Mumbai's Coastal Road project revs up
ROADS & HIGHWAYS

Mumbai's Coastal Road project revs up

The Municipal Corporation of Greater Mumbai's (MCGM) ambitious Mumbai Coastal Road project is revving up with a geological investigation being ordered by MCGM Commissioner Ajoy Mehta. Besides, final designs of the tunnel, bridges and jetty are also expected for the submission. 
A geological investigation is conducted mainly to ascertain the type of soil and rock that will help understand how deep the foundation could go. As of now, rock samples have been sent for testing and photographical survey has started, reveals a MCGM official on grounds of anonymity. 

At a glimpse
Categorised into three packages – Package-1, Package-2 and Package-4 – MCGM has divided the 9.98-km south Mumbai phase from Princess Street flyover to the south end of the Bandra-Worli Sea Link; construction work on all packages will begin simultaneously. Package-1 from Priyadarshani Park to Baroda Palace and Package-4 from Princess Street Flyover to Priyadarshini Park have been awarded to Larsen & Toubro (L&T); while Package-2, which starts from Baroda Palace up to the end of the Bandra-Worli Sea Link, has been awarded to Hindustan Construction Company (HCC) in a JV with Hyundai Development Corporation. Separate bids were invited for each of these three packages.
Package-1 reportedly involves the construction of a 3.82-km, eight-lane highway over reclaimed land from Priyadarshini Park to Baroda Palace, including interchanges at Amarson Garden and Haji Ali. 
The Haji Ali interchange is also expected to be a multilevel interchange inside Haji Ali bay, providing connectivity to the existing Khan Abdul Gaffar Khan Road. Package-4 involves the construction of up-and-down ramps from Marine Drive connecting to the underground road (twin) tunnel, which will pass below Girgaum Chowpatty and Malabar Hills and exit at Priyadarshini Park, connecting to Package-1.
Being a design-and-build contract, the project has been awarded to the contractor who will be working on the design. According to the official, these designs will then get approval from a general consultant appointed by the MCGM, while the project managing consultant will directly supervise the site.

Easing traffic woes
The Coastal Road is expected to be a mix of features such as tunnels, bridges, interchanges, elevated stretches and roads on reclaimed land, along with pedestrian underpasses and foot-over-bridges.
The road, which will run along the city’s western seafront, aims to provide swift travel from the western suburbs to south Mumbai, decongesting traffic in the city by connecting Marine Drive in the south to Kandivili in the north. 
The MCGM has stated that the project will save 70 per cent travelling time and 34 per cent fuel every year. Speaking exclusively with the CW team at an event in Mumbai, Ajoy Mehta, Municipal Commissioner, MCGM, said, “The Coastal Road project is a huge engineering feat undertaken by corporation engineers in terms of design and everything else, and it will surely ease traffic and make Mumbai a better place.” 

Up next!
Also, in a recent development, the Rs 70 billion contract for the 17-km Bandra-Versova Sea Link – which will eventually become a part of the total Coastal Road Project and is being handled separately by Maharashtra State Road Development Corporation – was recently awarded to Reliance Infrastructure. Undoubtedly, Mumbai is geared up for its next engineering feat!

