ISTS-TBCB Projects Award Rs1 Trillion in 9MFY25
POWER & RENEWABLE ENERGY

ISTS-TBCB Projects Award Rs1 Trillion in 9MFY25

India Ratings and Research (Ind-Ra) has maintained a Stable rating outlook for transmission projects for FY26, supported by consistent regulations and expectations of steady operational performance. The agency highlighted significant capital expenditure plans and project awards during the first nine months of FY25 as major positives for the sector.

Among 58 commissioned projects, only eight were completed on schedule, while the rest experienced an average delay of nine months. The Central Electricity Regulatory Commission (CERC) has been granting time extensions for delays caused by force majeure events, including route changes and approval setbacks.

The Inter-State Transmission System (ISTS) under the tariff-based competitive bidding (TBCB) framework witnessed the awarding of 37 projects in the first nine months of FY25, with a combined capital outlay of Rs 1,016.75 billion. This represents an increase compared to the cumulative Rs 808.93 billion capital outlay for all TBCB projects completed between FY14 and the first eight months of FY25.

Ind-Ra reported that the Power Grid Corporation of India Limited secured over 65% of awards in the ISTS-TBCB segment during FY25. The entry of new players into the segment has broadened the developer base, which the agency believes could enhance the value chain and reduce transmission costs for designated ISTS customers.

The credit profile of operational ISTS assets remains stable, aided by CERC’s Sharing Regulations 2020, which provide a revenue-sharing mechanism and mitigate counterparty risks. Annual collection efficiency for these assets is projected to exceed 95%. However, intrastate assets in states such as Maharashtra, Uttar Pradesh, and Rajasthan exhibited moderate collection volatility during the first half of FY25.

Ind-Ra noted that amendments to the Sharing Regulations in October 2023 introduced new revenue mechanisms for ISTS assets in deemed commercial operations date (COD) status. However, these projects face higher counterparty risks due to an unproven record of timely revenue collection.

India Ratings and Research (Ind-Ra) has maintained a Stable rating outlook for transmission projects for FY26, supported by consistent regulations and expectations of steady operational performance. The agency highlighted significant capital expenditure plans and project awards during the first nine months of FY25 as major positives for the sector. Among 58 commissioned projects, only eight were completed on schedule, while the rest experienced an average delay of nine months. The Central Electricity Regulatory Commission (CERC) has been granting time extensions for delays caused by force majeure events, including route changes and approval setbacks. The Inter-State Transmission System (ISTS) under the tariff-based competitive bidding (TBCB) framework witnessed the awarding of 37 projects in the first nine months of FY25, with a combined capital outlay of Rs 1,016.75 billion. This represents an increase compared to the cumulative Rs 808.93 billion capital outlay for all TBCB projects completed between FY14 and the first eight months of FY25. Ind-Ra reported that the Power Grid Corporation of India Limited secured over 65% of awards in the ISTS-TBCB segment during FY25. The entry of new players into the segment has broadened the developer base, which the agency believes could enhance the value chain and reduce transmission costs for designated ISTS customers. The credit profile of operational ISTS assets remains stable, aided by CERC’s Sharing Regulations 2020, which provide a revenue-sharing mechanism and mitigate counterparty risks. Annual collection efficiency for these assets is projected to exceed 95%. However, intrastate assets in states such as Maharashtra, Uttar Pradesh, and Rajasthan exhibited moderate collection volatility during the first half of FY25. Ind-Ra noted that amendments to the Sharing Regulations in October 2023 introduced new revenue mechanisms for ISTS assets in deemed commercial operations date (COD) status. However, these projects face higher counterparty risks due to an unproven record of timely revenue collection.

Next Story
Real Estate

CRDA Approves Rs 17.32 Bn Tenders for Housing and Infra

The Capital Region Development Authority (CRDA), during its forty-seventh meeting chaired by Chief Minister N. Chandrababu Naidu, approved tenders worth Rs 17.32 billion to develop key infrastructure in Amaravati’s core capital area.Municipal Administration and Urban Development Minister Ponguru Narayana announced that Rs 5.14 billion was sanctioned for completing gazetted officers’ towers initiated between 2014 and 2019. In addition, Rs 1.94 billion was approved for external infrastructure, Rs 5.07 billion for nine towers for non-gazetted employees, and Rs 5.17 billion for twelve new towe..

Next Story
Real Estate

Prestige Estates Nets Rs 30 Bn in NCR Debut Launch

Prestige Estates Projects Limited has recorded sales of over Rs 30 billion within one week of launching its first residential project in the National Capital Region (NCR). The project, The Prestige City, located in Indirapuram Extension on National Highway twenty-four, sold one thousand two hundred units during its initial launch phase.This marks the Bengaluru-based developer’s maiden entry into NCR’s residential real estate market. The company attributes the strong response to brand trust, strategic location, and rising demand for premium, planned communities.The launch covered two reside..

Next Story
Infrastructure Transport

Palakkad Railway Division Upgrades Turnouts for Safety

The Southern Railway’s Palakkad Division has implemented a series of infrastructure upgrades to enhance train safety and operational efficiency. Over the past one year, the division has replaced one hundred thirty-three ageing fifty-two kilogram turnouts with robust sixty kilogram Thick Web Switches, engineered for high-speed durability and increased strength.Seventy-seven track layouts were corrected using advanced computer-based geometry solutions, involving precise longitudinal and lateral alignment with the aid of the T-28 Track Relaying Machine. These corrections improve track stability..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?