DND Flyway Work Delayed as GRAP-IV Extends Timeline
ECONOMY & POLICY

DND Flyway Work Delayed as GRAP-IV Extends Timeline

Upgradation work on the DND Flyway has recently faced temporary disruption, leading to an extension of completion timelines by a few weeks. The delay follows the imposition of GRAP-IV measures across the National Capital Region due to hazardous air quality conditions.

Road improvement activities, categorised as polluting work, cannot be undertaken while GRAP-IV restrictions remain in force. As a result, continuity of planned construction schedules has been impacted.

Noida Toll Bridge Company had awarded the DND Flyway upgradation project and commenced preliminary activities in the third week of October 2025, after completing all preparatory work including materials, manpower mobilisation and detailed execution planning. The original completion target was end-December 2025 to January 2026.

However, statutory curbs under GRAP-IV pushed the commencement of key upgradation activities towards December 2025, resulting in a delay of nearly five weeks. In addition, based on technical recommendations, a portion of the work scheduled earlier cannot be executed during peak winter conditions, as it requires specific temperature parameters to ensure quality outcomes. This phase is now planned for January.

These factors have collectively affected construction progress, and work is currently on hold in compliance with regulatory directives. Once GRAP-IV measures are lifted and conditions become conducive, the remaining activities are expected to be completed within approximately five weeks, extending the timeline into February 2026.

The company said it remains committed to maintaining world-class infrastructure standards on the DND Flyway, ensuring commuter safety and smooth traffic movement, while coordinating closely with authorities to resume works at the earliest permissible opportunity.

Upgradation work on the DND Flyway has recently faced temporary disruption, leading to an extension of completion timelines by a few weeks. The delay follows the imposition of GRAP-IV measures across the National Capital Region due to hazardous air quality conditions. Road improvement activities, categorised as polluting work, cannot be undertaken while GRAP-IV restrictions remain in force. As a result, continuity of planned construction schedules has been impacted. Noida Toll Bridge Company had awarded the DND Flyway upgradation project and commenced preliminary activities in the third week of October 2025, after completing all preparatory work including materials, manpower mobilisation and detailed execution planning. The original completion target was end-December 2025 to January 2026. However, statutory curbs under GRAP-IV pushed the commencement of key upgradation activities towards December 2025, resulting in a delay of nearly five weeks. In addition, based on technical recommendations, a portion of the work scheduled earlier cannot be executed during peak winter conditions, as it requires specific temperature parameters to ensure quality outcomes. This phase is now planned for January. These factors have collectively affected construction progress, and work is currently on hold in compliance with regulatory directives. Once GRAP-IV measures are lifted and conditions become conducive, the remaining activities are expected to be completed within approximately five weeks, extending the timeline into February 2026. The company said it remains committed to maintaining world-class infrastructure standards on the DND Flyway, ensuring commuter safety and smooth traffic movement, while coordinating closely with authorities to resume works at the earliest permissible opportunity.

Next Story
Infrastructure Urban

InsideFPV Delivers ₹10 Crore Kamikaze Drone Order Under MoD’s EPR Route

InsideFPV, a Surat-based drone technology manufacturer, has successfully executed a ₹10 crore defence contract to supply indigenous kamikaze drones under the Ministry of Defence’s Emergency Procurement Route (EPR). The company completed the delivery of hundreds of FPV kamikaze drone platforms within a rapid two-month timeframe, highlighting its ability to meet urgent military procurement timelines.The supply orders were fulfilled under the emergency procurement mechanism, which is aimed at fast-tracking acquisitions for immediate operational needs. InsideFPV’s quick execution reflects it..

Next Story
Infrastructure Energy

Vedanta Resources Secures Fitch Upgrade to ‘BB-’, Best Rating Since 2015

Vedanta Resources Limited (VRL), a global player in metals, oil & gas, critical minerals, power and technology, has received a credit rating upgrade from Fitch Ratings, marking its strongest bond rating in over a decade.Fitch has raised Vedanta Resources’ Long-Term Foreign-Currency Issuer Default Rating (IDR) to ‘BB-’ from ‘B+’, while maintaining a Stable Outlook. The agency also upgraded VRL’s senior unsecured rating, along with the ratings of US dollar-denominated bonds issued by Vedanta Resources Finance II Plc and guaranteed by VRL, to ‘BB-’.The upgrade represents Vedan..

Next Story
Real Estate

NAREDCO NextGen NCR Chapter Launched

The NAREDCO NextGen NCR Chapter was recently launched at Excelerate 2026 in Mumbai, marking a key step towards integrating emerging real estate leaders from the National Capital Region with the national platform. The initiative aims to promote sustainable and responsible urban development through collaboration and knowledge exchange.The event brought together young developers, entrepreneurs, and professionals from across NCR, including Noida, Gurugram, Ghaziabad, Faridabad, Bhiwadi, and Meerut. Discussions focused on urban development, finance, sustainability, innovation, and policy, emphasisi..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement