Greater Chennai Corporation constructs Steel Flyover in T Nagar
ROADS & HIGHWAYS

Greater Chennai Corporation constructs Steel Flyover in T Nagar

In order to expedite the construction process, the Greater Chennai Corporation is currently erecting a steel flyover in T Nagar on the heavily congested South Usman Road. According to officials, this will be the second fully steel bridge in the state, with the first one located in Marthandam, Kanyakumari district.

S Rajendiran, the chief engineer (general) of the Corporation, explained that the concrete pile and pile cap are situated underground, while the pier, pier cap, and deck girders, made of high tensile steel, are manufactured in Trichy and transported to the site. Placing these components takes only a few hours. On top of the girders, a steel deck sheet is installed, followed by a 20-cm thick concrete slab and a bitumen road.

The flyover spans 1.2 kilometers and connects Anna Salai and T Nagar via CIT Nagar. The project is estimated to cost 13.1 billlion. Once completed, it will be connected to the existing concrete North Usman Road flyover, allowing commuters traveling from Anna Salai to cross Panagal Park in less than five minutes.

The steel flyover stands at a height of 6.5 meters, with underground support reaching approximately 30 meters deep. Rajendiran mentioned that there are exit and entry ramps near Ranganathan Street for vehicles coming from T Nagar and shoppers. Unlike concrete bridges where expansion joints are typically 20 meters apart, in this steel flyover they are spaced 75 meters apart, resulting in smoother rides for vehicles. The two-lane flyover will consist of 53 steel piers and three 8.5-meter-wide girders.

A professor of structural engineering from IIT-M, who is collaborating with the Greater Chennai Corporation on the project, highlighted the use of high-quality steel for the bridge, which is expected to have a lifespan of around 50 years. The decision to use steel was made to minimise construction time, given the congested nature of the T Nagar area. Barricading all the spots for an extended period would not be feasible.

Rajendiran mentioned that static and dynamic testing was conducted, including static load and moving load tests. "We applied a weight that was 2.5 times more than the prescribed amount for additional safety," he added.

G Sameeran, the Deputy Commissioner (Works), stated that the initial deadline for completion was set at 24 months. However, thanks to the implementation of steel structures, the project is expected to be finished in less than 20 months, by late 2024. 

In order to expedite the construction process, the Greater Chennai Corporation is currently erecting a steel flyover in T Nagar on the heavily congested South Usman Road. According to officials, this will be the second fully steel bridge in the state, with the first one located in Marthandam, Kanyakumari district.S Rajendiran, the chief engineer (general) of the Corporation, explained that the concrete pile and pile cap are situated underground, while the pier, pier cap, and deck girders, made of high tensile steel, are manufactured in Trichy and transported to the site. Placing these components takes only a few hours. On top of the girders, a steel deck sheet is installed, followed by a 20-cm thick concrete slab and a bitumen road.The flyover spans 1.2 kilometers and connects Anna Salai and T Nagar via CIT Nagar. The project is estimated to cost 13.1 billlion. Once completed, it will be connected to the existing concrete North Usman Road flyover, allowing commuters traveling from Anna Salai to cross Panagal Park in less than five minutes.The steel flyover stands at a height of 6.5 meters, with underground support reaching approximately 30 meters deep. Rajendiran mentioned that there are exit and entry ramps near Ranganathan Street for vehicles coming from T Nagar and shoppers. Unlike concrete bridges where expansion joints are typically 20 meters apart, in this steel flyover they are spaced 75 meters apart, resulting in smoother rides for vehicles. The two-lane flyover will consist of 53 steel piers and three 8.5-meter-wide girders.A professor of structural engineering from IIT-M, who is collaborating with the Greater Chennai Corporation on the project, highlighted the use of high-quality steel for the bridge, which is expected to have a lifespan of around 50 years. The decision to use steel was made to minimise construction time, given the congested nature of the T Nagar area. Barricading all the spots for an extended period would not be feasible.Rajendiran mentioned that static and dynamic testing was conducted, including static load and moving load tests. We applied a weight that was 2.5 times more than the prescribed amount for additional safety, he added.G Sameeran, the Deputy Commissioner (Works), stated that the initial deadline for completion was set at 24 months. However, thanks to the implementation of steel structures, the project is expected to be finished in less than 20 months, by late 2024. 

Next Story
Infrastructure Urban

Aadhaar Authentications Cross 27 Billion in FY25

Aadhaar authentication transactions surged past 27.07 billion in FY 2024–25, including 2.47 billion in March alone, reflecting its growing adoption across sectors such as banking, finance, telecom, and public service delivery. Since its inception, the cumulative number of Aadhaar authentication transactions has exceeded 148 billion.The Unique Identification Authority of India’s (UIDAI) AI/ML-based face authentication technology is also witnessing a sharp rise in usage. In March 2025 alone, over 150 million face authentication transactions were recorded. This biometric modality is now used ..

Next Story
Infrastructure Urban

IEPFA Holds Preparatory Meet for 'Niveshak Shivir' Initiative

The Investor Education and Protection Fund Authority (IEPFA), under the Ministry of Corporate Affairs, Government of India, hosted a preparatory meeting on April 28, 2025, with Nodal Officers from stakeholder companies via video conference. The session, chaired by IEPFA CEO Smt. Anita Shah Akella, focused on finalising operational plans for the upcoming ""Niveshak Shivir"" initiative—a joint effort between IEPFA and the Securities and Exchange Board of India (SEBI).""Niveshak Shivir"" aims to improve investor services and streamline the claims process by reaching out to cities with a high nu..

Next Story
Infrastructure Urban

India, France Sign Deal for 26 Rafale-Marine Jets for Navy

India and France have signed an Inter-Governmental Agreement (IGA) for the acquisition of 26 Rafale-Marine aircraft for the Indian Navy, comprising 22 single-seater and four twin-seater jets. The deal also includes training systems, simulators, associated equipment, weapons, and performance-based logistics, along with additional equipment for the Indian Air Force’s existing Rafale fleet.The IGA was signed by India’s Defence Minister Rajnath Singh and French Minister of Armed Forces Sébastien Lecornu. The agreement, along with supply protocols for aircraft and weapons, was exchanged in the..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?