The Municipal Corporation of Greater Mumbai's (MCGM) ambitious Mumbai Coastal Road project is revving up with a geological investigation being ordered by MCGM Commissioner Ajoy Mehta. Besides, final designs of the tunnel, bridges and jetty are also expected for the submission.  A geological investigation is conducted mainly to ascertain the type of soil and rock that will help understand how deep the foundation could go. As of now, rock samples have been sent for testing and photographical survey has started, reveals a MCGM official on grounds of anonymity.  At a glimpse Categorised into three packages – Package-1, Package-2 and Package-4 – MCGM has divided the 9.98-km south Mumbai phase from Princess Street flyover to the south end of the Bandra-Worli Sea Link; construction work on all packages will begin simultaneously. Package-1 from Priyadarshani Park to Baroda Palace and Package-4 from Princess Street Flyover to Priyadarshini Park have been awarded to Larsen & Toubro (L&T); while Package-2, which starts from Baroda Palace up to the end of the Bandra-Worli Sea Link, has been awarded to Hindustan Construction Company (HCC) in a JV with Hyundai Development Corporation. Separate bids were invited for each of these three packages. Package-1 reportedly involves the construction of a 3.82-km, eight-lane highway over reclaimed land from Priyadarshini Park to Baroda Palace, including interchanges at Amarson Garden and Haji Ali.  The Haji Ali interchange is also expected to be a multilevel interchange inside Haji Ali bay, providing connectivity to the existing Khan Abdul Gaffar Khan Road. Package-4 involves the construction of up-and-down ramps from Marine Drive connecting to the underground road (twin) tunnel, which will pass below Girgaum Chowpatty and Malabar Hills and exit at Priyadarshini Park, connecting to Package-1. Being a design-and-build contract, the project has been awarded to the contractor who will be working on the design. According to the official, these designs will then get approval from a general consultant appointed by the MCGM, while the project managing consultant will directly supervise the site. Easing traffic woes The Coastal Road is expected to be a mix of features such as tunnels, bridges, interchanges, elevated stretches and roads on reclaimed land, along with pedestrian underpasses and foot-over-bridges. The road, which will run along the city’s western seafront, aims to provide swift travel from the western suburbs to south Mumbai, decongesting traffic in the city by connecting Marine Drive in the south to Kandivili in the north.  The MCGM has stated that the project will save 70 per cent travelling time and 34 per cent fuel every year. Speaking exclusively with the CW team at an event in Mumbai, Ajoy Mehta, Municipal Commissioner, MCGM, said, “The Coastal Road project is a huge engineering feat undertaken by corporation engineers in terms of design and everything else, and it will surely ease traffic and make Mumbai a better place.”  Up next! Also, in a recent development, the Rs 70 billion contract for the 17-km Bandra-Versova Sea Link – which will eventually become a part of the total Coastal Road Project and is being handled separately by Maharashtra State Road Development Corporation – was recently awarded to Reliance Infrastructure. Undoubtedly, Mumbai is geared up for its next engineering feat!

Next Story
Infrastructure Transport

Dassault To Build Falcon Jets In India With Reliance

Reliance Infrastructure Ltd’s subsidiary, Reliance Aerostructure, has signed an agreement with France’s Dassault Aviation to manufacture Falcon 2000 business jets in India, with the first batch expected to roll out from its Nagpur facility by 2028. This marks the first time a Falcon aircraft will be entirely built outside France.The announcement sent Reliance Infrastructure shares surging, hitting the 5 per cent upper circuit on the BSE. Anil Ambani, Chairman of Reliance Group, hailed the agreement as a “symbol of India’s technological and manufacturing strength”, adding that it aims..

Next Story
Infrastructure Urban

INDEA Lays Foundation for India’s First Auto Design School

The Indian School for Design of Automobiles (INDEA), the country’s first institute focused solely on automobile design and management, held its foundation stone ceremony at XLRI Delhi-NCR. The event was graced by Union Minister for Road Transport and Highways, Nitin Gadkari, who virtually unveiled the stone as Chief Guest.INDEA aims to become a premier talent hub, driving innovation in the Indian automotive sector. The school will focus on advanced design, mobility solutions, and sustainable practices, playing a vital role in shaping India’s transition from a cost-driven to a quality-led a..

Next Story
Infrastructure Transport

Karnataka Launches Global Innovation Hub at Airport City

The Government of Karnataka, in collaboration with Bengaluru Airport City Limited (BACL) and ANSR, has launched a global innovation hub named District I at Bengaluru Airport City's business park. The initiative aims to elevate India’s innovation ecosystem to a global scale by fostering collaboration among startups, academia, enterprises, and government bodies.District I will serve as a platform for deep-tech entrepreneurship, enterprise innovation, and commercialisation of academic research. It brings together Global Capability Centres (GCCs), IT firms, corporate labs, startups, venture capi..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?