Delhi-Mumbai Expressway's Gujarat Stretch Faces Fourth Tender Setback
ROADS & HIGHWAYS

Delhi-Mumbai Expressway's Gujarat Stretch Faces Fourth Tender Setback

The Delhi-Mumbai Expressway continues to face delays in Gujarat, where the National Highways Authority of India (NHAI) has invited fresh bids for a 35.4-km stretch across Valsad and Navsari districts. The latest tender follows the refusal of the lowest bidder to accept the letter of award, making it the fourth attempt to appoint a contractor for package 8.

Bansal Construction Works emerged as the lowest bidder after quoting more than 10 per cent below the estimated project cost of Rs. 14.76 bn. The company reportedly declined the award, leading NHAI to encash its bid security of Rs. 147.6 mn. A fresh tender was issued on September 14, with bid submissions due by October 13.

Package 8 covers the Jujuwa-Gandeva section. Roadway Solutions India Infra (RSIIL) was initially awarded the work in 2021 under the Hybrid Annuity Mode (HAM), but NHAI terminated the contract in March 2023 after delays. The work was awarded to RSIIL again in November 2023 under the Engineering, Procurement and Construction (EPC) mode, before the contract was terminated once more in January.

Physical completion of the package stood at 4.85 per cent. Nine companies were assessed during the technical stage, while four were rejected or declared non-responsive, including RSIIL. Bansal Construction, Ashoka Buildcon, Ceigall India, G R Infraprojects and Kalthia Engineering and Construction participated in the financial bidding, with Ceigall India quoting Rs. 15.81 bn.

Two other Gujarat packages are also facing execution problems. NHAI terminated package 9, a 26.6-km Karvad-Jujuwa section, after progress reached around 22 per cent, and invited bids for the remaining work at an estimated Rs. 8.74 bn. Package 10, covering 24.6 km between Talasari and Karwad, is 36.23 per cent complete and faces a potential termination over poor performance.

The 1,386-km expressway, estimated to cost Rs. 1.04 tn, is being built through 53 packages. Expenditure had reached Rs. 717.18 bn by December 2025. The revised completion deadline is June 30, 2028, although repeated contract changes in Gujarat are likely to put additional pressure on the schedule.

The Delhi-Mumbai Expressway continues to face delays in Gujarat, where the National Highways Authority of India (NHAI) has invited fresh bids for a 35.4-km stretch across Valsad and Navsari districts. The latest tender follows the refusal of the lowest bidder to accept the letter of award, making it the fourth attempt to appoint a contractor for package 8. Bansal Construction Works emerged as the lowest bidder after quoting more than 10 per cent below the estimated project cost of Rs. 14.76 bn. The company reportedly declined the award, leading NHAI to encash its bid security of Rs. 147.6 mn. A fresh tender was issued on September 14, with bid submissions due by October 13. Package 8 covers the Jujuwa-Gandeva section. Roadway Solutions India Infra (RSIIL) was initially awarded the work in 2021 under the Hybrid Annuity Mode (HAM), but NHAI terminated the contract in March 2023 after delays. The work was awarded to RSIIL again in November 2023 under the Engineering, Procurement and Construction (EPC) mode, before the contract was terminated once more in January. Physical completion of the package stood at 4.85 per cent. Nine companies were assessed during the technical stage, while four were rejected or declared non-responsive, including RSIIL. Bansal Construction, Ashoka Buildcon, Ceigall India, G R Infraprojects and Kalthia Engineering and Construction participated in the financial bidding, with Ceigall India quoting Rs. 15.81 bn. Two other Gujarat packages are also facing execution problems. NHAI terminated package 9, a 26.6-km Karvad-Jujuwa section, after progress reached around 22 per cent, and invited bids for the remaining work at an estimated Rs. 8.74 bn. Package 10, covering 24.6 km between Talasari and Karwad, is 36.23 per cent complete and faces a potential termination over poor performance. The 1,386-km expressway, estimated to cost Rs. 1.04 tn, is being built through 53 packages. Expenditure had reached Rs. 717.18 bn by December 2025. The revised completion deadline is June 30, 2028, although repeated contract changes in Gujarat are likely to put additional pressure on the schedule.

Related Stories

Gold Stories

Next Story
Real Estate

Sumadhura leases 20,000 sq ft to Iron Hill Brewery in Bengaluru

Sumadhura Group has leased 20,000 sq ft of retail space to Iron Hill Brewery at Sumadhura Capitol Towers, its Grade A+ commercial development in Whitefield, East Bengaluru. The brewery is expected to commence operations at the property before the end of 2026.The development has also leased 3,700 sq ft to Yummy Bee, a café chain offering gluten-free and sugar-free products. The two additions will expand the food and beverage (F&B) offering at Capitol Towers, which combines office spaces with retail, dining and lifestyle facilities.Expanding the retail and F&B mixThe existing retail and..

Next Story
Real Estate

Peninsula Land enters Mumbai suburbs with Versova redevelopment

Peninsula Land, part of the Ashok Piramal Group, has signed a development agreement for the redevelopment of two adjoining residential societies in Versova, Andheri West, marking its entry into Mumbai’s western suburbs. Spread across approximately 1.5 acres, the project has an estimated gross development value (GDV) of Rs 7.5-7.75 billion.The consolidated land parcel is larger than the sub-one-acre developments typically seen in the Versova micro-market. According to the company, the larger site will allow it to develop a gated community with open spaces and integrated amenities.Commenting o..

Next Story
Technology

Goyal & Co. invests Rs 8.2 billion in Bengaluru tech park

Goyal & Co. is developing Titanium Tech Park, a 5 million sq ft commercial project in Whitefield’s technology corridor in Bengaluru, with an investment of approximately Rs 8.2 billion. Spread across 25 acres, the development has secured leasing commitments from global engineering companies Airbus and Caterpillar, which have taken up 880,000 sq ft and 300,000 sq ft, respectively. The combined annual rental value is estimated at Rs 1 billion.The project is being developed in multiple phases. Phase I comprises two operational office blocks of G+15 floors, offering 880,000 sq ft and 622,000 ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code