IPMD report highlights over 800 delayed infrastructure prjoects
ECONOMY & POLICY

IPMD report highlights over 800 delayed infrastructure prjoects

According to a government report, approximately 835 central sector infrastructure projects have been delayed from their original schedules. According to the most recent report published by the Infrastructure and Project Monitoring Division (IPMD), the road, transportation, and highways sector has the highest number of delayed projects in the country.

The IPMD is administered by the Ministry of Statistics and Program Implementation. It keeps track of the progress of projects worth more than Rs 150 crores.

Based on the IPMD December 2022 report, the Road Transport and Highways sector has 428 delayed projects, followed by 117 in Railways, 88 in Petroleum, 36 in coal, 55 in power, 27 in water resources, 4 in Health and Family Welfare, 15 in urban development, 24 in civil aviation, and many others.

The total original cost of these 1,438 projects was Rs 20,35,794.75 crores, with an estimated completion cost of Rs 24,86,069.52 crores. This indicates a cost overrun of Rs 4,50,274.77 crores.

In a statement, the IPMD said, “Out of the 1438 projects, 8 projects are ahead of schedule, 253 are on schedule, 835 are delayed, 343 projects reported cost overrun and 165 projects reported both time and cost overrun with respect to their original project implementation schedules.”

Sectorwise list of few projects having a maximum percentage of Cost Overruns

Road Transport and Highways:

  • For laning of Ghaghra Bridge to Varanasi (PKG-II)
  • Four laning of Sultanpur to Varanasi (PKG-I)
  • Construction of eight lane access controlled expressway carriageway from Rajasthan/MP border to JODM
  • Four laning of Solan-Kaithlighat section of NH-22 (Now NH-5)
  • Rehabilitation and Upgradation of existing NH-565 from KM86.057 TO 133.922 of Nagarjuna Sagar Dam T
  • Railways:

  • Lalitpur-Satna-Rewa-Singruli NL
  • Madurai-Tuticorin Via Aruppukkottai
  • Udhampur-Srinagar-Baramulla
  • New BG Line from Byrnihat to Shillong
  • Ramganjmundi-Bhopal
  • Urban Development:

  • Mumbai Metro Line 3 (Colaba-Bandra-SEEPZ)
  • Chennai Metro Rail LTD (Phase 1)
  • Kochi Metro Rail Project
  • Ahmedabad Metro Rail Project Phase 1
  • Nagpur Metro Rail
  • According to the IPMD report, the Muneerabad-Mahaboobnagar rail project is the most delayed by 276 months, followed by the Udhampur-Srinagar-Baramulla rail project (247 months), and the Belapur-Seawood-Urban Electrified Double Line (247 months) (by 228 months).

    See also:
    343 infra projects witness estimated cost exceeding
    Roads and transport experience most delays, says report


    "Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

    According to a government report, approximately 835 central sector infrastructure projects have been delayed from their original schedules. According to the most recent report published by the Infrastructure and Project Monitoring Division (IPMD), the road, transportation, and highways sector has the highest number of delayed projects in the country. The IPMD is administered by the Ministry of Statistics and Program Implementation. It keeps track of the progress of projects worth more than Rs 150 crores. Based on the IPMD December 2022 report, the Road Transport and Highways sector has 428 delayed projects, followed by 117 in Railways, 88 in Petroleum, 36 in coal, 55 in power, 27 in water resources, 4 in Health and Family Welfare, 15 in urban development, 24 in civil aviation, and many others. The total original cost of these 1,438 projects was Rs 20,35,794.75 crores, with an estimated completion cost of Rs 24,86,069.52 crores. This indicates a cost overrun of Rs 4,50,274.77 crores. In a statement, the IPMD said, “Out of the 1438 projects, 8 projects are ahead of schedule, 253 are on schedule, 835 are delayed, 343 projects reported cost overrun and 165 projects reported both time and cost overrun with respect to their original project implementation schedules.” Sectorwise list of few projects having a maximum percentage of Cost Overruns Road Transport and Highways: For laning of Ghaghra Bridge to Varanasi (PKG-II) Four laning of Sultanpur to Varanasi (PKG-I) Construction of eight lane access controlled expressway carriageway from Rajasthan/MP border to JODM Four laning of Solan-Kaithlighat section of NH-22 (Now NH-5) Rehabilitation and Upgradation of existing NH-565 from KM86.057 TO 133.922 of Nagarjuna Sagar Dam T Railways: Lalitpur-Satna-Rewa-Singruli NL Madurai-Tuticorin Via Aruppukkottai Udhampur-Srinagar-Baramulla New BG Line from Byrnihat to Shillong Ramganjmundi-Bhopal Urban Development: Mumbai Metro Line 3 (Colaba-Bandra-SEEPZ) Chennai Metro Rail LTD (Phase 1) Kochi Metro Rail Project Ahmedabad Metro Rail Project Phase 1 Nagpur Metro Rail According to the IPMD report, the Muneerabad-Mahaboobnagar rail project is the most delayed by 276 months, followed by the Udhampur-Srinagar-Baramulla rail project (247 months), and the Belapur-Seawood-Urban Electrified Double Line (247 months) (by 228 months). See also: 343 infra projects witness estimated cost exceeding Roads and transport experience most delays, says report

    Next Story
    Infrastructure Urban

    ABS Marine Sees CRISIL Credit Rating Upgrade

    ABS Marine Services has secured an upgrade to its long term and short term credit ratings from CRISIL, reflecting improved profitability and revenue growth through long term contracts. CRISIL moved the long term rating from BBB+/Stable to A-/Stable and revised the short term rating from A2 to A2+. The action signals strengthened financial metrics and operational resilience. The company benefited from durable client relationships with firms such as ONGC and Schlumberger. The rating decision followed stronger cash flows and an enlarged bank loan facility, which increased from Rs 3,705 million (m..

    Next Story
    Infrastructure Transport

    Project BRAHMANK Marks 16 Years Of Strategic Roads In Arunachal

    Project BRAHMANK is marking 16 years of work to establish strategic road and bridge links across Arunachal Pradesh, maintaining and developing 811 kilometres of roads and nearly 86 bridges that range from small culverts to large steel and arch bridges. These transport links are described as critical for ensuring year-round movement of defence personnel, equipment and essential supplies while improving everyday travel for people in remote villages. The project balances national security requirements with regional development by focusing on reliable access in challenging terrain. Notable enginee..

    Next Story
    Infrastructure Transport

    Longleng CSOs Give One Week Ultimatum Over Two-Lane Highway

    Civil society organisations (CSOs) in Longleng district have demanded immediate restoration of the deteriorating Changtongya–Longleng two-lane road and sought a detailed status report on the stalled construction within one week. The demand followed a consultative meeting convened under the Phom Peoples' Council (PPC) to discuss welfare and development concerns. PPC president YB Angam Phom said prolonged non-maintenance had caused hardship to commuters and affected transportation, local commerce and the district's development. The meeting urged authorities to undertake immediate restoration a..

    Advertisement

    Subscribe to Our Newsletter

    Get daily newsletters around different themes from Construction world.

    STAY CONNECTED

    Advertisement

    Advertisement

    Advertisement