Govt ramps up efforts to expedite Delhi-Mumbai expressway project
ROADS & HIGHWAYS

Govt ramps up efforts to expedite Delhi-Mumbai expressway project

Despite the ongoing Covid-19 pandemic, full efforts are being made to complete the Delhi-Mumbai Expressway project expeditiously, said Road Transport and Highways Minister Nitin Gadkari.

In the 1,350 km long Delhi-Mumbai Expressway project, 350 km has already been built, and construction work of 825 km is in progress, said Gadkari.

He further added that bids have been received or invited for the remaining 163 km length, and these remaining works are likely to be given in the current year.

The Delhi-Mumbai Expressway is estimated to be completed by January 2023.

Gadkari said that at present, the construction of seven expressways having a length of 2,507 km has been taken up, out of which 440 km construction has been completed.

He said that the ministry has announced detailed guidelines dated June 3, 2020, for providing relief due to the ongoing pandemic.

He further added that the ministry has announced guidelines for compulsory utilisation of waste plastic in periodic renewal coat of pavement on National Highways and also in wearing course of service roads within 50 km boundary of urban areas having five lakhs or more population.

He said at present, 149 fee plazas on state highways and 701 fee plazas on National Highways have been approved, with Electronic Toll Collection (ETC) infrastructure.

Through FASTag a total amount of Rs 52,386.58 crore has been collected till July 11, 2021.

Image Source


Also read: Pune-Nashik highway bypass is completed, Nitin Gadkari shares images

Also read: Delhi-Jaipur stretch set to become India's first e-highway

Despite the ongoing Covid-19 pandemic, full efforts are being made to complete the Delhi-Mumbai Expressway project expeditiously, said Road Transport and Highways Minister Nitin Gadkari. In the 1,350 km long Delhi-Mumbai Expressway project, 350 km has already been built, and construction work of 825 km is in progress, said Gadkari. He further added that bids have been received or invited for the remaining 163 km length, and these remaining works are likely to be given in the current year. The Delhi-Mumbai Expressway is estimated to be completed by January 2023. Gadkari said that at present, the construction of seven expressways having a length of 2,507 km has been taken up, out of which 440 km construction has been completed. He said that the ministry has announced detailed guidelines dated June 3, 2020, for providing relief due to the ongoing pandemic. He further added that the ministry has announced guidelines for compulsory utilisation of waste plastic in periodic renewal coat of pavement on National Highways and also in wearing course of service roads within 50 km boundary of urban areas having five lakhs or more population. He said at present, 149 fee plazas on state highways and 701 fee plazas on National Highways have been approved, with Electronic Toll Collection (ETC) infrastructure. Through FASTag a total amount of Rs 52,386.58 crore has been collected till July 11, 2021. Image Source Also read: Pune-Nashik highway bypass is completed, Nitin Gadkari shares images Also read: Delhi-Jaipur stretch set to become India's first e-highway

Next Story
Infrastructure Urban

Jyoti Structures FY26 profit rises 56.5%

Jyoti Structures (JSL) recently reported strong financial results for the quarter and year ended 31 March 2026, driven by disciplined execution, cost management and steady progress across its order book.For Q4 FY2025-26, total income rose 44.2 per cent to Rs 2.41 billion from Rs 1.67 billion in Q4 FY2024-25. EBITDA increased 58.6 per cent to Rs 237 million, while EBITDA margin improved by 89 basis points to 9.84 per cent. Profit before tax grew 53.3 per cent to Rs 188.5 million, and net profit rose 51.9 per cent to Rs 181.4 million.For FY2025-26, total income grew 53.1 per cent to Rs 7.72 bill..

Next Story
Infrastructure Energy

Cat BEPU to Power Doppstadt Separator at IFAT 2026

Caterpillar’s Cat Battery Electric Power Unit (BEPU) has been selected by Doppstadt to power its SWS 6 Spiral Shaft Separator, which will be showcased for the first time at IFAT 2026 in Munich, Germany, from 4–7 May.The compact plug-and-play BEPU is designed to replace a diesel engine within the same space, using the same mounting locations and relative machine position. It integrates the battery, motor, inverter, onboard charging, cooling and controls, enabling OEMs to electrify existing chassis platforms without extensive redesign.Caterpillar and Cat dealer Zeppelin Power Systems have be..

Next Story
Infrastructure Urban

VECV sales rise 6.9% in April 2026

VE Commercial Vehicles, a joint venture between Volvo Group and Eicher Motors, recorded sales of 7,318 units in April 2026, compared to 6,846 units in April 2025, registering 6.9 per cent growth. The total included 7,159 units under the Eicher brand and 159 units under the Volvo brand.Eicher branded trucks and buses reported sales of 7,159 units during the month, up 6.6 per cent from 6,717 units in April 2025. In the domestic commercial vehicle market, Eicher sales rose 8.6 per cent to 6,797 units from 6,257 units a year earlier.Exports declined 21.3 per cent, with VECV recording 362 units in ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement