We built our own capabilities to control execution
ECONOMY & POLICY

We built our own capabilities to control execution

With project timelines becoming increasingly demanding, EPC execution requires tighter control across design, approvals, procurement and site execution. For Enviro Infra Engineers, this has meant strengthening inhouse capabilities, using semi-automated project monitoring and adapting its workforce and machinery deployment to changing site conditions. Manish Jain, Managing Director, discusses project execution, technology adoption, vendor selection and the company’s approach to delivering water and wastewater projects, in conversation with KAVITA PARAB.

Large infrastructure projects often face pressure on timelines. How do you scale project management, engineering, procurement and site execution without compromising delivery?

The first priority when a project is awarded is to understand the timeline available for execution. While we are generally conversant with the normal timelines required, there are instances where the Government requires accelerated execution. In such cases, the first step is to revisit the planning. Design and approvals are critical because delays can occur at multiple stages. The design has to be completed and approved by the client; the PMC may then vet the technical documents, followed in some cases by review by an engineering college. These are three potential points of delay.

To read the full article Click Here

With project timelines becoming increasingly demanding, EPC execution requires tighter control across design, approvals, procurement and site execution. For Enviro Infra Engineers, this has meant strengthening inhouse capabilities, using semi-automated project monitoring and adapting its workforce and machinery deployment to changing site conditions. Manish Jain, Managing Director, discusses project execution, technology adoption, vendor selection and the company’s approach to delivering water and wastewater projects, in conversation with KAVITA PARAB.Large infrastructure projects often face pressure on timelines. How do you scale project management, engineering, procurement and site execution without compromising delivery?The first priority when a project is awarded is to understand the timeline available for execution. While we are generally conversant with the normal timelines required, there are instances where the Government requires accelerated execution. In such cases, the first step is to revisit the planning. Design and approvals are critical because delays can occur at multiple stages. The design has to be completed and approved by the client; the PMC may then vet the technical documents, followed in some cases by review by an engineering college. These are three potential points of delay.To read the full article Click Here

Related Stories

Gold Stories

Next Story
Infrastructure Energy

Vedanta Eyes AI to Accelerate Mineral Exploration

Vedanta Group is exploring the use of artificial intelligence (AI) to significantly improve efficiency in mineral exploration, geological analysis and resource modelling. The company aims to reduce exploration processes that traditionally take three to four months to just six to seven days through AI-driven technologies.The proposed approach involves AI-led geological analysis and mineral block modelling to accelerate mineral resource assessment and support faster, more cost-efficient development of domestic mineral reserves. The initiative aligns with India's growing focus on critical mineral..

Next Story
Technology

NXP Launches Unified Robotics Platform for Physical AI

NXP Semiconductors has launched a unified robotics platform designed to accelerate the development and deployment of trusted physical artificial intelligence (AI) systems. Built on the company's neural axis architecture, the platform integrates AI processing, connectivity, motor control, security and energy management within a common hardware and software ecosystem.The platform combines an open-source, modular software development kit (SDK) with pre-validated reference designs, enabling developers to build robotic systems more efficiently. It supports development ranging from individual subsys..

Next Story
Technology

Hindalco Hosts 44th ICSOBA Aluminium Conference in Bengaluru

Hindalco Industries, the metals flagship of the Aditya Birla Group, is hosting the 44th International Conference and Exhibition of the International Committee for Study of Bauxite, Alumina and Aluminium (ICSOBA) in Bengaluru from 15 to 20 November 2026.The conference brings together global aluminium producers, technology providers, researchers and industry experts to discuss technological advancements, sustainability and emerging opportunities across the aluminium value chain.Featuring more than 160 technical papers, nine keynote presentations and four parallel technical streams, the event foc..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code