The report also mentioned that neither the tentative gestation period nor the year of commissioning was reported for 924 projects. Time overruns quantum. Of the 531 projects that have been delayed, 121 projects reflect a delay of 61 months and more; 160 projects show a delay of any duration between 25 to 60 months; 128 projects reflect a delay in the range of 13-24 months; while 122 projects show an overall delay from anywhere between 1-12 months. The average time overrun in all the 531 projects is 43.89 months. Several project-implementing agencies reported various reasons for the time overruns. The reasons varied from delay in acquiring environment and forest clearances, a delay in acquisition of land or even a lack of linkages and infrastructural support. The report mentioned tendering delays, delay in ordering and supplying of equipment, delay in finalisation of detailed engineering, delays in project financing tie-ups and issues with law and order as some of the other reasons. The report also stated that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time and cost overrun figures are under-reported.

Next Story
Infrastructure Urban

India Spent Rs 1.5 Tn on Smart Cities in Past 10 Years

The Indian government launched the Smart Cities Mission on June 15, 2015, with the goal of transforming urban infrastructure across the country. As of April 11, 2025, ten years since its inception, over Rs 1.5 trillion has been spent on 7,504 completed projects, representing 94 per cent of the total planned projects valued at more than Rs 1.64 trillion. An additional Rs 131.42 billion worth of projects are currently under implementation. According to data from SBI Research, 92 per cent of the funds were utilised across 21 major states, with Uttar Pradesh, Tamil Nadu, and Maharashtra together ..

Next Story
Infrastructure Energy

Hyundai’s EcoGram Converts Gurugram’s Waste to Clean Energy

Hyundai’s EcoGram, a biogas plant and material recovery facility located in Gurugram, Haryana, has been established to support circular economy initiatives. The facility collects both wet and dry waste from 20 bulk waste generators, including residential welfare associations (RWAs), corporate offices, and commercial complexes, with assistance from the Municipal Corporation of Gurugram (MCG). At the facility, the collected waste undergoes processing—wet waste is converted into biogas, which is then used to generate electricity, while dry waste is sorted for recycling. Since its inception,..

Next Story
Infrastructure Transport

Metro Line 8 DPR Nears Completion; CIDCO to Float Rs 200 Bn Tenders

The City and Industrial Development Corporation (CIDCO) is nearing completion of the Detailed Project Report (DPR) for Metro Line 8, commonly known as the Gold Line. This strategic 34.9-kilometre corridor is set to link Mumbai’s Chhatrapati Shivaji Maharaj International Airport (CSMIA) with the upcoming Navi Mumbai International Airport (NMIA). Estimated to cost around Rs 200 billion, the project is being developed under the Public-Private Partnership (PPP) model. Once completed, Metro Line 8 will become Mumbai's second such corridor after Metro Line 1. CIDCO plans to float tenders once ..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?