Execution to remain strong while awards likely to remain subdued in 2019
ROADS & HIGHWAYS

Execution to remain strong while awards likely to remain subdued in 2019

According to rating firm ICRA outlook for the road sector, while the engineering, procurement and construction (EPC) project executions may witness a temporary slowdown during the general elections; the build-operate-transfer (BOT) and hybrid annuity model (HAM) projects executions are expected to continue unabated. Overall, a strong unexecuted pipeline and concerted effort on the right of way puts the NHAI on a strong footing and is set to witness sustained growth in execution in 2019.

The awards activity usually picks up substantially during the fourth quarter. Given the general elections in 2019, new award activity is likely to get affected in Q4 FY2019 and Q1 FY2020. Therefore, the awards will remain subdued owing to the general elections in 2019, according to the firm.

Credit profile of most industry players to be largely unaffected

Toll collections are expected to witness high single digit growth in 2019. However, high interest outgo due to leveraged balance sheets will continue to exert pressure on net profitability for the toll road projects. A significant pipeline of road projects to be awarded under the Bharatmala programme in the next three years is likely to boost the order book of medium-large size developers. Awarding projects after receiving all approvals is likely to reduce delays in execution and reduced idling of resources, thereby resulting in improved operating margins. Further, the toll-operate-transfer (TOT) awards are expected to crowd out the asset sale activity of private developers, resulting in lower stake sale transactions. Therefore, efforts to de-leverage the balance sheets through asset monetisation route are likely to get impacted.

NHAI’s borrowings to increase to fund the Bharatmala Pariyojana programme

Over the years, the NHAI’s expenditure increased primarily owing to the sharp increase in land acquisition cost. At the same time, budgetary support as a proportion of funding requirement for the NHAI steadily reduced, thereby increasing the dependence on internal and external budgetary resources (primarily debt). The total market borrowings for Bharatmala are estimated at Rs 209,279 crore till FY2022 (the total capital base including cess fund, toll collections and TOT proceeds is estimated at Rs 377,045 crore). At around Rs 60,000 crore per annum, the annual debt requirement is in line with that raised in the recent past. A major part of this is likely to be sourced from LIC and the EPFO.

Credit challenges persist

With banks facing a huge stressed asset problem, their ability to extend credit to the already stretched sectors like infrastructure will remain constrained. Lenders, in some cases, are insisting on higher as well as upfront equity infusion, particularly in the case of smaller players and developers with leveraged balance sheets. Many infrastructure players have raised funds through the corporate bond market for completed projects (replacing bank credit with bonds) – which is also one of the reasons for subdued growth of banking credit to the sector.

More than 90 per cent of the projects awarded under the HAM have achieved financial closure within the stipulated timeframe as per the concession agreement. Although the private sector banks have taken the lead in funding HAM projects, the FC-related challenges resurfaced in the recent past, given the stress in the banking system and with many PSU banks coming under prompt corrective action. Increasingly new developers are taking high exposure to HAM projects for whom achieving FC could be even more challenging in the current situation.

 

