Kalunga ROB project nears completion; operational by November 2024
ROADS & HIGHWAYS

Kalunga ROB project nears completion; operational by November 2024

Residents of Kalunga Panchayat near Rourkela can finally expect some relief from their traffic woes. The long-awaited Road Over Bridge (ROB) project in the IDCO area is nearing completion and is expected to be operational by the end of 2024. This bridge, being built over Level Crossing No. 213 on the busy Howrah-Mumbai railway line, is crucial for both local residents and the industries operating in Kalunga under Lathikata block. Previously, a damaged road with heavy truck traffic made commuting a nightmare.

After a delay of nearly 12 years, construction of the ROB finally began in May 2022. The project, estimated at Rs 430 million, is being jointly funded and executed by the state government, the South Eastern Railway (SER), and the Works Department. The bridge itself is a substantial structure, stretching 780 meters and comprised of 15 slabs. Thankfully, pillar construction is already complete.

"The project is on track for completion by the end of this year," confirms A. Jena, SDO, Public 1Works Department.

Adding to the good news, a four-lane road project is also underway to connect the new ROB to the IDCO area. This 3.5-km road, funded by the Sundargarh District Mineral Foundation (DMF) and executed by the Public Works Department, has an estimated cost of Rs 200 million.

Jena informs that utility relocation is currently underway, after which road construction will proceed swiftly. The road construction is expected to be completed by November, taking just three to four months. Once finished, the four-lane road will provide a vital connection to the ROB, significantly improving overall connectivity in the region.

(Source: The New Indian Express)

Residents of Kalunga Panchayat near Rourkela can finally expect some relief from their traffic woes. The long-awaited Road Over Bridge (ROB) project in the IDCO area is nearing completion and is expected to be operational by the end of 2024. This bridge, being built over Level Crossing No. 213 on the busy Howrah-Mumbai railway line, is crucial for both local residents and the industries operating in Kalunga under Lathikata block. Previously, a damaged road with heavy truck traffic made commuting a nightmare. After a delay of nearly 12 years, construction of the ROB finally began in May 2022. The project, estimated at Rs 430 million, is being jointly funded and executed by the state government, the South Eastern Railway (SER), and the Works Department. The bridge itself is a substantial structure, stretching 780 meters and comprised of 15 slabs. Thankfully, pillar construction is already complete. The project is on track for completion by the end of this year, confirms A. Jena, SDO, Public 1Works Department. Adding to the good news, a four-lane road project is also underway to connect the new ROB to the IDCO area. This 3.5-km road, funded by the Sundargarh District Mineral Foundation (DMF) and executed by the Public Works Department, has an estimated cost of Rs 200 million. Jena informs that utility relocation is currently underway, after which road construction will proceed swiftly. The road construction is expected to be completed by November, taking just three to four months. Once finished, the four-lane road will provide a vital connection to the ROB, significantly improving overall connectivity in the region. (Source: The New Indian Express)

Related Stories

Gold Stories

Next Story
Infrastructure Urban

NABARD Holds Seminar on Vigilance, Integrity and Good Governance

National Bank for Agriculture and Rural Development (NABARD) organised a seminar on “Vigilance: Strengthening Integrity and Good Governance” on 25 August 2026 at its Head Office in Mumbai as part of the ongoing Vigilance Awareness Campaign 2026 being observed from 17 August to 16 November 2026, with the theme “Probity for Prosperity."" The seminar was graced by Suresh N Patel, Former Central Vigilance Commissioner, Government of India, as the chief guest and keynote speaker.  The programme was attended by G S Rawat, Deputy Managing Director, Dr Ajay K Sood, Deputy Managing Dire..

Next Story
Equipment

XCMG Unveils World's First 14,000-Ton Ring Crane for Heavy Lifting

XCMG has announced that the first main unit of the world's first 14,000-ton ring crane has rolled off the production line, marking a historic breakthrough in ultra-heavy lifting technology. Jointly developed by XCMG and Sinopec Heavy Lifting & Transportation Co., Ltd., the crane will be the largest-capacity ring crane ever built, setting a new benchmark for major construction projects worldwide.The crane features a modular configuration comprising two main units that work in tandem. The first main unit has completed final assembly and can independently perform lifting operations. Once both..

Next Story
Infrastructure Urban

Thriveni Logistics orders 200 tip trailers from Jagdamba trailers

Jagdamba Trailers (JTPL), one of India’s growing trailer manufacturers, has secured a significant order for 200 Tip Trailers from Thriveni Transport and Logistics Pvt. Ltd., a leading mining and logistics company serving operations across India and overseas.The order, placed for iron ore transportation, is a major milestone for JTPL, particularly as the company secured the business after competing with more than 10 established trailer manufacturers. It also strengthens an already successful relationship between the two companies. Approximately one and a half years ago, Thriveni Transport and..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code