373 projects show cost overruns of Rs 3.89 trillion
ECONOMY & POLICY

373 projects show cost overruns of Rs 3.89 trillion

The Ministry of Statistics and Programme Implementation (MoSPI), charged with the responsibility of monitoring infrastructure projects worth Rs 1.5 billion or more, has released a report for August 2019, according to which, out of a total 1,634 projects, around 373 have shown cost overruns to the tune of Rs 3.89 trillion.

The report states that the original estimated cost of all the projects is approximately Rs 19.40 trillion. Completion cost is now expected to be around Rs 23.29 trillion. This amounts to cost overruns of around 20.05 per cent from the original cost – of around Rs 3.89 trillion. Till August 2019, the expenses incurred by these projects amounts to Rs 9.75 trillion, which is 41.85 per cent of the expected cost of the projects.

Additionally, the report included the number of projects that had crossed their deadlines; these amounted to 552. The average time overrun for all 552 projects was reported to be 38.89 months.

Reportedly, out of all the 552 projects showing time overruns, 181 projects are showing an overall delay in the range of 1 to 12 months, 128 projects have delay of 13 to 24 months, 127 projects show delay in the range of 25 to 60 months and 116 projects reflect delay of 61 months and above. However, as per the report, the number of delayed projects decreases to 489 if the delay is calculated on the basis of latest schedule of completion. Moreover, for 687 projects neither the year of commissioning nor the tentative gestation period has been reported.

Escalations in time could be caused by issues relating to obtaining forest clearances, acquiring required land and supply of equipment. According to the report, developers also face additional constraints because of funding, geographical conditions, labour issues and court cases, among other reasons. Reportedly, it is possible that the time and cost overrun figures have been under-reported since project agencies have not reported revised cost estimates and commissioning schedules for numerous projects.

The Ministry of Statistics and Programme Implementation (MoSPI), charged with the responsibility of monitoring infrastructure projects worth Rs 1.5 billion or more, has released a report for August 2019, according to which, out of a total 1,634 projects, around 373 have shown cost overruns to the tune of Rs 3.89 trillion. The report states that the original estimated cost of all the projects is approximately Rs 19.40 trillion. Completion cost is now expected to be around Rs 23.29 trillion. This amounts to cost overruns of around 20.05 per cent from the original cost – of around Rs 3.89 trillion. Till August 2019, the expenses incurred by these projects amounts to Rs 9.75 trillion, which is 41.85 per cent of the expected cost of the projects. Additionally, the report included the number of projects that had crossed their deadlines; these amounted to 552. The average time overrun for all 552 projects was reported to be 38.89 months. Reportedly, out of all the 552 projects showing time overruns, 181 projects are showing an overall delay in the range of 1 to 12 months, 128 projects have delay of 13 to 24 months, 127 projects show delay in the range of 25 to 60 months and 116 projects reflect delay of 61 months and above. However, as per the report, the number of delayed projects decreases to 489 if the delay is calculated on the basis of latest schedule of completion. Moreover, for 687 projects neither the year of commissioning nor the tentative gestation period has been reported. Escalations in time could be caused by issues relating to obtaining forest clearances, acquiring required land and supply of equipment. According to the report, developers also face additional constraints because of funding, geographical conditions, labour issues and court cases, among other reasons. Reportedly, it is possible that the time and cost overrun figures have been under-reported since project agencies have not reported revised cost estimates and commissioning schedules for numerous projects.

Next Story
Infrastructure Urban

AI Data Centre Leaders Map India’s Infrastructure Roadmap

Mumbai, 22 July 2026: As artificial intelligence reshapes global digital infrastructure, industry leaders gathered in Mumbai today at the AI-Powered Data Centre Conference 2026 to discuss how India can build the capacity, technology and ecosystem required to emerge as a global AI infrastructure hub. Organised by ASAPP Info Global Group and conceptualised by FIRST Construction Council, the conference revolved around the theme, “From Capacity Gap to AI Superpower: Building India's Digital Backbone for the Intelligence Economy.” Bringing together developers, technology providers, enterpr..

Next Story
Infrastructure Urban

SCLR Extension Nears Completion Linking BKC With Signal-Free Route

The Santacruz-Chembur Link Road (SCLR) extension towards Bandra-Kurla Complex (BKC) via the Mumbai University campus has entered its final stage, bringing motorists closer to a direct, signal-free connection between the Western Express Highway and the city’s commercial district. The elevated connector is being built as an arm from the SCLR alignment and will link the western suburbs with BKC without surface signals. The link is designed to reduce journey times for commuters travelling from the western suburbs to BKC and to improve access to eastern Mumbai. By carrying through traffic above s..

Next Story
Infrastructure Transport

Raiganj MP Seeks Bengal Only Highway Link To Siliguri

Raiganj Member of Parliament Kartik Chandra Paul met Union Minister for Road Transport and Highways Nitin Gadkari in New Delhi to press for a new stretch of national highway in North Dinajpur district. He urged approval for a Bengal-to-Bengal link that would connect National Highways 12 and 27 to allow vehicles bound for Siliguri to avoid the current route through Kishanganj in neighbouring Bihar. He also submitted a proposed alignment of the new road to the ministry for consideration. At present vehicles from Raiganj travel along NH-12 and join NH-27 at Purnia More in Dalkhola, a route that p..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement