IPMD report highlights over 800 delayed infrastructure prjoects
ECONOMY & POLICY

IPMD report highlights over 800 delayed infrastructure prjoects

According to a government report, approximately 835 central sector infrastructure projects have been delayed from their original schedules. According to the most recent report published by the Infrastructure and Project Monitoring Division (IPMD), the road, transportation, and highways sector has the highest number of delayed projects in the country.

The IPMD is administered by the Ministry of Statistics and Program Implementation. It keeps track of the progress of projects worth more than Rs 150 crores.

Based on the IPMD December 2022 report, the Road Transport and Highways sector has 428 delayed projects, followed by 117 in Railways, 88 in Petroleum, 36 in coal, 55 in power, 27 in water resources, 4 in Health and Family Welfare, 15 in urban development, 24 in civil aviation, and many others.

The total original cost of these 1,438 projects was Rs 20,35,794.75 crores, with an estimated completion cost of Rs 24,86,069.52 crores. This indicates a cost overrun of Rs 4,50,274.77 crores.

In a statement, the IPMD said, “Out of the 1438 projects, 8 projects are ahead of schedule, 253 are on schedule, 835 are delayed, 343 projects reported cost overrun and 165 projects reported both time and cost overrun with respect to their original project implementation schedules.”

Sectorwise list of few projects having a maximum percentage of Cost Overruns

Road Transport and Highways:

  • For laning of Ghaghra Bridge to Varanasi (PKG-II)
  • Four laning of Sultanpur to Varanasi (PKG-I)
  • Construction of eight lane access controlled expressway carriageway from Rajasthan/MP border to JODM
  • Four laning of Solan-Kaithlighat section of NH-22 (Now NH-5)
  • Rehabilitation and Upgradation of existing NH-565 from KM86.057 TO 133.922 of Nagarjuna Sagar Dam T
  • Railways:

  • Lalitpur-Satna-Rewa-Singruli NL
  • Madurai-Tuticorin Via Aruppukkottai
  • Udhampur-Srinagar-Baramulla
  • New BG Line from Byrnihat to Shillong
  • Ramganjmundi-Bhopal
  • Urban Development:

  • Mumbai Metro Line 3 (Colaba-Bandra-SEEPZ)
  • Chennai Metro Rail LTD (Phase 1)
  • Kochi Metro Rail Project
  • Ahmedabad Metro Rail Project Phase 1
  • Nagpur Metro Rail
  • According to the IPMD report, the Muneerabad-Mahaboobnagar rail project is the most delayed by 276 months, followed by the Udhampur-Srinagar-Baramulla rail project (247 months), and the Belapur-Seawood-Urban Electrified Double Line (247 months) (by 228 months).

    See also:
    343 infra projects witness estimated cost exceeding
    Roads and transport experience most delays, says report


    According to a government report, approximately 835 central sector infrastructure projects have been delayed from their original schedules. According to the most recent report published by the Infrastructure and Project Monitoring Division (IPMD), the road, transportation, and highways sector has the highest number of delayed projects in the country. The IPMD is administered by the Ministry of Statistics and Program Implementation. It keeps track of the progress of projects worth more than Rs 150 crores. Based on the IPMD December 2022 report, the Road Transport and Highways sector has 428 delayed projects, followed by 117 in Railways, 88 in Petroleum, 36 in coal, 55 in power, 27 in water resources, 4 in Health and Family Welfare, 15 in urban development, 24 in civil aviation, and many others. The total original cost of these 1,438 projects was Rs 20,35,794.75 crores, with an estimated completion cost of Rs 24,86,069.52 crores. This indicates a cost overrun of Rs 4,50,274.77 crores. In a statement, the IPMD said, “Out of the 1438 projects, 8 projects are ahead of schedule, 253 are on schedule, 835 are delayed, 343 projects reported cost overrun and 165 projects reported both time and cost overrun with respect to their original project implementation schedules.” Sectorwise list of few projects having a maximum percentage of Cost Overruns Road Transport and Highways: For laning of Ghaghra Bridge to Varanasi (PKG-II) Four laning of Sultanpur to Varanasi (PKG-I) Construction of eight lane access controlled expressway carriageway from Rajasthan/MP border to JODM Four laning of Solan-Kaithlighat section of NH-22 (Now NH-5) Rehabilitation and Upgradation of existing NH-565 from KM86.057 TO 133.922 of Nagarjuna Sagar Dam T Railways: Lalitpur-Satna-Rewa-Singruli NL Madurai-Tuticorin Via Aruppukkottai Udhampur-Srinagar-Baramulla New BG Line from Byrnihat to Shillong Ramganjmundi-Bhopal Urban Development: Mumbai Metro Line 3 (Colaba-Bandra-SEEPZ) Chennai Metro Rail LTD (Phase 1) Kochi Metro Rail Project Ahmedabad Metro Rail Project Phase 1 Nagpur Metro Rail According to the IPMD report, the Muneerabad-Mahaboobnagar rail project is the most delayed by 276 months, followed by the Udhampur-Srinagar-Baramulla rail project (247 months), and the Belapur-Seawood-Urban Electrified Double Line (247 months) (by 228 months). See also: 343 infra projects witness estimated cost exceeding Roads and transport experience most delays, says report

    Related Stories

    Gold Stories

    Next Story
    Infrastructure Urban

    Infrastructure Opportunity Outlook by IMPACCT.Info

    India’s infrastructure pipeline is witnessing dynamic activity across stages — from immediate bidding to future planning. IMPACCT segments these into three categories: Immediate, 3–6 Month, and Future Opportunities, enabling businesses to identify, prepare, and participate in high-value tenders and projects across sectors.To read full article Click Here ..

    Next Story
    Real Estate

    Glass, Reframed!

    Glass façades, quintessential aesthetic building envelopes globally, have been widely adopted in India as well. But when the focus is high-performance building systems that deliver energy efficiency, comfort and architectural identity, glass isn’t the only preference. Combination solutions, involving glass and some other material, improve façade outcomes. Some combinations come at comparable prices, some at a higher price. Here is a selection of performance-oriented solutions...To read the full story Click Here ..

    Next Story
    Infrastructure Urban

    Beyond Building Faster

    India’s cities are expanding at an unprecedented pace, bringing new infrastructure and development opportunities while also intensifying challenges around mobility, public spaces, liveability and supporting infrastructure. The question, therefore, is not simply whether India can build faster, but whether it can build cities that work better.At a CW webinar, Are We Designing Better Cities – or Just Building Faster?, moderator Ar. Samir Shaikh, Founding Principal, AR&UD Studio, brought together perspectives from design, development, master planning and technology...To read the full artic..

    Advertisement

    Subscribe to Our Newsletter

    Get daily newsletters around different themes from Construction world.

    STAY CONNECTED

    Advertisement

    SPECIAL OFFER
    QR Code