In 2023-2024, Odisha intends to build 3,200 km of road
ROADS & HIGHWAYS

In 2023-2024, Odisha intends to build 3,200 km of road

The Odisha state administration surpassed its goal by building rural roads totaling 2,189.72 km instead of the 2,000 km yearly target established by the end of February. By the conclusion of the current fiscal year, the Rural Development department anticipates that the overall length of new roads may surpass 2,500 km at the current rate of construction. In order to provide 40 habitations with all-weather connectivity in the upcoming fiscal year, the state has presented a proposal to the Center for the building of 3,200 km of roads. The state government has budgeted Rs 14.50 billion for the Pradhan Mantri Gram Sadak Yojana (PMGSY) in expectation of Ministry of Rural Development (MoRD) clearance.

According to the status report, the state has finished building 67,598 km of the 72,257 km of road that MoRD approved. 93% of the goals were met as 16,382 habitations are currently connected.

Since 2020-21 the government approved 9,400 km for the PMGSY–III, of which 9,222 km have been awarded and 4,970 km have seen construction. With a budgetary assistance of Rs 20.61 billion, the state government has set an ambitious goal to build and improve 6,000 km of roads throughout the state in the upcoming fiscal year.

While Rs 6.50 billion has been budgeted for new roads under the MMSY in 2023-2024, Rs 3.50 billion is set aside for RD road rehabilitation. The department spent Rs 8.25 billion on 135 road projects that totalled 725.51 km in length from February 2022-2023 until completion. Under the state programme Connection of Missing Road Links (CMRL) till February 2023, the department has completed 25 road projects totalling 147 km at a cost of roughly Rs 300 million. Under CMRL, a provision of Rs 3 billion has been established for 2023-2024. In addition, the government has budgeted Rs 19 billion to build 526 new bridges as part of the Biju Setu Yojana (BSY).

The Odisha state administration surpassed its goal by building rural roads totaling 2,189.72 km instead of the 2,000 km yearly target established by the end of February. By the conclusion of the current fiscal year, the Rural Development department anticipates that the overall length of new roads may surpass 2,500 km at the current rate of construction. In order to provide 40 habitations with all-weather connectivity in the upcoming fiscal year, the state has presented a proposal to the Center for the building of 3,200 km of roads. The state government has budgeted Rs 14.50 billion for the Pradhan Mantri Gram Sadak Yojana (PMGSY) in expectation of Ministry of Rural Development (MoRD) clearance. According to the status report, the state has finished building 67,598 km of the 72,257 km of road that MoRD approved. 93% of the goals were met as 16,382 habitations are currently connected. Since 2020-21 the government approved 9,400 km for the PMGSY–III, of which 9,222 km have been awarded and 4,970 km have seen construction. With a budgetary assistance of Rs 20.61 billion, the state government has set an ambitious goal to build and improve 6,000 km of roads throughout the state in the upcoming fiscal year. While Rs 6.50 billion has been budgeted for new roads under the MMSY in 2023-2024, Rs 3.50 billion is set aside for RD road rehabilitation. The department spent Rs 8.25 billion on 135 road projects that totalled 725.51 km in length from February 2022-2023 until completion. Under the state programme Connection of Missing Road Links (CMRL) till February 2023, the department has completed 25 road projects totalling 147 km at a cost of roughly Rs 300 million. Under CMRL, a provision of Rs 3 billion has been established for 2023-2024. In addition, the government has budgeted Rs 19 billion to build 526 new bridges as part of the Biju Setu Yojana (BSY).

Next Story
Infrastructure Urban

InsideFPV Delivers ₹10 Crore Kamikaze Drone Order Under MoD’s EPR Route

InsideFPV, a Surat-based drone technology manufacturer, has successfully executed a ₹10 crore defence contract to supply indigenous kamikaze drones under the Ministry of Defence’s Emergency Procurement Route (EPR). The company completed the delivery of hundreds of FPV kamikaze drone platforms within a rapid two-month timeframe, highlighting its ability to meet urgent military procurement timelines.The supply orders were fulfilled under the emergency procurement mechanism, which is aimed at fast-tracking acquisitions for immediate operational needs. InsideFPV’s quick execution reflects it..

Next Story
Infrastructure Energy

Vedanta Resources Secures Fitch Upgrade to ‘BB-’, Best Rating Since 2015

Vedanta Resources Limited (VRL), a global player in metals, oil & gas, critical minerals, power and technology, has received a credit rating upgrade from Fitch Ratings, marking its strongest bond rating in over a decade.Fitch has raised Vedanta Resources’ Long-Term Foreign-Currency Issuer Default Rating (IDR) to ‘BB-’ from ‘B+’, while maintaining a Stable Outlook. The agency also upgraded VRL’s senior unsecured rating, along with the ratings of US dollar-denominated bonds issued by Vedanta Resources Finance II Plc and guaranteed by VRL, to ‘BB-’.The upgrade represents Vedan..

Next Story
Real Estate

NAREDCO NextGen NCR Chapter Launched

The NAREDCO NextGen NCR Chapter was recently launched at Excelerate 2026 in Mumbai, marking a key step towards integrating emerging real estate leaders from the National Capital Region with the national platform. The initiative aims to promote sustainable and responsible urban development through collaboration and knowledge exchange.The event brought together young developers, entrepreneurs, and professionals from across NCR, including Noida, Gurugram, Ghaziabad, Faridabad, Bhiwadi, and Meerut. Discussions focused on urban development, finance, sustainability, innovation, and policy, emphasisi..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement