Delhi-Mumbai Expressway Delayed to 2025, Misses Revised 2024 Target
ROADS & HIGHWAYS

Delhi-Mumbai Expressway Delayed to 2025, Misses Revised 2024 Target

The ambitious Delhi-Mumbai expressway project, hailed as a transformative development for Indian infrastructure, is experiencing substantial delays primarily due to land acquisition issues in Gujarat. Bidding for two key segments totalling 62 kilometres in Gujarat only began in November 2023. Construction on one of these segments started in April this year, while work on the other began just this month.

Originally scheduled for completion by January 2023, the project has faced numerous delays, pushing the revised completion target to March 2024, which has also been missed. It has been revealed that each segment requires at least eighteen months constructing. To accelerate progress, the project was divided into smaller 'packages' for more efficient execution. Officials have assured that all unresolved land acquisition issues are being actively addressed.

Currently, about 630 kilometres of the total 1,386 kilometres have been opened to traffic in various segments. Significant portions include Sohna-Dausa-Sawai Madhopur (293 km) and Jhalawar-MP/Gujarat border (245 km). Authorities are optimistic that the 845-kilometre stretch from Sohna to Vadodara will be fully operational by March 2025. Subsequent sections, which are vital connections to Mumbai's JNPT port, Jewar Airport in Uttar Pradesh, and Delhi's DND Flyway, are expected to follow.

Former NHAI officials stress the importance of timely land acquisition for such projects and highlight the need for proactive measures by state governments. A former official noted that the biggest obstacle in executing road projects, particularly greenfield expressways, is the lack of available land.

Recently, the Ministry of Road Transport and Highways announced that contracts worth Rs 36.33 billion and Rs 22.87 billion were awarded for constructing 35 kilometres in Valsad and 27 kilometres in Navsari districts, respectively. However, construction in these areas has yet to begin.

The ambitious Delhi-Mumbai expressway project, hailed as a transformative development for Indian infrastructure, is experiencing substantial delays primarily due to land acquisition issues in Gujarat. Bidding for two key segments totalling 62 kilometres in Gujarat only began in November 2023. Construction on one of these segments started in April this year, while work on the other began just this month. Originally scheduled for completion by January 2023, the project has faced numerous delays, pushing the revised completion target to March 2024, which has also been missed. It has been revealed that each segment requires at least eighteen months constructing. To accelerate progress, the project was divided into smaller 'packages' for more efficient execution. Officials have assured that all unresolved land acquisition issues are being actively addressed. Currently, about 630 kilometres of the total 1,386 kilometres have been opened to traffic in various segments. Significant portions include Sohna-Dausa-Sawai Madhopur (293 km) and Jhalawar-MP/Gujarat border (245 km). Authorities are optimistic that the 845-kilometre stretch from Sohna to Vadodara will be fully operational by March 2025. Subsequent sections, which are vital connections to Mumbai's JNPT port, Jewar Airport in Uttar Pradesh, and Delhi's DND Flyway, are expected to follow. Former NHAI officials stress the importance of timely land acquisition for such projects and highlight the need for proactive measures by state governments. A former official noted that the biggest obstacle in executing road projects, particularly greenfield expressways, is the lack of available land. Recently, the Ministry of Road Transport and Highways announced that contracts worth Rs 36.33 billion and Rs 22.87 billion were awarded for constructing 35 kilometres in Valsad and 27 kilometres in Navsari districts, respectively. However, construction in these areas has yet to begin.

Next Story
Real Estate

Integrated Waterproofing Strategies

Waterproofing buildings used to be an annual pre-monsoon affair but the evolution of real-estate development has changed that approach. In new developments, developers are weaving waterproofing solutions into both the design and construction phases, an approach that Nikhil Madan, Managing Director, Mahima Group, says, “is all about ensuring lasting durability [of the building] and keeping lifecycle risks including water seepage and extensive maintenance to a minimum.”Watertight by designAluminium formwork systems aren’t commonly thought of as a waterproofing tool but at the Mahima Group,..

Next Story
Infrastructure Urban

GROHE Showcases Water-Led Design At Milan

GROHE unveiled its GROHE SPA Aqua Sanctuary at Milan Design Week 2026, transforming Piccolo Teatro Studio Melato into an immersive showcase of water, design and wellbeing. Built on the philosophy of ‘Wellbeing Through Water’, the installation reimagined bathrooms as holistic spaces for relaxation, rejuvenation and self-care.The Aqua Sanctuary was presented through three interconnected sanctums. The first showcased the 3D-printed GROHE SPA AquaTree shower and faucet, highlighting bespoke innovation and biophilic design. The second featured the Atrio Private Collection and GROHE SPA x Buster..

Next Story
Infrastructure Transport

Rahee Group Expands Rail Manufacturing Capacity

Rahee Group has outlined a multi-year investment roadmap to expand its operational footprint and strengthen manufacturing capabilities for India’s growing railway and urban transit sector. The Group is expanding in Odisha with a new Track Component Casting Unit, for which the groundbreaking ceremony was held on 8 April 2026 in the presence of Odisha Chief Minister Mohan Charan Majhi.The Group’s flagship EPC arm, Rahee Infratech Ltd, continues to focus on complex rail infrastructure projects, including track systems, bridges, viaducts and ballastless infrastructure. Its wholly owned subsidi..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement