373 projects show cost overruns of Rs 3.89 trillion
ECONOMY & POLICY

373 projects show cost overruns of Rs 3.89 trillion

The Ministry of Statistics and Programme Implementation (MoSPI), charged with the responsibility of monitoring infrastructure projects worth Rs 1.5 billion or more, has released a report for August 2019, according to which, out of a total 1,634 projects, around 373 have shown cost overruns to the tune of Rs 3.89 trillion.

The report states that the original estimated cost of all the projects is approximately Rs 19.40 trillion. Completion cost is now expected to be around Rs 23.29 trillion. This amounts to cost overruns of around 20.05 per cent from the original cost – of around Rs 3.89 trillion. Till August 2019, the expenses incurred by these projects amounts to Rs 9.75 trillion, which is 41.85 per cent of the expected cost of the projects.

Additionally, the report included the number of projects that had crossed their deadlines; these amounted to 552. The average time overrun for all 552 projects was reported to be 38.89 months.

Reportedly, out of all the 552 projects showing time overruns, 181 projects are showing an overall delay in the range of 1 to 12 months, 128 projects have delay of 13 to 24 months, 127 projects show delay in the range of 25 to 60 months and 116 projects reflect delay of 61 months and above. However, as per the report, the number of delayed projects decreases to 489 if the delay is calculated on the basis of latest schedule of completion. Moreover, for 687 projects neither the year of commissioning nor the tentative gestation period has been reported.

Escalations in time could be caused by issues relating to obtaining forest clearances, acquiring required land and supply of equipment. According to the report, developers also face additional constraints because of funding, geographical conditions, labour issues and court cases, among other reasons. Reportedly, it is possible that the time and cost overrun figures have been under-reported since project agencies have not reported revised cost estimates and commissioning schedules for numerous projects.

The Ministry of Statistics and Programme Implementation (MoSPI), charged with the responsibility of monitoring infrastructure projects worth Rs 1.5 billion or more, has released a report for August 2019, according to which, out of a total 1,634 projects, around 373 have shown cost overruns to the tune of Rs 3.89 trillion. The report states that the original estimated cost of all the projects is approximately Rs 19.40 trillion. Completion cost is now expected to be around Rs 23.29 trillion. This amounts to cost overruns of around 20.05 per cent from the original cost – of around Rs 3.89 trillion. Till August 2019, the expenses incurred by these projects amounts to Rs 9.75 trillion, which is 41.85 per cent of the expected cost of the projects. Additionally, the report included the number of projects that had crossed their deadlines; these amounted to 552. The average time overrun for all 552 projects was reported to be 38.89 months. Reportedly, out of all the 552 projects showing time overruns, 181 projects are showing an overall delay in the range of 1 to 12 months, 128 projects have delay of 13 to 24 months, 127 projects show delay in the range of 25 to 60 months and 116 projects reflect delay of 61 months and above. However, as per the report, the number of delayed projects decreases to 489 if the delay is calculated on the basis of latest schedule of completion. Moreover, for 687 projects neither the year of commissioning nor the tentative gestation period has been reported. Escalations in time could be caused by issues relating to obtaining forest clearances, acquiring required land and supply of equipment. According to the report, developers also face additional constraints because of funding, geographical conditions, labour issues and court cases, among other reasons. Reportedly, it is possible that the time and cost overrun figures have been under-reported since project agencies have not reported revised cost estimates and commissioning schedules for numerous projects.

Next Story
Products

SOMANY unveils flagship Atelier showroom in New Delhi

SOMANY Ceramics has inaugurated its new flagship Atelier showroom in Rajouri Garden, New Delhi. Spread across 5,500 sq ft, the immersive showroom is aimed at architects, designers, and customers seeking cutting-edge tile and bathware solutions.The experience centre features SOMANY’s high-end collections including the Coverstone large-format slabs, Regalia finishes, and the Italian-inspired Italmarmi range. It also showcases the French Collection-Bathware with matte-finish fittings, as well as new tile lines like Colorato, Porto, and Sedimento. A dedicated EZY Fix zone offers end-to-end solut..

Next Story
Resources

Nestlé India goes digital and green with new Bhiwandi DC

Nestlé India has inaugurated a fully automated, paperless Distribution Center (DC) in Bhiwandi, Maharashtra, reinforcing its commitment to sustainability and digital transformation. The centre is the company’s first to feature a Digital Twin, enabling warehouse simulation and predictive planning.Built in just seven months, the facility houses 20,000 pallet positions and the country’s largest cold room for chocolate storage. It also features India’s first shuttle racking system, improving space efficiency and throughput. Other innovations include AI-enabled CCTV, a digital rack inspectio..

Next Story
Technology

Simple Energy eyes Rs 30 billion IPO in FY27

Simple Energy is planning an Initial Public Offering in Q2–Q3 FY27 to raise Rs 30 billion (USD 350 million) as it focuses on profitability and manufacturing expansion. The clean-tech startup aims to achieve $96 million (Rs 800 crore) in revenue in FY26 and cross $180 million (Rs 1,500 crore) in cumulative revenue over the next 18 months.Founded in 2019, the company has recorded 500 per cent year-on-year growth and achieved gross margin breakeven within two years of commercial operations. It is targeting EBITDA positivity by FY26 and net profitability ahead of the IPO.Proceeds from the IPO wi..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?