In 2023-2024, Odisha intends to build 3,200 km of road
ROADS & HIGHWAYS

In 2023-2024, Odisha intends to build 3,200 km of road

The Odisha state administration surpassed its goal by building rural roads totaling 2,189.72 km instead of the 2,000 km yearly target established by the end of February. By the conclusion of the current fiscal year, the Rural Development department anticipates that the overall length of new roads may surpass 2,500 km at the current rate of construction. In order to provide 40 habitations with all-weather connectivity in the upcoming fiscal year, the state has presented a proposal to the Center for the building of 3,200 km of roads. The state government has budgeted Rs 14.50 billion for the Pradhan Mantri Gram Sadak Yojana (PMGSY) in expectation of Ministry of Rural Development (MoRD) clearance.

According to the status report, the state has finished building 67,598 km of the 72,257 km of road that MoRD approved. 93% of the goals were met as 16,382 habitations are currently connected.

Since 2020-21 the government approved 9,400 km for the PMGSY–III, of which 9,222 km have been awarded and 4,970 km have seen construction. With a budgetary assistance of Rs 20.61 billion, the state government has set an ambitious goal to build and improve 6,000 km of roads throughout the state in the upcoming fiscal year.

While Rs 6.50 billion has been budgeted for new roads under the MMSY in 2023-2024, Rs 3.50 billion is set aside for RD road rehabilitation. The department spent Rs 8.25 billion on 135 road projects that totalled 725.51 km in length from February 2022-2023 until completion. Under the state programme Connection of Missing Road Links (CMRL) till February 2023, the department has completed 25 road projects totalling 147 km at a cost of roughly Rs 300 million. Under CMRL, a provision of Rs 3 billion has been established for 2023-2024. In addition, the government has budgeted Rs 19 billion to build 526 new bridges as part of the Biju Setu Yojana (BSY).

The Odisha state administration surpassed its goal by building rural roads totaling 2,189.72 km instead of the 2,000 km yearly target established by the end of February. By the conclusion of the current fiscal year, the Rural Development department anticipates that the overall length of new roads may surpass 2,500 km at the current rate of construction. In order to provide 40 habitations with all-weather connectivity in the upcoming fiscal year, the state has presented a proposal to the Center for the building of 3,200 km of roads. The state government has budgeted Rs 14.50 billion for the Pradhan Mantri Gram Sadak Yojana (PMGSY) in expectation of Ministry of Rural Development (MoRD) clearance. According to the status report, the state has finished building 67,598 km of the 72,257 km of road that MoRD approved. 93% of the goals were met as 16,382 habitations are currently connected. Since 2020-21 the government approved 9,400 km for the PMGSY–III, of which 9,222 km have been awarded and 4,970 km have seen construction. With a budgetary assistance of Rs 20.61 billion, the state government has set an ambitious goal to build and improve 6,000 km of roads throughout the state in the upcoming fiscal year. While Rs 6.50 billion has been budgeted for new roads under the MMSY in 2023-2024, Rs 3.50 billion is set aside for RD road rehabilitation. The department spent Rs 8.25 billion on 135 road projects that totalled 725.51 km in length from February 2022-2023 until completion. Under the state programme Connection of Missing Road Links (CMRL) till February 2023, the department has completed 25 road projects totalling 147 km at a cost of roughly Rs 300 million. Under CMRL, a provision of Rs 3 billion has been established for 2023-2024. In addition, the government has budgeted Rs 19 billion to build 526 new bridges as part of the Biju Setu Yojana (BSY).

Next Story
Infrastructure Transport

MMRDA advances 250 m on Orange Gate–Marine Drive tunnel

The Mumbai Metropolitan Region Development Authority (MMRDA) has completed 250 m of underground tunnelling for the Orange Gate–Marine Drive Urban Road Tunnel using India’s largest slurry shield tunnel boring machine (TBM) deployed for an urban road project.The project involves twin tunnels extending over 7 km beneath critical transport corridors, including Central Railway, Western Railway and Metro Line 3. The work requires high-precision engineering to navigate densely developed urban infrastructure.Once completed, the tunnel is expected to reduce travel time between Orange Gate and Marin..

Next Story
Infrastructure Urban

Hindustan Zinc Pays Rs 188.46 Billion in FY26

Hindustan Zinc contributed Rs 188.46 billion to the public exchequer in FY 2025-26, according to its 9th Tax Transparency Report. The contribution, equivalent to 46 per cent of the company’s revenue, included direct and indirect taxes, government royalties, dividends to the Government of India, withholding taxes and other statutory levies.The company’s five-year cumulative contribution to the exchequer stood at Rs 915.72 billion. In FY26, Hindustan Zinc reported revenue of Rs 408.44 billion, EBITDA of Rs 221.62 billion and profit after tax of Rs 138.32 billion. It also achieved its highest..

Next Story
Infrastructure Urban

World of Concrete India 2026 Opens in Mumbai

Informa Markets in India will host the 12th edition of World of Concrete India 2026 from 3–5 June 2026 at the Bombay Exhibition Centre, Mumbai. The specialised B2B exhibition will bring together manufacturers, suppliers, contractors, developers, architects, consultants, infrastructure companies, project leaders and government stakeholders.The event is expected to feature over 350 brands and more than 18,000 trade professionals. It will cover concrete and cement, dry mortar, precast technologies, formwork, construction chemicals, industrial and commercial flooring, scaffolding, safety solutio..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

-->