DND Flyway Work Delayed as GRAP-IV Extends Timeline
ECONOMY & POLICY

DND Flyway Work Delayed as GRAP-IV Extends Timeline

Upgradation work on the DND Flyway has recently faced temporary disruption, leading to an extension of completion timelines by a few weeks. The delay follows the imposition of GRAP-IV measures across the National Capital Region due to hazardous air quality conditions.

Road improvement activities, categorised as polluting work, cannot be undertaken while GRAP-IV restrictions remain in force. As a result, continuity of planned construction schedules has been impacted.

Noida Toll Bridge Company had awarded the DND Flyway upgradation project and commenced preliminary activities in the third week of October 2025, after completing all preparatory work including materials, manpower mobilisation and detailed execution planning. The original completion target was end-December 2025 to January 2026.

However, statutory curbs under GRAP-IV pushed the commencement of key upgradation activities towards December 2025, resulting in a delay of nearly five weeks. In addition, based on technical recommendations, a portion of the work scheduled earlier cannot be executed during peak winter conditions, as it requires specific temperature parameters to ensure quality outcomes. This phase is now planned for January.

These factors have collectively affected construction progress, and work is currently on hold in compliance with regulatory directives. Once GRAP-IV measures are lifted and conditions become conducive, the remaining activities are expected to be completed within approximately five weeks, extending the timeline into February 2026.

The company said it remains committed to maintaining world-class infrastructure standards on the DND Flyway, ensuring commuter safety and smooth traffic movement, while coordinating closely with authorities to resume works at the earliest permissible opportunity.

Upgradation work on the DND Flyway has recently faced temporary disruption, leading to an extension of completion timelines by a few weeks. The delay follows the imposition of GRAP-IV measures across the National Capital Region due to hazardous air quality conditions. Road improvement activities, categorised as polluting work, cannot be undertaken while GRAP-IV restrictions remain in force. As a result, continuity of planned construction schedules has been impacted. Noida Toll Bridge Company had awarded the DND Flyway upgradation project and commenced preliminary activities in the third week of October 2025, after completing all preparatory work including materials, manpower mobilisation and detailed execution planning. The original completion target was end-December 2025 to January 2026. However, statutory curbs under GRAP-IV pushed the commencement of key upgradation activities towards December 2025, resulting in a delay of nearly five weeks. In addition, based on technical recommendations, a portion of the work scheduled earlier cannot be executed during peak winter conditions, as it requires specific temperature parameters to ensure quality outcomes. This phase is now planned for January. These factors have collectively affected construction progress, and work is currently on hold in compliance with regulatory directives. Once GRAP-IV measures are lifted and conditions become conducive, the remaining activities are expected to be completed within approximately five weeks, extending the timeline into February 2026. The company said it remains committed to maintaining world-class infrastructure standards on the DND Flyway, ensuring commuter safety and smooth traffic movement, while coordinating closely with authorities to resume works at the earliest permissible opportunity.

Next Story
Infrastructure Urban

Panasonic Showcases Connected Display Solutions

Panasonic Life Solutions India showcased its integrated display, projection, broadcast and communication technologies at Panasonic Tech Summit 2026 in New Delhi. Hosted through its System Solutions Division, the two-day event highlighted connected technology solutions for education, healthcare, retail, transportation, corporate offices and entertainment.The summit, themed ‘Turning Technology into Value’, featured experience-led zones covering QSR, retail, transit, corporate offices, healthcare, education, security, projection, home theatre and professional displays. Panasonic also introduc..

Next Story
Infrastructure Transport

Kapsch to Deliver India’s First C-ITS Project

"Kapsch TrafficCom will deliver India’s first Cooperative Intelligent Transport Systems project on a key expressway near New Delhi. The project will be implemented with Superwave Communication And Infrasolution Limited to demonstrate how connected mobility can improve road safety and traffic efficiency.The pilot will use real-time connectivity and AI-enabled situational awareness to support road users, especially in high-risk areas such as temporary work zones. Drivers will receive alerts on roadworks, maintenance vehicles, hazardous locations, traffic queues and temporary virtual signage di..

Next Story
Infrastructure Urban

Eurobond Net Profit Rises 44 Per Cent

Euro Panel Products, the parent company of Eurobond, reported a 44.13 per cent year-on-year rise in net profit for FY25–26. The company’s revenue from operations grew 18.91 per cent to Rs 503.20 crore, compared to Rs 423.18 crore in the previous financial year.The company’s full-year EBITDA stood at Rs 56.67 crore, marking a 31.82 per cent increase. Profit after tax rose to Rs 26.56 crore, while net worth increased 20.15 per cent to Rs 160.07 crore. Earnings per share for the year stood at Rs 10.84.Divyam Rajesh Shah, Whole Time Director and CFO, Euro Panel Products, said the company’s..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

-->