Morbi Collapse: A Commoner’s Perspective!
ROADS & HIGHWAYS

Morbi Collapse: A Commoner’s Perspective!

The recently collapsed suspension bridge in Morbi was erected a century back, during the British era, a period that gave us numerous infrastructural edifices that still stands strong in many cases.

After enduring the load of the locals for all these years, the government officials eventually decided to refurbish this bridge and in March 2022 it was closed for renovation.

Well, let’s first understand how a typical suspension bridge structurally functions!

The deck of such types of bridges is held together using vertical suspenders or hangers made from ductile material and is subjected to tension. This deck can bear its own weight along with the weight of a certain number of people walking on it, depending on the enormity and the structural capacity of the bridge.


The suspenders of such bridge types are connected to the main cable which is again ductile and tension-specific. Structurally, the main cable spans between the points connected by the bridge, and is intermediately supported by the vertical main column piers. Ultimately, these cables provide the much-needed strength to the vertical suspenders and allow it to stand vertically strong.

The irony of the Morbi...

  • The bridge was opened to the public five months ahead of its schedule
  • The company that renovated the bridge did not take a fitness certificate from the civic authorities before opening the bridge to the public
  • The company was bound by its contract to keep the bridge shut for at least 8-12 months for maintenance and repairs
  • Being a Diwali Sunday, there was a rush of attractions from tourists. Even though the maximum load-carrying capacity of the bridge was around 125 people, more than thrice amount of visitors were permitted access to the bridge
  • Just before the mishap, some people were supposedly found jumping on the bridge and pulling its big wires. Strangely, some of the old cables of the bridge were not reinstated during the renovation
  • Canvassing commoner’s curiosity...

  • When all the national-level and monumental projects are minutely scrutinized by the authorities at every possible checkpoint, why not projects like the Morbi get the same dedicated concerns?
  • Why human lives associated with relatively small-scale projects like Morbi are not given the same priority?
  • Despite the structural and technical flaws, how did the company get the necessary sanctions to throw the bridge open to the public before the schedule?
  • When every single aspect involving a suspension bridge is supposedly vulnerable, why the materials used for renovating the bridge were not thoroughly audited by the inspection authorities?
  • Without any official fitness certification derived from the local civic authorities how the bridge got an operational go-ahead for the public?
  • When such types of bridges require the most attention in terms of regular checks, why the timely structural audit was not adhered to while the project delivery date was still five months away?
  • CW’s POV...

  • There is a limitless disparity in the processes followed for the national-level projects vis-a-vis significantly small-scale projects in our country
  • The project monitoring of these big-scale projects follows a stringent process at every stage of the project, and surprisingly the same intensity is currently missing in projects like the Morbi
  • Technically, all the aspects including material inspection, structural audit, project sanctions, safety certifications, and so on should have been an integral part of the stringent process that is to be followed for every single project, be it public or private, be it big or small
  • Even though an agreement may hold a private party responsible when dealing with citizen's safety, the SOP must include a third party certification for ensuring safety and adherence
  • Unless a standardisation of process is mandated by the authorities for every single project, with the same fervour all across, we could possibly witness another Morbi
  • While the original structure erected a century ago stood enormously strong and suffered no mishaps, the renovated structure, barely a week old, apparently turned out to become a slayer!

    This appalling episode throws some stern questions to all the stakeholders associated with this project.

    It is estimated that around 50 children, along with several women and the elderly were among the dead. Ironically, the Supreme Court will take up the plea on November 14 which also happens to be Children’s Day.

    Will the commoners’ lives be treated with the same sense of parity?
    Will the administrators show valour in setting the right example?
    Will the lessons be learned after this atrocious incident?

    Perhaps the commoner will just have to wait and watch to get his answers!

