IPMD report highlights over 800 delayed infrastructure prjoects
ECONOMY & POLICY

IPMD report highlights over 800 delayed infrastructure prjoects

According to a government report, approximately 835 central sector infrastructure projects have been delayed from their original schedules. According to the most recent report published by the Infrastructure and Project Monitoring Division (IPMD), the road, transportation, and highways sector has the highest number of delayed projects in the country.

The IPMD is administered by the Ministry of Statistics and Program Implementation. It keeps track of the progress of projects worth more than Rs 150 crores.

Based on the IPMD December 2022 report, the Road Transport and Highways sector has 428 delayed projects, followed by 117 in Railways, 88 in Petroleum, 36 in coal, 55 in power, 27 in water resources, 4 in Health and Family Welfare, 15 in urban development, 24 in civil aviation, and many others.

The total original cost of these 1,438 projects was Rs 20,35,794.75 crores, with an estimated completion cost of Rs 24,86,069.52 crores. This indicates a cost overrun of Rs 4,50,274.77 crores.

In a statement, the IPMD said, “Out of the 1438 projects, 8 projects are ahead of schedule, 253 are on schedule, 835 are delayed, 343 projects reported cost overrun and 165 projects reported both time and cost overrun with respect to their original project implementation schedules.”

Sectorwise list of few projects having a maximum percentage of Cost Overruns

Road Transport and Highways:

  • For laning of Ghaghra Bridge to Varanasi (PKG-II)
  • Four laning of Sultanpur to Varanasi (PKG-I)
  • Construction of eight lane access controlled expressway carriageway from Rajasthan/MP border to JODM
  • Four laning of Solan-Kaithlighat section of NH-22 (Now NH-5)
  • Rehabilitation and Upgradation of existing NH-565 from KM86.057 TO 133.922 of Nagarjuna Sagar Dam T
  • Railways:

  • Lalitpur-Satna-Rewa-Singruli NL
  • Madurai-Tuticorin Via Aruppukkottai
  • Udhampur-Srinagar-Baramulla
  • New BG Line from Byrnihat to Shillong
  • Ramganjmundi-Bhopal
  • Urban Development:

  • Mumbai Metro Line 3 (Colaba-Bandra-SEEPZ)
  • Chennai Metro Rail LTD (Phase 1)
  • Kochi Metro Rail Project
  • Ahmedabad Metro Rail Project Phase 1
  • Nagpur Metro Rail
  • According to the IPMD report, the Muneerabad-Mahaboobnagar rail project is the most delayed by 276 months, followed by the Udhampur-Srinagar-Baramulla rail project (247 months), and the Belapur-Seawood-Urban Electrified Double Line (247 months) (by 228 months).

    See also:
    343 infra projects witness estimated cost exceeding
    Roads and transport experience most delays, says report


    According to a government report, approximately 835 central sector infrastructure projects have been delayed from their original schedules. According to the most recent report published by the Infrastructure and Project Monitoring Division (IPMD), the road, transportation, and highways sector has the highest number of delayed projects in the country. The IPMD is administered by the Ministry of Statistics and Program Implementation. It keeps track of the progress of projects worth more than Rs 150 crores. Based on the IPMD December 2022 report, the Road Transport and Highways sector has 428 delayed projects, followed by 117 in Railways, 88 in Petroleum, 36 in coal, 55 in power, 27 in water resources, 4 in Health and Family Welfare, 15 in urban development, 24 in civil aviation, and many others. The total original cost of these 1,438 projects was Rs 20,35,794.75 crores, with an estimated completion cost of Rs 24,86,069.52 crores. This indicates a cost overrun of Rs 4,50,274.77 crores. In a statement, the IPMD said, “Out of the 1438 projects, 8 projects are ahead of schedule, 253 are on schedule, 835 are delayed, 343 projects reported cost overrun and 165 projects reported both time and cost overrun with respect to their original project implementation schedules.” Sectorwise list of few projects having a maximum percentage of Cost Overruns Road Transport and Highways: For laning of Ghaghra Bridge to Varanasi (PKG-II) Four laning of Sultanpur to Varanasi (PKG-I) Construction of eight lane access controlled expressway carriageway from Rajasthan/MP border to JODM Four laning of Solan-Kaithlighat section of NH-22 (Now NH-5) Rehabilitation and Upgradation of existing NH-565 from KM86.057 TO 133.922 of Nagarjuna Sagar Dam T Railways: Lalitpur-Satna-Rewa-Singruli NL Madurai-Tuticorin Via Aruppukkottai Udhampur-Srinagar-Baramulla New BG Line from Byrnihat to Shillong Ramganjmundi-Bhopal Urban Development: Mumbai Metro Line 3 (Colaba-Bandra-SEEPZ) Chennai Metro Rail LTD (Phase 1) Kochi Metro Rail Project Ahmedabad Metro Rail Project Phase 1 Nagpur Metro Rail According to the IPMD report, the Muneerabad-Mahaboobnagar rail project is the most delayed by 276 months, followed by the Udhampur-Srinagar-Baramulla rail project (247 months), and the Belapur-Seawood-Urban Electrified Double Line (247 months) (by 228 months). See also: 343 infra projects witness estimated cost exceeding Roads and transport experience most delays, says report

    Related Stories

    Gold Stories

    Next Story
    Resources

    Schindler named among Forbes’ World’s Best Employers 2026

    Schindler has been named among Forbes’ World’s Best Employers 2026, a global ranking recognising companies for their workplace environments.Compiled by Forbes in partnership with Statista, the ranking is based on independent employee feedback, including whether employees would recommend their organisation to friends and family.The company said the recognition reflected its focus on creating a workplace where employees can develop their expertise and build careers. ..

    Next Story
    Infrastructure Urban

    India needs an export-execution mindset: Vishesh Jain

    Interview with Vishesh Jain, Founder & CEO, EximpleWhat gaps in India’s global trade ecosystem led you to build Eximple, and what problem did you see businesses struggling with most?Eximple came out of a problem that all three founders had seen from different choke points in the trade ecosystem. India has millions of MSMEs and manufacturers, and many of them can make products that are genuinely competitive on quality. Yet only a small fraction is able to build meaningful international businesses. In our experience, the gap is usually not manufacturing capability; it is the ability to exe..

    Next Story
    Building Material

    Nuvoco reports 13.5% revenue growth in Q2 FY27

    Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid re..

    Advertisement

    Subscribe to Our Newsletter

    Get daily newsletters around different themes from Construction world.

    STAY CONNECTED

    Advertisement

    SPECIAL OFFER
    QR Code