+
Land Acquisition delays Stymie Progress of Kukudagate ROB Project
ROADS & HIGHWAYS

Land Acquisition delays Stymie Progress of Kukudagate ROB Project

The highly anticipated road over bridge (ROB) initiative at the Kukudagate level-crossing, situated along the bustling Howrah-Mumbai main line, has encountered obstacles in the process of land acquisition. The construction of this ROB, which is being established at the junction of NH-320D near Rourkela city, has encountered a pause on one side due to delays in procuring the necessary land. Despite being granted approval in 2010, the project has hit this setback.

According to sources, there was a series of protests by a segment of tribal communities, causing significant delays before the ROB project could commence. Eventually, in March 2022, the project was finally initiated, starting from the Bisra end following the arrest of 22 protesters by the police. Notably, considerable progress has been achieved towards completion from the Bisra end, while activity is yet to commence at the Rourkela end.

Ashutosh Jena, the Sub-Divisional Officer of the Works department, highlighted that the project is a collaborative effort between the state government and the South Eastern Railway (SER), estimated to cost around Rs 470 million. Since work has not yet commenced at the Rourkela end, the projected completion date has been extended by a year, now targeting November 2024.

In response to the demands of local residents, a joint assessment was carried out by the Works department and SER to potentially establish an underpass for the Kapatmunda village. A separate cost estimation of over Rs 200 million for this underpass is soon to be submitted to the government for approval, as mentioned by Jena.

The highly anticipated road over bridge (ROB) initiative at the Kukudagate level-crossing, situated along the bustling Howrah-Mumbai main line, has encountered obstacles in the process of land acquisition. The construction of this ROB, which is being established at the junction of NH-320D near Rourkela city, has encountered a pause on one side due to delays in procuring the necessary land. Despite being granted approval in 2010, the project has hit this setback.According to sources, there was a series of protests by a segment of tribal communities, causing significant delays before the ROB project could commence. Eventually, in March 2022, the project was finally initiated, starting from the Bisra end following the arrest of 22 protesters by the police. Notably, considerable progress has been achieved towards completion from the Bisra end, while activity is yet to commence at the Rourkela end.Ashutosh Jena, the Sub-Divisional Officer of the Works department, highlighted that the project is a collaborative effort between the state government and the South Eastern Railway (SER), estimated to cost around Rs 470 million. Since work has not yet commenced at the Rourkela end, the projected completion date has been extended by a year, now targeting November 2024.In response to the demands of local residents, a joint assessment was carried out by the Works department and SER to potentially establish an underpass for the Kapatmunda village. A separate cost estimation of over Rs 200 million for this underpass is soon to be submitted to the government for approval, as mentioned by Jena.

Next Story
Infrastructure Transport

Kavach 4.0 Commissioned on Delhi–Mumbai and Delhi–Howrah

"Kavach version four has been commissioned on 1,452 route km, covering the high density Delhi–Mumbai and Delhi–Howrah corridors. The rollout included laying 8,570 km of optical fibre, installation of 1,100 telecom towers, deployment of trackside equipment over 6,776 RKm and establishment of 767 station data centres. Trackside implementation has been taken up on 24,427 RKm covering Golden Quadrilateral, Golden Diagonal and High Density Network sections. The programme aims to strengthen signalling and train protection on key routes.Kavach is an indigenously developed automatic train protecti..

Next Story
Infrastructure Transport

Railways Advance Kalyan–Murbad Line And Mumbai Capacity Expansion

"Indian Railways is advancing multiple rail infrastructure projects in Maharashtra, including the sanctioned Kalyan–Murbad new line and sizable investments under the Mumbai Urban Transport Project and the Mumbai–Ahmedabad High Speed Rail project. The Kalyan–Murbad 28 km new line has been sanctioned at Rs 8.36 billion (bn) on a 50:50 cost-sharing basis with the Government of Maharashtra and has been declared a Special Railway Project for land acquisition; proposals covering 214 hectares are at various stages of acquisition. Budgetary outlay for projects falling fully or partly in Maharash..

Next Story
Infrastructure Urban

Parliamentary Panel Flags Funding Gaps in Heavy Industries

"The Department-Related Parliamentary Standing Committee on Industry (Rajya Sabha) presented its 332nd report on the Demands for Grants 2026-27 of the Ministry of Heavy Industries (MHI). Figures converted from crore and lakh are expressed in million (mn). The Budget Estimates 2026-27 for the Ministry stand at Rs 79,399 mn against a projected requirement of Rs 94,843.2 mn, a shortfall of about 16 per cent, with revenue at Rs 79,370.8 mn and capital compressed to Rs 28.2 mn from Rs 5,020 mn.The committee flagged recurring BE-to-RE compression and declining revised estimate utilisation, and calle..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement