373 projects show cost overruns of Rs 3.89 trillion
ECONOMY & POLICY

373 projects show cost overruns of Rs 3.89 trillion

The Ministry of Statistics and Programme Implementation (MoSPI), charged with the responsibility of monitoring infrastructure projects worth Rs 1.5 billion or more, has released a report for August 2019, according to which, out of a total 1,634 projects, around 373 have shown cost overruns to the tune of Rs 3.89 trillion.

The report states that the original estimated cost of all the projects is approximately Rs 19.40 trillion. Completion cost is now expected to be around Rs 23.29 trillion. This amounts to cost overruns of around 20.05 per cent from the original cost – of around Rs 3.89 trillion. Till August 2019, the expenses incurred by these projects amounts to Rs 9.75 trillion, which is 41.85 per cent of the expected cost of the projects.

Additionally, the report included the number of projects that had crossed their deadlines; these amounted to 552. The average time overrun for all 552 projects was reported to be 38.89 months.

Reportedly, out of all the 552 projects showing time overruns, 181 projects are showing an overall delay in the range of 1 to 12 months, 128 projects have delay of 13 to 24 months, 127 projects show delay in the range of 25 to 60 months and 116 projects reflect delay of 61 months and above. However, as per the report, the number of delayed projects decreases to 489 if the delay is calculated on the basis of latest schedule of completion. Moreover, for 687 projects neither the year of commissioning nor the tentative gestation period has been reported.

Escalations in time could be caused by issues relating to obtaining forest clearances, acquiring required land and supply of equipment. According to the report, developers also face additional constraints because of funding, geographical conditions, labour issues and court cases, among other reasons. Reportedly, it is possible that the time and cost overrun figures have been under-reported since project agencies have not reported revised cost estimates and commissioning schedules for numerous projects.

The Ministry of Statistics and Programme Implementation (MoSPI), charged with the responsibility of monitoring infrastructure projects worth Rs 1.5 billion or more, has released a report for August 2019, according to which, out of a total 1,634 projects, around 373 have shown cost overruns to the tune of Rs 3.89 trillion. The report states that the original estimated cost of all the projects is approximately Rs 19.40 trillion. Completion cost is now expected to be around Rs 23.29 trillion. This amounts to cost overruns of around 20.05 per cent from the original cost – of around Rs 3.89 trillion. Till August 2019, the expenses incurred by these projects amounts to Rs 9.75 trillion, which is 41.85 per cent of the expected cost of the projects. Additionally, the report included the number of projects that had crossed their deadlines; these amounted to 552. The average time overrun for all 552 projects was reported to be 38.89 months. Reportedly, out of all the 552 projects showing time overruns, 181 projects are showing an overall delay in the range of 1 to 12 months, 128 projects have delay of 13 to 24 months, 127 projects show delay in the range of 25 to 60 months and 116 projects reflect delay of 61 months and above. However, as per the report, the number of delayed projects decreases to 489 if the delay is calculated on the basis of latest schedule of completion. Moreover, for 687 projects neither the year of commissioning nor the tentative gestation period has been reported. Escalations in time could be caused by issues relating to obtaining forest clearances, acquiring required land and supply of equipment. According to the report, developers also face additional constraints because of funding, geographical conditions, labour issues and court cases, among other reasons. Reportedly, it is possible that the time and cost overrun figures have been under-reported since project agencies have not reported revised cost estimates and commissioning schedules for numerous projects.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

India’s Global CE Connect

India’s construction equipment industry is entering a phase where scale is increasingly being matched by productivity, technology, localisation and lifecycle economics. Against this backdrop, bauma ConExpo India 2026, scheduled for September 15-18 at the India Expo Centre, Greater Noida, will bring the global and Indian construction machinery ecosystem together.The eighth edition is expected to be the largest yet, with the exhibition sold out across around 1.45 million sq ft. More than 1,100 exhibitors from over 100 countries are expected to participate, with visitor numbers projected to exc..

Next Story
Real Estate

Orris, Godrej Properties Settle Dispute Over Gurugram Project

Orris Infrastructure and Godrej Properties Limited have reached an amicable settlement over matters related to the jointly developed Godrej Air project in Gurugram, bringing an end to the dispute between the two companies.The Bombay High Court, while hearing a petition filed by Orris Infrastructure, ordered the immediate and unconditional release of Orris Managing Director Amit Gupta on August 25, 2026, after being informed about the settlement agreement between the parties.A single-judge bench led by Justice Milind N. Jadhav noted that in view of the settlement agreement signed by both compan..

Next Story
Infrastructure Urban

Panasonic Launches Second Cycle of Startup Co-Creation Programme

Panasonic Life Solutions India (PLSIND), through its IGNITION Open Innovation platform, has announced the second cycle of Co.lab Studio, a startup collaboration initiative focused on developing scalable digital services and solutions.The new cycle will focus on Safety & Security and Daily Living solutions for communities by leveraging Panasonic’s AI and IoT-enabled connected living platform, MirAIe. The programme aims to help startups move from innovation concepts to pilot deployments, platform integrations and commercialisation-ready solutions.The first cycle of Co.lab Studio received 1..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code