According to rating firm ICRA outlook for the road sector, while the engineering, procurement and construction (EPC) project executions may witness a temporary slowdown during the general elections; the build-operate-transfer (BOT) and hybrid annuity model (HAM) projects executions are expected to continue unabated. Overall, a strong unexecuted pipeline and concerted effort on the right of way puts the NHAI on a strong footing and is set to witness sustained growth in execution in 2019. The awards activity usually picks up substantially during the fourth quarter. Given the general elections in 2019, new award activity is likely to get affected in Q4 FY2019 and Q1 FY2020. Therefore, the awards will remain subdued owing to the general elections in 2019, according to the firm. Credit profile of most industry players to be largely unaffected Toll collections are expected to witness high single digit growth in 2019. However, high interest outgo due to leveraged balance sheets will continue to exert pressure on net profitability for the toll road projects. A significant pipeline of road projects to be awarded under the Bharatmala programme in the next three years is likely to boost the order book of medium-large size developers. Awarding projects after receiving all approvals is likely to reduce delays in execution and reduced idling of resources, thereby resulting in improved operating margins. Further, the toll-operate-transfer (TOT) awards are expected to crowd out the asset sale activity of private developers, resulting in lower stake sale transactions. Therefore, efforts to de-leverage the balance sheets through asset monetisation route are likely to get impacted. NHAI’s borrowings to increase to fund the Bharatmala Pariyojana programme Over the years, the NHAI’s expenditure increased primarily owing to the sharp increase in land acquisition cost. At the same time, budgetary support as a proportion of funding requirement for the NHAI steadily reduced, thereby increasing the dependence on internal and external budgetary resources (primarily debt). The total market borrowings for Bharatmala are estimated at Rs 209,279 crore till FY2022 (the total capital base including cess fund, toll collections and TOT proceeds is estimated at Rs 377,045 crore). At around Rs 60,000 crore per annum, the annual debt requirement is in line with that raised in the recent past. A major part of this is likely to be sourced from LIC and the EPFO. Credit challenges persist With banks facing a huge stressed asset problem, their ability to extend credit to the already stretched sectors like infrastructure will remain constrained. Lenders, in some cases, are insisting on higher as well as upfront equity infusion, particularly in the case of smaller players and developers with leveraged balance sheets. Many infrastructure players have raised funds through the corporate bond market for completed projects (replacing bank credit with bonds) – which is also one of the reasons for subdued growth of banking credit to the sector. More than 90 per cent of the projects awarded under the HAM have achieved financial closure within the stipulated timeframe as per the concession agreement. Although the private sector banks have taken the lead in funding HAM projects, the FC-related challenges resurfaced in the recent past, given the stress in the banking system and with many PSU banks coming under prompt corrective action. Increasingly new developers are taking high exposure to HAM projects for whom achieving FC could be even more challenging in the current situation.  

Next Story
Infrastructure Transport

JNPA Becomes First Indian Port to Cross 10 Million TEU Capacity

The Jawaharlal Nehru Port Authority (JNPA), located at Uran in Navi Mumbai, has become the first port in India to achieve over 10 million TEUs (twenty-foot equivalent units) in container handling capacity.With the recent expansion, the port now operates five container terminals with a combined capacity of 10.4 million TEUs, alongside two liquid and two general cargo terminals.Handling more than half of India’s container traffic, JNPA processed 7.05 million TEUs in 2024 and has moved 15.39 million tonnes of containers and 16.64 million tonnes of total cargo in the first two months of FY 2025â..

Next Story
Infrastructure Transport

Nod for Rs. 36.26 billion Expansion of Pune Metro Line 2

The Union Cabinet has approved the Rs.36.26 billion expansion of Pune Metro Line 2, adding 12.75 km of track and 13 new stations to improve east–west connectivity across the city.The project aims to link Pune’s urban core with rapidly growing suburbs, supporting the city’s rising demand for efficient and sustainable transport solutions. This expansion is part of Corridor 2 of the Pune Metro and includes two key routes: Vanaz to Chandani Chowk (Corridor 2A) and Ramwadi to Wagholi/Vitthalwadi (Corridor 2B).It will connect residential, IT, and educational hubs in areas such as Bavdhan, Koth..

Next Story
Infrastructure Transport

Assembly begins for ‘Nayak’ TBM on Thane– Borivali Twin Tunnel Project

The assembly of ‘Nayak’, the first of four Tunnel Boring Machines (TBMs) for the Thane–Borivali Twin Tube Tunnel Project, has commenced at the Thane site. Built by German firm Herrenknecht AG and deployed by Megha Engineering & Infrastructure (MEIL), the TBM marks a key milestone in Mumbai’s ambitious 11.8-km underground road corridor beneath Sanjay Gandhi National Park.The twin tunnels will reduce the Thane–Borivali travel distance by 12 km and decongest Thane Ghodbunder Road. ‘Nayak’, with a 13.2-metre diameter, is designed to bore through challenging geological conditions ..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?