6 Tunnel Boring Machines Idle in Chennai
RAILWAYS & METRO RAIL

6 Tunnel Boring Machines Idle in Chennai

Six tunnel boring machines (TBMs) deployed by the Chennai Metro Rail Limited (CMRL) are currently lying idle beneath city roads, stuck in limbo due to delayed construction of underground stations at Moolakadai, Perambur, and Mandaveli.

The TBMs, launched as part of Corridor 3 of the Phase II Metro project from Madhavaram to SIPCOT, have reached their designated stations but are unable to proceed as the station boxes are incomplete. Without a completed diaphragm wall or station box, the machines cannot break through or be dismantled for reuse.

According to CMRL officials, the root of the delay traces back to a decision made four years ago, when six tenders for underground station construction along this corridor were scrapped due to high and unreasonable bids. Reissuing the tenders caused a significant time lag, directly affecting the tunneling schedule.

"Though the TBMs started work on time, they were held up because the station construction lagged behind," a CMRL official stated. "Now, the tunneling is done — the machines are just waiting for the stations to catch up."

Two TBMs are stuck at the Moolakadai station, two at Perambur, and two near Mandaveli. They had originated from Madhavaram High Road, Ayanavaram, and Greenways Road, respectively.

In addition to tender issues, officials cited challenges like shifting utilities, relocating borewells, and obtaining traffic diversion permissions as factors that hampered progress.

However, there’s a glimmer of movement ahead. "From next month, the TBMs will gradually begin making breakthroughs, and all six are expected to be out before the end of this year," the official confirmed.

Until then, the machines — each weighing hundreds of tonnes — remain idle beneath Chennai, symbolizing how tendering missteps can slow the wheels of urban transit development.

Image source:themetrorailguy

Six tunnel boring machines (TBMs) deployed by the Chennai Metro Rail Limited (CMRL) are currently lying idle beneath city roads, stuck in limbo due to delayed construction of underground stations at Moolakadai, Perambur, and Mandaveli. The TBMs, launched as part of Corridor 3 of the Phase II Metro project from Madhavaram to SIPCOT, have reached their designated stations but are unable to proceed as the station boxes are incomplete. Without a completed diaphragm wall or station box, the machines cannot break through or be dismantled for reuse. According to CMRL officials, the root of the delay traces back to a decision made four years ago, when six tenders for underground station construction along this corridor were scrapped due to high and unreasonable bids. Reissuing the tenders caused a significant time lag, directly affecting the tunneling schedule. Though the TBMs started work on time, they were held up because the station construction lagged behind, a CMRL official stated. Now, the tunneling is done — the machines are just waiting for the stations to catch up. Two TBMs are stuck at the Moolakadai station, two at Perambur, and two near Mandaveli. They had originated from Madhavaram High Road, Ayanavaram, and Greenways Road, respectively. In addition to tender issues, officials cited challenges like shifting utilities, relocating borewells, and obtaining traffic diversion permissions as factors that hampered progress. However, there’s a glimmer of movement ahead. From next month, the TBMs will gradually begin making breakthroughs, and all six are expected to be out before the end of this year, the official confirmed. Until then, the machines — each weighing hundreds of tonnes — remain idle beneath Chennai, symbolizing how tendering missteps can slow the wheels of urban transit development.Image source:themetrorailguy

Next Story
Building Material

Suraj Estate Wins Euromoney Award for India’s Best Residential Developer

"Suraj Estate Developers Limited has received the Euromoney Real Estate Award 2025 for ‘India’s Best Residential Developer’, positioning the company among globally benchmarked leaders in the sector. The recognition reflects its four-decade legacy in delivering high-quality residential and redevelopment-led projects across South Central Mumbai. The Euromoney Real Estate Awards, presented by the London-based Euromoney magazine, are widely regarded as one of the most credible global assessments of performance in real estate, banking and finance. Winners are selected through surveys of inte..

Next Story
Building Material

Lloyds Metals, Tata Steel Sign MoU to Explore Strategic Collaboration

"Lloyds Metals and Energy Limited has signed a non-binding Memorandum of Understanding with Tata Steel Limited to evaluate potential areas of strategic cooperation across mining, logistics, pelletisation and steelmaking. The MoU was signed by B Prabhakaran, Managing Director of Lloyds Metals, and Mr T V Narendran, CEO and Managing Director of Tata Steel. The partnership framework aims to leverage the natural operational synergies between both companies and assess opportunities in greenfield steel projects, iron ore mining, slurry pipeline infrastructure, pellet manufacturing in iron ore–ric..

Next Story
Building Material

IndiaAI, Gujarat Govt Host Regional Conclave Ahead of 2026 AI Summit

The IndiaAI Mission under the Ministry of Electronics and Information Technology, along with the Government of Gujarat and IIT Gandhinagar, convened a Regional Pre-Summit Event at Mahatma Mandir, Gandhinagar. The initiative is part of the build-up to the India–AI Impact Summit 2026, scheduled for 15–20 February 2026 at Bharat Mandapam, New Delhi. The conclave brought together senior policymakers, technology leaders, researchers and industry practitioners to examine how AI can accelerate economic, digital and social transformation across sectors. The programme focused on the overarching th..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Open In App