Govt ramps up efforts to expedite Delhi-Mumbai expressway project
ROADS & HIGHWAYS

Govt ramps up efforts to expedite Delhi-Mumbai expressway project

Despite the ongoing Covid-19 pandemic, full efforts are being made to complete the Delhi-Mumbai Expressway project expeditiously, said Road Transport and Highways Minister Nitin Gadkari.

In the 1,350 km long Delhi-Mumbai Expressway project, 350 km has already been built, and construction work of 825 km is in progress, said Gadkari.

He further added that bids have been received or invited for the remaining 163 km length, and these remaining works are likely to be given in the current year.

The Delhi-Mumbai Expressway is estimated to be completed by January 2023.

Gadkari said that at present, the construction of seven expressways having a length of 2,507 km has been taken up, out of which 440 km construction has been completed.

He said that the ministry has announced detailed guidelines dated June 3, 2020, for providing relief due to the ongoing pandemic.

He further added that the ministry has announced guidelines for compulsory utilisation of waste plastic in periodic renewal coat of pavement on National Highways and also in wearing course of service roads within 50 km boundary of urban areas having five lakhs or more population.

He said at present, 149 fee plazas on state highways and 701 fee plazas on National Highways have been approved, with Electronic Toll Collection (ETC) infrastructure.

Through FASTag a total amount of Rs 52,386.58 crore has been collected till July 11, 2021.

Image Source


Also read: Pune-Nashik highway bypass is completed, Nitin Gadkari shares images

Also read: Delhi-Jaipur stretch set to become India's first e-highway

Despite the ongoing Covid-19 pandemic, full efforts are being made to complete the Delhi-Mumbai Expressway project expeditiously, said Road Transport and Highways Minister Nitin Gadkari. In the 1,350 km long Delhi-Mumbai Expressway project, 350 km has already been built, and construction work of 825 km is in progress, said Gadkari. He further added that bids have been received or invited for the remaining 163 km length, and these remaining works are likely to be given in the current year. The Delhi-Mumbai Expressway is estimated to be completed by January 2023. Gadkari said that at present, the construction of seven expressways having a length of 2,507 km has been taken up, out of which 440 km construction has been completed. He said that the ministry has announced detailed guidelines dated June 3, 2020, for providing relief due to the ongoing pandemic. He further added that the ministry has announced guidelines for compulsory utilisation of waste plastic in periodic renewal coat of pavement on National Highways and also in wearing course of service roads within 50 km boundary of urban areas having five lakhs or more population. He said at present, 149 fee plazas on state highways and 701 fee plazas on National Highways have been approved, with Electronic Toll Collection (ETC) infrastructure. Through FASTag a total amount of Rs 52,386.58 crore has been collected till July 11, 2021. Image Source Also read: Pune-Nashik highway bypass is completed, Nitin Gadkari shares images Also read: Delhi-Jaipur stretch set to become India's first e-highway

Next Story
Infrastructure Urban

TBO Tek Q2 Profit Climbs 12%, Revenue Surges 26% YoY

TBO Tek Limited one of the world’s largest travel distribution platforms, reported a solid performance for Q2 FY26 with a 26 per cent year-on-year increase in revenue to Rs 5.68 billion, reflecting broad-based growth and improving profitability.The company recorded a Gross Transaction Value (GTV) of Rs 8,901 crore, up 12 per cent YoY, driven by strong performance across Europe, MEA, and APAC regions. Adjusted EBITDA before acquisition-related costs stood at Rs 1.04 billion, up 16 per cent YoY, translating into an 18.32 per cent margin compared to 16.56 per cent in Q1 FY26. Profit after tax r..

Next Story
Infrastructure Energy

Northern Graphite, Rain Carbon Secure R&D Grant for Greener Battery Materials

Northern Graphite Corporation and Rain Carbon Canada Inc, a subsidiary of Rain Carbon Inc, have jointly received up to C$860,000 (€530,000) in funding under the Canada–Germany Collaborative Industrial Research and Development Programme to develop sustainable battery anode materials.The two-year, C$2.2 million project aims to transform natural graphite processing by-products into high-performance, battery-grade anode material (BAM). Supported by the National Research Council of Canada Industrial Research Assistance Programme (NRC IRAP) and Germany’s Federal Ministry for Economic Affairs a..

Next Story
Infrastructure Urban

Antony Waste Q2 Revenue Jumps 16%; Subsidiary Wins Rs 3,200 Cr WtE Projects

Antony Waste Handling Cell Limited (AWHCL), a leading player in India’s municipal solid waste management sector, announced a 16 per cent year-on-year increase in total operating revenue to Rs 2.33 billion for Q2 FY26. The growth was driven by higher waste volumes, escalated contracts, and strong operational execution.EBITDA rose 18 per cent to Rs 570 million, with margins steady at 21.6 per cent, while profit after tax stood at Rs 173 million, up 13 per cent YoY. Revenue from Municipal Solid Waste Collection and Transportation (MSW C&T) reached Rs 1.605 billion, and MSW Processing re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Get CW App