Kilambakkam Skywalk Construction Resumes After Revision
ECONOMY & POLICY

Kilambakkam Skywalk Construction Resumes After Revision

Work on the much-anticipated pedestrian skywalk connecting Kilambakkam’s Kalaignar Centenary Bus Terminus (KCBT) with a new suburban railway halt station has resumed, following a redesign that resolved long-standing land acquisition disputes. The project, overseen by the Chennai Unified Metropolitan Transport Authority (CUMTA), aims to enhance last-mile connectivity and boost multi-modal transport integration in South Chennai.

Originally envisioned as a 275-metre-long skywalk supported by 55 structural grids, the project was stalled due to legal challenges from landowners opposing the acquisition of nearly one acre of private land. A stay order from the Madras High Court halted construction activities along GST Road. To address the impasse, CUMTA reworked the alignment to reduce dependency on private land. The revised design now requires only 55% of the initially contested land, with the owner agreeing to the revised terms.

According to I Jayakumar, Special Officer at CUMTA, “Construction is underway alongside land acquisition. We have redesigned the segment between 20 and 100 metres to align with the new land boundary conditions, and structural consultants are working on updated plans.”

The new skywalk, now 450 metres long, will connect the Rs 393 crore KCBT—one of South Chennai’s largest intercity transport hubs—with the new halt station located approximately 200 metres away. The infrastructure is being developed by the Chennai Metropolitan Development Authority (CMDA) and includes lifts, escalators, and staircases to ensure frictionless movement between bus and rail systems.

With the North-East Monsoon approaching, officials are targeting an inauguration in the first week of October. Should weather conditions delay progress, the revised deadline extends to December 2025. The Rs 100 crore skywalk is seen as a key step towards transforming Kilambakkam into a seamless transport interchange that reduces road congestion, lowers reliance on feeder buses, and provides accessibility to long-distance and daily commuters.

Work on the much-anticipated pedestrian skywalk connecting Kilambakkam’s Kalaignar Centenary Bus Terminus (KCBT) with a new suburban railway halt station has resumed, following a redesign that resolved long-standing land acquisition disputes. The project, overseen by the Chennai Unified Metropolitan Transport Authority (CUMTA), aims to enhance last-mile connectivity and boost multi-modal transport integration in South Chennai.Originally envisioned as a 275-metre-long skywalk supported by 55 structural grids, the project was stalled due to legal challenges from landowners opposing the acquisition of nearly one acre of private land. A stay order from the Madras High Court halted construction activities along GST Road. To address the impasse, CUMTA reworked the alignment to reduce dependency on private land. The revised design now requires only 55% of the initially contested land, with the owner agreeing to the revised terms.According to I Jayakumar, Special Officer at CUMTA, “Construction is underway alongside land acquisition. We have redesigned the segment between 20 and 100 metres to align with the new land boundary conditions, and structural consultants are working on updated plans.”The new skywalk, now 450 metres long, will connect the Rs 393 crore KCBT—one of South Chennai’s largest intercity transport hubs—with the new halt station located approximately 200 metres away. The infrastructure is being developed by the Chennai Metropolitan Development Authority (CMDA) and includes lifts, escalators, and staircases to ensure frictionless movement between bus and rail systems.With the North-East Monsoon approaching, officials are targeting an inauguration in the first week of October. Should weather conditions delay progress, the revised deadline extends to December 2025. The Rs 100 crore skywalk is seen as a key step towards transforming Kilambakkam into a seamless transport interchange that reduces road congestion, lowers reliance on feeder buses, and provides accessibility to long-distance and daily commuters.

Next Story
Infrastructure Energy

Rajesh Power Secures 65 MW BESS Project in Gujarat

Rajesh Power Services has recently secured a 65 MW / 130 MWh standalone Battery Energy Storage System (BESS) project in Gujarat, marking its entry into utility-scale energy storage. The company received a Letter of Intent from Gujarat Urja Vikas Nigam for the project, which will be developed at Virpore under a tariff-based competitive bidding mechanism supported by Viability Gap Funding through the Power System Development Fund.The project is expected to be executed within 18 months from the signing of the Battery Energy Storage Purchase Agreement. With the ability to supply 65 MW of power for..

Next Story
Infrastructure Energy

ONGC Forms JV with MOL for Ethane Shipping Operations

Oil and Natural Gas Corporation (Oil and Natural Gas Corporation) has recently entered the ethane shipping segment through joint venture agreements with M/s Mitsui O.S.K. Lines Ltd (Mitsui O.S.K. Lines), Japan. The agreements involve equity participation in two joint venture entities—Bharat Ethane One IFSC Private Limited and Bharat Ethane Two IFSC Private Limited—registered at GIFT City, Gandhinagar.Under the arrangement, ONGC will subscribe to 2,00,000 equity shares of Rs 100 each in both entities, resulting in a 50 per cent equity holding in each joint venture, with the remaining stake ..

Next Story
Infrastructure Energy

Waaree Energy Storage Raises Rs 10.03 Billio for 20 GWh Plant

Waaree Energy Storage Solutions Private, a subsidiary of Waaree Energies, has recently completed a strategic fund raise of around Rs 10.03 billion from a group of strategic investors, including family offices, high-net-worth individuals and institutional backers. The funding strengthens the company’s position in India’s rapidly expanding energy storage ecosystem.The capital raise forms part of an announced capital expenditure programme of nearly Rs 100 billion for setting up a 20 GWh advanced lithium-ion cell and battery pack manufacturing facility. The plant will manufacture high-performa..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Open In App