DND Flyway Work Delayed as GRAP-IV Extends Timeline
ECONOMY & POLICY

DND Flyway Work Delayed as GRAP-IV Extends Timeline

Upgradation work on the DND Flyway has recently faced temporary disruption, leading to an extension of completion timelines by a few weeks. The delay follows the imposition of GRAP-IV measures across the National Capital Region due to hazardous air quality conditions.

Road improvement activities, categorised as polluting work, cannot be undertaken while GRAP-IV restrictions remain in force. As a result, continuity of planned construction schedules has been impacted.

Noida Toll Bridge Company had awarded the DND Flyway upgradation project and commenced preliminary activities in the third week of October 2025, after completing all preparatory work including materials, manpower mobilisation and detailed execution planning. The original completion target was end-December 2025 to January 2026.

However, statutory curbs under GRAP-IV pushed the commencement of key upgradation activities towards December 2025, resulting in a delay of nearly five weeks. In addition, based on technical recommendations, a portion of the work scheduled earlier cannot be executed during peak winter conditions, as it requires specific temperature parameters to ensure quality outcomes. This phase is now planned for January.

These factors have collectively affected construction progress, and work is currently on hold in compliance with regulatory directives. Once GRAP-IV measures are lifted and conditions become conducive, the remaining activities are expected to be completed within approximately five weeks, extending the timeline into February 2026.

The company said it remains committed to maintaining world-class infrastructure standards on the DND Flyway, ensuring commuter safety and smooth traffic movement, while coordinating closely with authorities to resume works at the earliest permissible opportunity.

Upgradation work on the DND Flyway has recently faced temporary disruption, leading to an extension of completion timelines by a few weeks. The delay follows the imposition of GRAP-IV measures across the National Capital Region due to hazardous air quality conditions. Road improvement activities, categorised as polluting work, cannot be undertaken while GRAP-IV restrictions remain in force. As a result, continuity of planned construction schedules has been impacted. Noida Toll Bridge Company had awarded the DND Flyway upgradation project and commenced preliminary activities in the third week of October 2025, after completing all preparatory work including materials, manpower mobilisation and detailed execution planning. The original completion target was end-December 2025 to January 2026. However, statutory curbs under GRAP-IV pushed the commencement of key upgradation activities towards December 2025, resulting in a delay of nearly five weeks. In addition, based on technical recommendations, a portion of the work scheduled earlier cannot be executed during peak winter conditions, as it requires specific temperature parameters to ensure quality outcomes. This phase is now planned for January. These factors have collectively affected construction progress, and work is currently on hold in compliance with regulatory directives. Once GRAP-IV measures are lifted and conditions become conducive, the remaining activities are expected to be completed within approximately five weeks, extending the timeline into February 2026. The company said it remains committed to maintaining world-class infrastructure standards on the DND Flyway, ensuring commuter safety and smooth traffic movement, while coordinating closely with authorities to resume works at the earliest permissible opportunity.

Next Story
Infrastructure Urban

Runaya–ECKART JV Launches India’s First Gas-Atomised Al Unit

Runaya Metsource and Germany-based ECKART have announced the launch of their joint venture facility, Runaya Eckart Aluminium Powders Private Limited (REL), in Jharsuguda, Odisha, marking the establishment of India’s first plant for manufacturing green, spherical gas-atomised aluminium powders.The facility will produce high-precision aluminium powders for advanced applications across aviation, aerospace, space exploration, solar technology, process catalyst industries and effect pigments. These fine spherical powders, which were previously fully imported into India, represent a significant mi..

Next Story
Infrastructure Urban

Tamil Nadu Extends 100% EV Road Tax Exemption Till 2027

The Tamil Nadu government has extended the 100% road tax exemption for battery-operated electric vehicles for another two years, reinforcing its efforts to sustain momentum in EV adoption across the state.According to a government order issued on December 29, the tax exemption has been extended for all categories of battery-operated vehicles, including both transport and non-transport vehicles, from January 1, 2026, to December 31, 2027. The move ensures continuity of fiscal incentives as electric vehicle penetration continues to rise in the state.The decision follows sustained representations..

Next Story
Infrastructure Energy

Coal India Arm BCCL Targets 54 MT Output, Rs 200 Bn by FY30

Bharat Coking Coal (BCCL), a subsidiary of Coal India, plans to scale up its coking coal production to 54 million tonnes by FY 2029–30, with the bulk of incremental supplies earmarked for the steel sector. The expansion is expected to drive the company’s revenue close to Rs 200 billion by the end of the decade, senior officials said.The production push aligns with India’s broader objective of achieving a national coking coal output target of 140 million tonnes to reduce dependence on imports. BCCL currently produces around 40.5 million tonnes of coking coal and contributes nearly 58.5 pe..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Open In App