    The recently collapsed suspension bridge in Morbi was erected a century back, during the British era, a period that gave us numerous infrastructural edifices that still stands strong in many cases. After enduring the load of the locals for all these years, the government officials eventually decided to refurbish this bridge and in March 2022 it was closed for renovation. Well, let’s first understand how a typical suspension bridge structurally functions! The deck of such types of bridges is held together using vertical suspenders or hangers made from ductile material and is subjected to tension. This deck can bear its own weight along with the weight of a certain number of people walking on it, depending on the enormity and the structural capacity of the bridge. The suspenders of such bridge types are connected to the main cable which is again ductile and tension-specific. Structurally, the main cable spans between the points connected by the bridge, and is intermediately supported by the vertical main column piers. Ultimately, these cables provide the much-needed strength to the vertical suspenders and allow it to stand vertically strong. The irony of the Morbi... The bridge was opened to the public five months ahead of its schedule The company that renovated the bridge did not take a fitness certificate from the civic authorities before opening the bridge to the public The company was bound by its contract to keep the bridge shut for at least 8-12 months for maintenance and repairs Being a Diwali Sunday, there was a rush of attractions from tourists. Even though the maximum load-carrying capacity of the bridge was around 125 people, more than thrice amount of visitors were permitted access to the bridge Just before the mishap, some people were supposedly found jumping on the bridge and pulling its big wires. Strangely, some of the old cables of the bridge were not reinstated during the renovation Canvassing commoner’s curiosity... When all the national-level and monumental projects are minutely scrutinized by the authorities at every possible checkpoint, why not projects like the Morbi get the same dedicated concerns? Why human lives associated with relatively small-scale projects like Morbi are not given the same priority? Despite the structural and technical flaws, how did the company get the necessary sanctions to throw the bridge open to the public before the schedule? When every single aspect involving a suspension bridge is supposedly vulnerable, why the materials used for renovating the bridge were not thoroughly audited by the inspection authorities? Without any official fitness certification derived from the local civic authorities how the bridge got an operational go-ahead for the public? When such types of bridges require the most attention in terms of regular checks, why the timely structural audit was not adhered to while the project delivery date was still five months away? CW’s POV... There is a limitless disparity in the processes followed for the national-level projects vis-a-vis significantly small-scale projects in our country The project monitoring of these big-scale projects follows a stringent process at every stage of the project, and surprisingly the same intensity is currently missing in projects like the Morbi Technically, all the aspects including material inspection, structural audit, project sanctions, safety certifications, and so on should have been an integral part of the stringent process that is to be followed for every single project, be it public or private, be it big or small Even though an agreement may hold a private party responsible when dealing with citizen's safety, the SOP must include a third party certification for ensuring safety and adherence Unless a standardisation of process is mandated by the authorities for every single project, with the same fervour all across, we could possibly witness another Morbi While the original structure erected a century ago stood enormously strong and suffered no mishaps, the renovated structure, barely a week old, apparently turned out to become a slayer! This appalling episode throws some stern questions to all the stakeholders associated with this project. It is estimated that around 50 children, along with several women and the elderly were among the dead. Ironically, the Supreme Court will take up the plea on November 14 which also happens to be Children’s Day. Will the commoners’ lives be treated with the same sense of parity? Will the administrators show valour in setting the right example? Will the lessons be learned after this atrocious incident? Perhaps the commoner will just have to wait and watch to get his answers!

    Related Stories

    Gold Stories

    Next Story
    Infrastructure Transport

    97 Per Cent Of Rongjeng-Mangsang-Adokgre Road Nears Completion

    Deputy Chief Minister in-charge of public works Prestone Tynsong said in Shillong on 26 August that 97 per cent physical progress had been achieved on the ongoing Rongjeng-Mangsang-Adokgre road being constructed under the Non-Lapsable Central Pool of Resources (NLCPR). He noted the project was sanctioned in 2017 and that the stipulated time for completion had been 24 months from issue of the final work order. The deputy chief minister informed the assembly that the government had decided to include the remaining work under a World Bank project. In reply to a query from Rongjeng MLA Jim M Sangm..

    Next Story
    Infrastructure Transport

    First TBM Starts Digging Five Point Three Kilometre Tunnel Under SGNP

    The Goregaon-Mulund Link Road (GMLR) Phase three (B) project has reached a key milestone as the first tunnel boring machine (TBM) began excavation of the first of two tunnels beneath the Sanjay Gandhi National Park (SGNP). The machine, named Tulsi, started cutting a five point three kilometre bore that will link Dadasaheb Phalke Chitranagari in Goregaon East with Amar Nagar in Mulund West. Officials issued a statement noting the commencement of tunnelling work under the protected green belt. The twin tunnels are being constructed using mechanised tunnelling methods that aim to limit surface di..

    Next Story
    Infrastructure Transport

    UP Approves Two Expressways And Rs 240 bn Infrastructure Push

    The Uttar Pradesh Cabinet approved a series of infrastructure and industrial investment proposals totalling Rs 240 billion (Rs 240 bn), including two major expressway projects, a manufacturing and logistics cluster in Sultanpur and incentives for 11 industrial projects across the state. The decisions, taken at a meeting chaired by Chief Minister Yogi Adityanath, underline the state government’s focus on expanding road connectivity around emerging industrial hubs while attracting manufacturing investment to districts beyond major urban centres. The approvals cover both greenfield expressway c..

    Advertisement

    Subscribe to Our Newsletter

    Get daily newsletters around different themes from Construction world.

    STAY CONNECTED

    Advertisement

    SPECIAL OFFER
    QR Code