May sees Rs 4.8 trillion cost overruns in 408 projects
ECONOMY & POLICY

May sees Rs 4.8 trillion cost overruns in 408 projects

A total of 408 infrastructure projects, each requiring an investment of Rs 1.5 billion or more, had experienced cost overruns exceeding Rs 4.8 trillion in May 2023. The Ministry of Statistics and Programme Implementation, responsible for monitoring infrastructure projects valued at Rs 1.5 billion and above, reported that out of a total of 1,681 projects, 408 projects had cost overruns and 814 projects had faced delays.

The Ministry's latest report for May 2023 revealed that the initial cost of implementing the 1,681 projects was Rs 24.16 trillion. However, the anticipated completion cost was estimated to be Rs 28.96 trillion, indicating an overall cost overrun of Rs 4.8 trillion, which accounted for 19.86% of the original cost. As of May 2023, the total expenditure incurred on these projects amounted to Rs 15.23 trillion, which was 52.61% of the anticipated project cost.

In the March quarter, a total of 384 infrastructure projects encountered cost overruns amounting to Rs 4.6 trillion crore. However, the number of delayed projects decreased to 607 when considering the latest completion schedule. Additionally, the report noted that for 419 projects, neither the year of commissioning nor the estimated gestation period had been reported.

Out of the 814 projects that experienced delays, 200 projects faced delays ranging from 1 to 12 months, 183 projects were delayed for 13 to 24 months, 300 projects were delayed for 25 to 60 months, and 131 projects were delayed for more than 60 months. The average time overrun for these 814 delayed projects was 37.04 months. Project implementing agencies cited various reasons for the time overruns, including delays in land acquisition, obtaining forest and environment clearances, and inadequate infrastructure support and linkages. Other factors contributing to delays included delays in securing project financing, finalising detailed engineering, changes in project scope, tendering, ordering and equipment supply, as well as law and order issues.

The report also highlighted that the implementation of these projects was hindered by state-wise lockdowns imposed due to COVID-19 in 2020 and 2021.

Also read:
Amazon to Invest $15 Billion in India by 2030
L&T, DRDO ink deal for Scorpene submarines' AIP modules


A total of 408 infrastructure projects, each requiring an investment of Rs 1.5 billion or more, had experienced cost overruns exceeding Rs 4.8 trillion in May 2023. The Ministry of Statistics and Programme Implementation, responsible for monitoring infrastructure projects valued at Rs 1.5 billion and above, reported that out of a total of 1,681 projects, 408 projects had cost overruns and 814 projects had faced delays. The Ministry's latest report for May 2023 revealed that the initial cost of implementing the 1,681 projects was Rs 24.16 trillion. However, the anticipated completion cost was estimated to be Rs 28.96 trillion, indicating an overall cost overrun of Rs 4.8 trillion, which accounted for 19.86% of the original cost. As of May 2023, the total expenditure incurred on these projects amounted to Rs 15.23 trillion, which was 52.61% of the anticipated project cost. In the March quarter, a total of 384 infrastructure projects encountered cost overruns amounting to Rs 4.6 trillion crore. However, the number of delayed projects decreased to 607 when considering the latest completion schedule. Additionally, the report noted that for 419 projects, neither the year of commissioning nor the estimated gestation period had been reported. Out of the 814 projects that experienced delays, 200 projects faced delays ranging from 1 to 12 months, 183 projects were delayed for 13 to 24 months, 300 projects were delayed for 25 to 60 months, and 131 projects were delayed for more than 60 months. The average time overrun for these 814 delayed projects was 37.04 months. Project implementing agencies cited various reasons for the time overruns, including delays in land acquisition, obtaining forest and environment clearances, and inadequate infrastructure support and linkages. Other factors contributing to delays included delays in securing project financing, finalising detailed engineering, changes in project scope, tendering, ordering and equipment supply, as well as law and order issues. The report also highlighted that the implementation of these projects was hindered by state-wise lockdowns imposed due to COVID-19 in 2020 and 2021. Also read: Amazon to Invest $15 Billion in India by 2030L&T, DRDO ink deal for Scorpene submarines' AIP modules

Next Story
Infrastructure Energy

India Adds Record 44.61 GW Solar Capacity in FY2026

India’s solar sector reached a milestone in FY2026, with cumulative installed capacity crossing 150 GW and annual additions hitting a record 44.61 GW, exceeding the government target of 34 GW and nearly doubling FY2025’s 23.83 GW. Distributed Renewable Energy contributed 16.3 GW, while PPA and C&I segments accounted for 34 per cent and 30 per cent, respectively.India has risen from 9th globally in 2015 to 3rd in cumulative solar capacity by 2025 and is set to become the world’s second-largest solar market in annual installations in 2026. Seven states, led by Rajasthan and Gujarat, ac..

Next Story
Real Estate

Abhee Ventures unveils Scottish-themed 45-acre township in Bengaluru

Abhee Ventures, a leading South Indian real estate developer, has announced “Codename New Dimension,” a 45-acre Scottish-themed residential township at Gunjur on Whitefield–Sarjapur Road, Bengaluru. Strategically located between Whitefield and Sarjapur Road, Gunjur benefits from strong connectivity to the Outer Ring Road IT corridor, ITPL, EPIP, the upcoming Dommasandra Metro Station, and the proposed SWIFT City and Peripheral Ring Road.The township, designed in collaboration with London-based UHA London and India’s RSP Architects, offers low-density living with 85 per cent open spaces..

Next Story
Infrastructure Urban

Hindalco unveils Eternia experience centre for high-performance aluminium windows

Hindalco Industries, the metals flagship of the Aditya Birla Group, has launched its Eternia experience centre in Lajpat Nagar, New Delhi, highlighting its high-performance aluminium window systems designed for India’s evolving construction sector. The company is also expanding its manufacturing footprint in North India with a new Bilaspur facility.Eternia has emerged as one of the fastest-growing brands in system aluminium windows, registering nearly 65 per cent CAGR over the last three years. With a nationwide network of 170+ channel partners across 100+ cities, the brand serves homeowners..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement