May sees Rs 4.8 trillion cost overruns in 408 projects
ECONOMY & POLICY

May sees Rs 4.8 trillion cost overruns in 408 projects

A total of 408 infrastructure projects, each requiring an investment of Rs 1.5 billion or more, had experienced cost overruns exceeding Rs 4.8 trillion in May 2023. The Ministry of Statistics and Programme Implementation, responsible for monitoring infrastructure projects valued at Rs 1.5 billion and above, reported that out of a total of 1,681 projects, 408 projects had cost overruns and 814 projects had faced delays.

The Ministry's latest report for May 2023 revealed that the initial cost of implementing the 1,681 projects was Rs 24.16 trillion. However, the anticipated completion cost was estimated to be Rs 28.96 trillion, indicating an overall cost overrun of Rs 4.8 trillion, which accounted for 19.86% of the original cost. As of May 2023, the total expenditure incurred on these projects amounted to Rs 15.23 trillion, which was 52.61% of the anticipated project cost.

In the March quarter, a total of 384 infrastructure projects encountered cost overruns amounting to Rs 4.6 trillion crore. However, the number of delayed projects decreased to 607 when considering the latest completion schedule. Additionally, the report noted that for 419 projects, neither the year of commissioning nor the estimated gestation period had been reported.

Out of the 814 projects that experienced delays, 200 projects faced delays ranging from 1 to 12 months, 183 projects were delayed for 13 to 24 months, 300 projects were delayed for 25 to 60 months, and 131 projects were delayed for more than 60 months. The average time overrun for these 814 delayed projects was 37.04 months. Project implementing agencies cited various reasons for the time overruns, including delays in land acquisition, obtaining forest and environment clearances, and inadequate infrastructure support and linkages. Other factors contributing to delays included delays in securing project financing, finalising detailed engineering, changes in project scope, tendering, ordering and equipment supply, as well as law and order issues.

The report also highlighted that the implementation of these projects was hindered by state-wise lockdowns imposed due to COVID-19 in 2020 and 2021.

Also read:
Amazon to Invest $15 Billion in India by 2030
L&T, DRDO ink deal for Scorpene submarines' AIP modules


A total of 408 infrastructure projects, each requiring an investment of Rs 1.5 billion or more, had experienced cost overruns exceeding Rs 4.8 trillion in May 2023. The Ministry of Statistics and Programme Implementation, responsible for monitoring infrastructure projects valued at Rs 1.5 billion and above, reported that out of a total of 1,681 projects, 408 projects had cost overruns and 814 projects had faced delays. The Ministry's latest report for May 2023 revealed that the initial cost of implementing the 1,681 projects was Rs 24.16 trillion. However, the anticipated completion cost was estimated to be Rs 28.96 trillion, indicating an overall cost overrun of Rs 4.8 trillion, which accounted for 19.86% of the original cost. As of May 2023, the total expenditure incurred on these projects amounted to Rs 15.23 trillion, which was 52.61% of the anticipated project cost. In the March quarter, a total of 384 infrastructure projects encountered cost overruns amounting to Rs 4.6 trillion crore. However, the number of delayed projects decreased to 607 when considering the latest completion schedule. Additionally, the report noted that for 419 projects, neither the year of commissioning nor the estimated gestation period had been reported. Out of the 814 projects that experienced delays, 200 projects faced delays ranging from 1 to 12 months, 183 projects were delayed for 13 to 24 months, 300 projects were delayed for 25 to 60 months, and 131 projects were delayed for more than 60 months. The average time overrun for these 814 delayed projects was 37.04 months. Project implementing agencies cited various reasons for the time overruns, including delays in land acquisition, obtaining forest and environment clearances, and inadequate infrastructure support and linkages. Other factors contributing to delays included delays in securing project financing, finalising detailed engineering, changes in project scope, tendering, ordering and equipment supply, as well as law and order issues. The report also highlighted that the implementation of these projects was hindered by state-wise lockdowns imposed due to COVID-19 in 2020 and 2021. Also read: Amazon to Invest $15 Billion in India by 2030L&T, DRDO ink deal for Scorpene submarines' AIP modules

Next Story
Infrastructure Transport

Lack of Bidders Stalls VOC Port’s Rs 70.56 Bn Harbour Project Again

The VOC Port Authority’s Rs 70.56 billion outer harbour project has once again faced a setback, with the latest tender process cancelled due to the absence of qualified bidders. This marks the second failed attempt to secure participation for the mega infrastructure initiative.The tender has reportedly been withdrawn from the active list of bids, and the authority is now expected to re-evaluate and possibly restructure the project to enhance its appeal to potential developers.The port authority had initially floated the Request for Proposal (RFP) in December 2024, following the cancellation ..

Next Story
Infrastructure Transport

Sea Lord Containers Opens Cryogenic LPG Terminal in Mangalore

Sea Lord Containers (SCL), a wholly-owned subsidiary of Aegis Logistics, has commissioned a new cryogenic Liquified Petroleum Gas (LPG) terminal in Mangalore. The facility, which became operational on 12 June 2025, offers a static storage capacity of 82,000 metric tons (MT), significantly strengthening the region’s LPG logistics infrastructure.The terminal was developed by SCL on behalf of Aegis Vopak Terminals, an associate company of Aegis Logistics. The asset is expected to be transferred to Aegis Vopak Terminals Limited at a later date, with formal updates to be shared separately with st..

Next Story
Infrastructure Urban

Cochin Port and Oil India Partner for Offshore Exploration Support

The Cochin Port Authority (CoPA) has signed a Memorandum of Understanding (MoU) with Oil India (OIL) to establish a shore base facility supporting offshore oil exploration in the Kerala-Konkan Basin. The agreement was formalised at a ceremony held at CoPA, Willingdon Island, on 12 June 2025, in the presence of senior officials from both organisations.Under the partnership, Cochin Port will provide critical logistics infrastructure for OIL’s offshore drilling operations, expected to begin later in 2025. The planned shore base will include a dedicated warehouse, dry bulk handling plant, and an..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?