13-km Zojila tunnel expected to be completed by 2026-end
ROADS & HIGHWAYS

13-km Zojila tunnel expected to be completed by 2026-end

The work on the Zojila tunnel is in full swing in order to restore Jammu and Kashmir's road connectivity to Ladakh in all seasons, and it is expected to be completed by the end of 2026.

Harpal Singh, project manager for Megha Engineering and Infrastructure Constructions Limited (MIL), which is building the 13-kilometre-long Zojila Tunnel, stated “The construction of the tunnel is going on in full swing and is expected that it should be dedicated to the people at the end of 2026.”

According to him, once the final tube of the Zojila project is completed, the 32-kilometre distance between Sonmarg and Minamarg will be covered in less than 40 minutes rather than four hours. Aside from that, the all-weather connectivity will be extremely beneficial to the deployed forces and the people of Ladakh.

He added, “Though the tunnel was announced in 2005, the project was later delayed. The company that got the job went bankrupt and the work was suspended for almost two years. After which the Central government made some changes in the project and restarted the work in 2020 and awarded its tender to MIL.”

Regarding the difficulties encountered during tunnel construction, he stated that “Kashmir is very cold, the temperature is negative, despite this, and 1,000 people are working day and night on this project.”

He stated that the work on the so-called Badalto tunnel will be doubled now; currently, around 2300 people work here, the majority of who are local (Jammu and Kashmir) citizens. He said that all precautions have been taken with regard to the work completed thus far.

This project includes three tunnels: Nilgarar-1 and Nilgarar-2, each with two tunnels. All four tunnels are nearly finished. There are four pools in addition to this. All of them are nearly finished. Following that, the 13-kilometre-long Zojila tunnel will be completed. The road and tunnels on Nilgarar-1 and Nilgarar-2 are still being plastered.

The tunnel's completion will restore Jammu and Kashmir's road connectivity to Ladakh throughout the year, boosting the Ladakh economy and providing people with all essentials regardless of how much snow there is in winter.

See also:
Transport minister reviews Zojila tunnel construction work
MEIL to complete Zojila tunnel project ahead of completion deadline


The work on the Zojila tunnel is in full swing in order to restore Jammu and Kashmir's road connectivity to Ladakh in all seasons, and it is expected to be completed by the end of 2026. Harpal Singh, project manager for Megha Engineering and Infrastructure Constructions Limited (MIL), which is building the 13-kilometre-long Zojila Tunnel, stated “The construction of the tunnel is going on in full swing and is expected that it should be dedicated to the people at the end of 2026.” According to him, once the final tube of the Zojila project is completed, the 32-kilometre distance between Sonmarg and Minamarg will be covered in less than 40 minutes rather than four hours. Aside from that, the all-weather connectivity will be extremely beneficial to the deployed forces and the people of Ladakh. He added, “Though the tunnel was announced in 2005, the project was later delayed. The company that got the job went bankrupt and the work was suspended for almost two years. After which the Central government made some changes in the project and restarted the work in 2020 and awarded its tender to MIL.” Regarding the difficulties encountered during tunnel construction, he stated that “Kashmir is very cold, the temperature is negative, despite this, and 1,000 people are working day and night on this project.” He stated that the work on the so-called Badalto tunnel will be doubled now; currently, around 2300 people work here, the majority of who are local (Jammu and Kashmir) citizens. He said that all precautions have been taken with regard to the work completed thus far. This project includes three tunnels: Nilgarar-1 and Nilgarar-2, each with two tunnels. All four tunnels are nearly finished. There are four pools in addition to this. All of them are nearly finished. Following that, the 13-kilometre-long Zojila tunnel will be completed. The road and tunnels on Nilgarar-1 and Nilgarar-2 are still being plastered. The tunnel's completion will restore Jammu and Kashmir's road connectivity to Ladakh throughout the year, boosting the Ladakh economy and providing people with all essentials regardless of how much snow there is in winter. See also: Transport minister reviews Zojila tunnel construction work MEIL to complete Zojila tunnel project ahead of completion deadline

Next Story
Real Estate

India's first AI-integrated campus announced in Noida

Yashoda Hospital and Bhutani Infra have announced plans to develop India’s first fully AI-integrated mixed-use campus in Greater Noida West. The upcoming project will feature a hospital, retail spaces, offices, SOHOs, serviced apartments, and a hotel—all operating within a self-learning, generative AI-powered ecosystem.The AI-first campus will integrate real-time data systems, predictive analytics, and adaptive infrastructure to offer personalised experiences across functions. From AI-enabled footfall tracking and dynamic energy optimisation to smart F&B and retail insights, the develo..

Next Story
Real Estate

New Mall Supply to Touch 1.54 Bn Sq. Ft. by 2026 in Top Cities

Häfele has introduced its new Matrix range of undermount runners, designed to enhance drawer motion across kitchens, wardrobes, bathroom units, and more.Available in four weight capacities and a wide range of lengths, the Matrix undermount runners support diverse drawer designs. The 40 kg and 60 kg variants feature synchronised technology for superior motion and drawer stability. All runners come with an integrated soft-close mechanism to ensure smooth and noiseless operation.This in-house range is ideal for kitchen cabinets, bed storage units, living room furniture and bathroom drawers, offe..

Next Story
Infrastructure Urban

Postal Dept Unveils Stamp Honouring 125 Years of Kodaikanal Observatory

The Department of Posts is proud to release a commemorative postage stamp celebrating 125 years of the Kodaikanal Solar Observatory (KSO). Recognising the legacy of the KSO through this special stamp is a fitting tribute to one of India’s most significant scientific institutions and highlights the nation’s long-standing contribution to global science.The Commemorative stamp was released by S Rajendra Kumar, Chief Postmaster General, Karnataka Circle in the gracious presence of A S Kiran Kumar, Chairperson, Governing Council, IIA and Former Chairman, ISRO and other esteemed guests at Indian..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?