+
DND Flyway Work Delayed as GRAP-IV Extends Timeline
ECONOMY & POLICY

DND Flyway Work Delayed as GRAP-IV Extends Timeline

Upgradation work on the DND Flyway has recently faced temporary disruption, leading to an extension of completion timelines by a few weeks. The delay follows the imposition of GRAP-IV measures across the National Capital Region due to hazardous air quality conditions.

Road improvement activities, categorised as polluting work, cannot be undertaken while GRAP-IV restrictions remain in force. As a result, continuity of planned construction schedules has been impacted.

Noida Toll Bridge Company had awarded the DND Flyway upgradation project and commenced preliminary activities in the third week of October 2025, after completing all preparatory work including materials, manpower mobilisation and detailed execution planning. The original completion target was end-December 2025 to January 2026.

However, statutory curbs under GRAP-IV pushed the commencement of key upgradation activities towards December 2025, resulting in a delay of nearly five weeks. In addition, based on technical recommendations, a portion of the work scheduled earlier cannot be executed during peak winter conditions, as it requires specific temperature parameters to ensure quality outcomes. This phase is now planned for January.

These factors have collectively affected construction progress, and work is currently on hold in compliance with regulatory directives. Once GRAP-IV measures are lifted and conditions become conducive, the remaining activities are expected to be completed within approximately five weeks, extending the timeline into February 2026.

The company said it remains committed to maintaining world-class infrastructure standards on the DND Flyway, ensuring commuter safety and smooth traffic movement, while coordinating closely with authorities to resume works at the earliest permissible opportunity.

Upgradation work on the DND Flyway has recently faced temporary disruption, leading to an extension of completion timelines by a few weeks. The delay follows the imposition of GRAP-IV measures across the National Capital Region due to hazardous air quality conditions. Road improvement activities, categorised as polluting work, cannot be undertaken while GRAP-IV restrictions remain in force. As a result, continuity of planned construction schedules has been impacted. Noida Toll Bridge Company had awarded the DND Flyway upgradation project and commenced preliminary activities in the third week of October 2025, after completing all preparatory work including materials, manpower mobilisation and detailed execution planning. The original completion target was end-December 2025 to January 2026. However, statutory curbs under GRAP-IV pushed the commencement of key upgradation activities towards December 2025, resulting in a delay of nearly five weeks. In addition, based on technical recommendations, a portion of the work scheduled earlier cannot be executed during peak winter conditions, as it requires specific temperature parameters to ensure quality outcomes. This phase is now planned for January. These factors have collectively affected construction progress, and work is currently on hold in compliance with regulatory directives. Once GRAP-IV measures are lifted and conditions become conducive, the remaining activities are expected to be completed within approximately five weeks, extending the timeline into February 2026. The company said it remains committed to maintaining world-class infrastructure standards on the DND Flyway, ensuring commuter safety and smooth traffic movement, while coordinating closely with authorities to resume works at the earliest permissible opportunity.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

NABARD Holds Seminar on Vigilance, Integrity and Good Governance

National Bank for Agriculture and Rural Development (NABARD) organised a seminar on “Vigilance: Strengthening Integrity and Good Governance” on 25 August 2026 at its Head Office in Mumbai as part of the ongoing Vigilance Awareness Campaign 2026 being observed from 17 August to 16 November 2026, with the theme “Probity for Prosperity."" The seminar was graced by Suresh N Patel, Former Central Vigilance Commissioner, Government of India, as the chief guest and keynote speaker.  The programme was attended by G S Rawat, Deputy Managing Director, Dr Ajay K Sood, Deputy Managing Dire..

Next Story
Equipment

XCMG Unveils World's First 14,000-Ton Ring Crane for Heavy Lifting

XCMG has announced that the first main unit of the world's first 14,000-ton ring crane has rolled off the production line, marking a historic breakthrough in ultra-heavy lifting technology. Jointly developed by XCMG and Sinopec Heavy Lifting & Transportation Co., Ltd., the crane will be the largest-capacity ring crane ever built, setting a new benchmark for major construction projects worldwide.The crane features a modular configuration comprising two main units that work in tandem. The first main unit has completed final assembly and can independently perform lifting operations. Once both..

Next Story
Infrastructure Urban

Thriveni Logistics orders 200 tip trailers from Jagdamba trailers

Jagdamba Trailers (JTPL), one of India’s growing trailer manufacturers, has secured a significant order for 200 Tip Trailers from Thriveni Transport and Logistics Pvt. Ltd., a leading mining and logistics company serving operations across India and overseas.The order, placed for iron ore transportation, is a major milestone for JTPL, particularly as the company secured the business after competing with more than 10 established trailer manufacturers. It also strengthens an already successful relationship between the two companies. Approximately one and a half years ago, Thriveni Transport and..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code